Questão 1
Questão
In which process is the initiation of the project authorised?
Questão 2
Questão
When does the process of Directing a Projectformally begin?
Responda
-
Before Starting up a Project
-
After Starting up a Project
-
After Initiating a Project
-
After Managing a Stage Boundary
Questão 3
Questão
Which of the following products is NOT reviewed by the Project Board when authorising project closure?
Questão 4
Questão
Which role recommends the project closure?
Responda
-
The Executive
-
The Senior User
-
The Senior Supplier
-
The Project Manager
Questão 5
Questão
Which management product is provided to the Project Board with a request to authorise initiation?
Questão 6
Questão
What is the purpose of an Exception Report?
Responda
-
Where there is a forecast to exceed tolerance, it is prepared to inform the Project board of the situation.
-
It provides the Project Board with a summary of stage staus at intervals defined by them.
-
It contains the description, impact assessment and recommendations for a request for change or off-specification.
-
When there is a forecast to exceed tolerance, it replaces the plan which is no longer valid.
Questão 7
Questão
How often is the Managing Stage Boundary process invoked?
Responda
-
At the end of the Starting Up a Project process.
-
At the end of each project.
-
At the end of each stage, except the final one.
-
At the end of each Work Package.
Questão 8
Questão
Who needs the information gathered in Managing a Stage Boundary to assess the continuing viability of a project?
Questão 9
Questão
Which of the following plans listed below is NOT produced or updated in the Managing a Stage Boundary process?
Responda
-
Exception Plan
-
Next Stage Plan
-
Team Plan
-
Project Plan
Questão 10
Questão
The Project Board may request that the current stage is replanned, and the output from replanning is... which is submitted for Project Board approval?
Responda
-
a Stage Plan
-
a Project Plan
-
a Team Plan
-
an Exception Plan
Questão 11
Questão
What is a purpose of the Closing a Project process?
Responda
-
Enable the Project Manager to review whether the project has anything further to contribute.
-
Enable the Project Board to make the decision about whether or not to close the project.
-
Enable the Project Manager to manage the final delivery report.
-
Enable the delivery team to create the specialist products of the final stage.
Questão 12
Questão
How might the Project Manager use the Project Plan during the Closing a Project process?
Responda
-
To update with actuals from the final stage.
-
To update with forecasts for the final stage.
-
To plan the work to review the post-project benefits.
-
To control and monitor the work of the final stage.
Questão 13
Questão
Which of the following statements represents how the Closing a Project process helps to implement the Risk theme?
Responda
-
Describes the activity where the procedure for managing threats for the project is defined.
-
Describes the activity where ongoing opportunities for the project's products are passed on to the operational and maintenance teams.
-
Describes the activity where the delivery team report risks to the Project Manager
-
Describes the activity where risks are captured in the Risk Register.