Crashing differs from fast tracking because crashing:
Responda
a. Usually increases value.
b. Usually increases the cost.
c. Usually saves more time
d. Usually saves more money.
Questão 2
Questão
Crashing in time management is:
Responda
a. A schedule compression technique includes reducing schedule activity durations and increasing the assignment of resources to schedule activities.
b. A schedule compression technique in which phases or activities that normally would be done in sequence are performed in parallel.
c. The timely input of data to calculate the critical path.
d. Equivalent to minimizing float.
Questão 3
Questão
Bar charts are useful in determining:?
Responda
a. The level of effort of an activity.
b. Activity start and end dates, as well as expected durations.
c. Availability of resources assigned to perform an activity.
d. Relative priority of activities.
Questão 4
Questão
An example of a “soft logic” dependency, is:?
Responda
a. Project A, the company’s participation in a Industry trade show, depends on the successful completion of Project B, which is building the prototype of the product that is going to be displayed.
b. To install the plumbing and electrical work at the same time family is living in a house.
c. Finished software before training program.
d. To schedule the final testing activity of a computer before the manual is finish.
Questão 5
Questão
Analogous duration estimating is:?
Responda
a. Bottom-up estimating.
b. Frequently used to estimate project duration when there is a limited amount of detailed information.
c. Similar to multiple duration estimating.
d. Deductive estimating.
Questão 6
Questão
All of the following are true about resource leveling EXCEPT:?
Responda
a. Can be used to keep selected resource usage at a constant level during specific time periods.
b. Offer results in a projected duration for the project that is longer than the preliminary project schedule.
c. Is sometimes called the resource-based method.
d. Is used to develop a meaningful WBS.
Questão 7
Questão
An organization uses a desktop scheduling software for project scheduling. What would this software be considered as??
Responda
a. Project management office.
b. Enterprise environmental factor.
c. Organizational process asset.
d. Integrated change control system.
Questão 8
Questão
All of the following choices represent inputs to the Estimate Activity Resources EXCEPT:?
Responda
a. Organizational process assets.
b. Activity cost estimates.
c. The actual final cost of the last project.
d. Risk register
Questão 9
Questão
As one of the tools and techniques of Sequence Activities, a lead:?
Responda
a. Directs a delay in the successor activity.
b. Could be accomplished by a finish-to-start relationship with a delay time.
c. Means the successor activity cannot start until after the predecessor is completed.
d. Allows an acceleration of the successor activity.
Questão 10
Questão
A schedule compression technique to determine how to obtain the greatest amount of compression for the least incremental cost is called:?
Responda
a. Crashing.
b. PERT.
c. Precedence Diagram Method - PDM.
d. Fast tracking.
Quer criar seus próprios Quizzesgratuitos com a GoConqr? Saiba mais.