Tie 1

Descrição

Tie 1
Enrique Gomez
Quiz por Enrique Gomez, atualizado more than 1 year ago
Enrique Gomez
Criado por Enrique Gomez mais de 5 anos atrás
4
0

Resumo de Recurso

Questão 1

Questão
Crashing differs from fast tracking because crashing:
Responda
  • a. Usually increases value.
  • b. Usually increases the cost.
  • c. Usually saves more time
  • d. Usually saves more money.

Questão 2

Questão
Crashing in time management is:
Responda
  • a. A schedule compression technique includes reducing schedule activity durations and increasing the assignment of resources to schedule activities.
  • b. A schedule compression technique in which phases or activities that normally would be done in sequence are performed in parallel.
  • c. The timely input of data to calculate the critical path.
  • d. Equivalent to minimizing float.

Questão 3

Questão
Bar charts are useful in determining:?
Responda
  • a. The level of effort of an activity.
  • b. Activity start and end dates, as well as expected durations.
  • c. Availability of resources assigned to perform an activity.
  • d. Relative priority of activities.

Questão 4

Questão
An example of a “soft logic” dependency, is:?
Responda
  • a. Project A, the company’s participation in a Industry trade show, depends on the successful completion of Project B, which is building the prototype of the product that is going to be displayed.
  • b. To install the plumbing and electrical work at the same time family is living in a house.
  • c. Finished software before training program.
  • d. To schedule the final testing activity of a computer before the manual is finish.

Questão 5

Questão
Analogous duration estimating is:?
Responda
  • a. Bottom-up estimating.
  • b. Frequently used to estimate project duration when there is a limited amount of detailed information.
  • c. Similar to multiple duration estimating.
  • d. Deductive estimating.

Questão 6

Questão
All of the following are true about resource leveling EXCEPT:?
Responda
  • a. Can be used to keep selected resource usage at a constant level during specific time periods.
  • b. Offer results in a projected duration for the project that is longer than the preliminary project schedule.
  • c. Is sometimes called the resource-based method.
  • d. Is used to develop a meaningful WBS.

Questão 7

Questão
An organization uses a desktop scheduling software for project scheduling. What would this software be considered as??
Responda
  • a. Project management office.
  • b. Enterprise environmental factor.
  • c. Organizational process asset.
  • d. Integrated change control system.

Questão 8

Questão
All of the following choices represent inputs to the Estimate Activity Resources EXCEPT:?
Responda
  • a. Organizational process assets.
  • b. Activity cost estimates.
  • c. The actual final cost of the last project.
  • d. Risk register

Questão 9

Questão
As one of the tools and techniques of Sequence Activities, a lead:?
Responda
  • a. Directs a delay in the successor activity.
  • b. Could be accomplished by a finish-to-start relationship with a delay time.
  • c. Means the successor activity cannot start until after the predecessor is completed.
  • d. Allows an acceleration of the successor activity.

Questão 10

Questão
A schedule compression technique to determine how to obtain the greatest amount of compression for the least incremental cost is called:?
Responda
  • a. Crashing.
  • b. PERT.
  • c. Precedence Diagram Method - PDM.
  • d. Fast tracking.

Semelhante

Novo Acordo Ortográfico - Uso do Hífen
Alessandra S.
Direito Civil - Personalidade Jurídica
Lucas Ávila
Inglês resumo
Felipe Penha
QUESTIONÁRIO DE INFORMÁTICA: SISTEMAS OPERACIONAIS
anapaulabrasilam
Phrasal Verbs - Inglês #3
Eduardo .
Português 1 - Sintaxe: Frase, Oração e Período
wallace.da
Hereditariedade
Nicanor H. Iba
O que estudar para a OAB
GoConqr suporte .
Fotossíntese
GoConqr suporte .
TCC - ELABORAÇÃO DE PARÁGRAFOS
dtybel
Regra de Sinais
Adenilson Santana