PRINCE 2 (Lecture 5)- Starting Up a Project (SU) / Initiating a Project (IP)

Descrição

Quiz sobre PRINCE 2 (Lecture 5)- Starting Up a Project (SU) / Initiating a Project (IP), criado por Natalie Hallam em 23-02-2015.
Natalie Hallam
Quiz por Natalie Hallam, atualizado more than 1 year ago
Natalie Hallam
Criado por Natalie Hallam mais de 9 anos atrás
96
1

Resumo de Recurso

Questão 1

Questão
Which is NOT an objective of the Initiating a project process?
Responda
  • Ensure there is a common understanding of who will take significant project management roles within the project.
  • Ensure there is a common understanding of how and when the project's products will be achieved and at what cost.
  • Ensure there is a common understanding of the reasons for doing the project, the benefits expected and the associated risks.

Questão 2

Questão
Which of the following is NOT a PRINCE2 management product?
Responda
  • Risk Management Strategy
  • Configuration Management Strategy
  • Communication Management Strategy
  • Cost Management Strategy

Questão 3

Questão
The Business Case will contain a summary of key risks, where will the details of all the risks be stored?
Responda
  • Issues Register.
  • Configuration Item Records
  • Risk Management Strategy
  • Risk Register

Questão 4

Questão
Which of the following is defined as part of setting up controls for the project?
Responda
  • Tolerances for delegated authority.
  • Quality management procedure.
  • Tools and techiques for managing risks
  • How information from outside of the project environment will be sent or received.

Questão 5

Questão
Information on project controls is included in which management product?
Responda
  • Project Brief
  • Business Case
  • Stage Quality Plan
  • Project Initiation Documentation

Questão 6

Questão
The Outline Business Case is prepared as part of which process?
Responda
  • Controlling a Stage
  • Starting up a Project
  • Initiating a Project
  • Directing a Project

Questão 7

Questão
The information gathered in the Starting Up a Project process should answer what basic uestions?
Responda
  • Do we have a viable and worthwhile project?
  • Do we know who thought of this idea?
  • Do we care about the outcome at this stage?
  • Do we solve the problem now or later?

Questão 8

Questão
What management product produced in Starting Up a Project is submitted to the Project Board with a request to initiate a Project?
Responda
  • Project Brief
  • Refined Business Case
  • Project Initiation Document (PID)
  • Project Plan

Questão 9

Questão
How does the Starting up a Project process support the defined roles and responsibilities principle?
Responda
  • By nominating the project manager responsible for project assurance.
  • By appointing the executive, the project manager and the project management team.
  • It doesn't.
  • By ensuring lessons from previous projects are captured and analyzed.

Questão 10

Questão
Who is responsible for creating the Initiation Stage Plan?
Responda
  • Project Manager
  • Project Board
  • Team Manager
  • Project Assurance

Semelhante

Paulo Freire Pedagogia da Autonomia
lb.roberto
Quiz Sobre Genética
Marerodrigues
LICITAÇÕES
roberta.dams
Nihongo Kanji PT BR
Allan Carlos
METODOLOGIA E PRÁTICA DE ALFABETIZAÇÃO E LETRAMENTO
vanessasenez
Glossário de Biologia
GoConqr suporte .
DOENÇA MENTAL E TRATAMENTO -Texto 16
eleuterapara
Músculos e ossos - Nível fácil
Daniel Pereira
Anatomia: sistema esquelético I
Natália Abitbol
Conteúdo de Português - 6° ano
biallima6
Sistema Nervoso
Simone Machado Pereira