Which of the following is NOT an input into Plan Resource Management??
Responda
a. Enterprise Environmental Factors
b. Roles and responsibilities
c. Organizational Process Assets
d. Project management plan
Questão 2
Questão
Which of the following is not a tool used in Develop Project Team??
Responda
a. Interpersonal and team skills.
b. Training.
c. Colocation
d. Empowerment.
Questão 3
Questão
The sponsor of a new strategic project ask you for an estimate of the total project budget for the corporate meeting next Friday. You collect some opinions from colleagues and a provider of a similar project developed last year. Which tool are you using?
Responda
a. Analogous estimating
b. Data analysis
c. Project Management Information System
d. Public databases
Questão 4
Questão
Which of the following is NOT a process of Resources Management??
Responda
a. Plan Resource Management.
b. Control Resources
c. Control Project team.
d. Develop Project Team.
Questão 5
Questão
Who manages the resources in a matrix organization??
Responda
a. Senior management
b. Functional managers
c. Project manager
d. Human resources
Questão 6
Questão
Which of the following is not true about a project’s ground rules??
Responda
a. Ground rules should be communicated to all team members.
b. Ground rules should be consistent across projects in an organization.
c. Ground rules should be clearly defined.
d. Ground rules define behavioral boundaries on a project.
Questão 7
Questão
Examples of experts judgment during Plan Resource Management are:
Responda
a. Evaluate the supplier performance.
b. Integrate the team with communication activities
c. Estimating lead times required for acquisition of wood and concrete, based on lesson learned and market conditions
d. Decide to change of a machine because it is non performing.
Questão 8
Questão
Which of the following is NOT true of team building??
Responda
a. Team agreement should be obtained on all major actions.
b. Team building requires role modeling on the part of the project manager.
c. Team building becomes less important as the project progresses.
d. Teamwork cannot be forced.
Questão 9
Questão
Which of the following is not likely a project resource for a software project??
Responda
a. Conference room near the team location
b. Project Manager
c. Maintenance operator
d. Computer programmer
Questão 10
Questão
Which of the following techniques produces the most lasting results??
Responda
a. Problem solve
b. Smooth
c. Compromise
d. Withdraw