EVM Quiz
Este quiz tem tempo limite, por isso abre no player de sempre.
Perguntas do quiz (10)
1BAC=300; PV=200;AC=220;EV=100
If the future work is assumed to be performed at an efficiency rate that considers both the cost and schedule performance indices what is the EAC (Estimate At Completion).- A660
- B500
- C745
- D1109
2BAC=300; PV=200;AC=220;EV=100.
If you future work is assumed that it will be similar to current variance , the VAC (variance At Ccompletion) is.- A-300
- B-360
- C+360
- D+445
3In a project, Earned Value is half of the Planned Value. Actual cost is double the Planned Value. Comment on the cost and schedule performance of the project.
- Aon schedule, on cost
- Bahead of schedule, under cost
- Cbehind schedule, over cost
- Dbehind schedule, on cost
4You are a Project manager for a road construction project to lay a road of length 20km.
The budget for 1km road is $4000. half way down 10km road has been laid but the actual cost is $60,000.
Assuming the current variance will continue in the future what is the Estimate At Completion(EAC)?- A$120,000
- B$100,000
- C$40,000
- D$60,000
5A project's PV,EV and AC values are shown in this picture. What is the cost and schedule performance of the project?

- Abehind schedule, over cost
- Bbehind schedule, on cost
- Con schedule, on cost
- Dahead of schedule, under cost
6A project's estimated VAC = -$10,000. The BAC of the project = $50,000 and the ETC pending works = $15,000. What is AC till date?
- A$25,000
- B$45,000
- C$40,000
- D$35,000
7In your project, currently there are variances, which are not expected to occur in the future. What is the EAC of your project? BAC = $400,000; AC = $250,000; EV = $200,000; CPI = 1.25
- A$320,000
- B$750,000
- C$450,000
- D$600,000
8CPI = 1.5, SPI = 0.8
What about the cost and schedule performance of the project?- Aon schedule, on cost
- Bbehind schedule, over cost
- Cbehind schedule, under cost
- Dahead of schedule, on cost
9SV = 4000 and CV = 0.
What is the cost and schedule performance of the project?- Aahead of schedule, under cost
- Bbehind schedule, on cost
- Cahead of schedule, over cost
- Dahead of schedule, on cost
10In a project , PV > EV and AC > EV.
Which of the following is true?.- ACost performance alone is good
- BSchedule performance alone is not good
- CBoth cost and schedule performance are good
- DBoth cost and schedule performance are not good
Informações
- Descrição
- this is a sample test quiz
- Autor
- venkatram_vasi
- Idioma
- English
- Visualizações
- 695
- Etiquetas
- Avaliação
- Ainda sem avaliações Avalie este quiz