The process of developing a detailed project scope statement as the basis for future project decisions is known as:
Responda
  • A Create WBS.
  • B Plan Scope.
  • C Define Scope.
  • D Control Scope.

Questão 2

Questão
Configuration management activities for requirements are most likely specified in which of the following?
Responda
  • A Requirements management plan
  • B Requirements documentation
  • C Quality management plan
  • D Requirements traceability matrix

Questão 3

Questão
Inspection is a technique that includes:
Responda
  • A Identifying early and late start dates, as well as early and late finish dates, for the uncompleted portions of project schedule activities
  • Directing, managing, performing and accomplishing the project work, providing the deliverables and providing work performance information.
  • C Examining or measuring to determine whether an activity, component, product, result, or service conforms to specified requirements.
  • D The assurance that a product, service, or system meets the needs of the customer and other identified stakeholders.

Questão 4

Questão
Question 4 of 20 (Scope) Go to Question: Which of the following is NOT a component of the scope baseline?
Responda
  • A WBS dictionary
  • B Project scope statement
  • C WBS
  • D Change requests

Questão 5

Questão
All of the following can be outputs of Control Scope EXCEPT:
Responda
  • A Organizational process assets updates.
  • B Change requests.
  • C Work performance data.
  • D Scope baseline updates.

Questão 6

Questão
All of the following are inputs to the Create WBS process EXCEPT:
Responda
  • A Work breakdown structure.
  • B Project scope statement.
  • C Requirements documentation.
  • D Organizational process assets.

Questão 7

Questão
You have just signed on with a pharmaceutical company as a new employee. As the project manager for a new project, you learn that project charters are not used in your new company. You discuss this with your boss and inform her that in your former company, you always had a project charter for every new project. She suggests that you and the project team gather comparable information that can then be used to develop the detailed ________________.
Responda
  • A Work breakdown structure
  • B Project scope statement
  • C Project plan
  • D Project cost estimate

Questão 8

Questão
You are the project manager responsible for your company's most expensive R&D project. The current SPI for your project is 1.06, and the current CPI for your project is 1.05. Your boss enters your office and informs you that the executive governance committee has decided to terminate your project due to recent market changes. You are surprised, but understand the importance of the business decision. During this conversation, your boss requests that you to set up a meeting with your contracted vendor to agree upon and document all of the work that has been completed up to this point. Your boss has just asked you to conduct _______________. A Validate Scope. B Define Scope. C Conflict resolution. D Contract administration. Explanation: The scope has already been defined, so Choice B is not correct. Choice C is not the best option since no conflict is suggested in the question. Choice D, contract administration, is not a PMBOK® process. If the project is terminated early, the Validate Scope process should be used to determine accepted deliverables and make updates to project documents. Choice A is the correct answer. PMBOK® 5.5, pgs 133-134
Responda
  • A Validate Scope.
  • B Define Scope.
  • C Conflict resolution.
  • D Contract administration.

Questão 9

Questão
An output of Collect Requirements is:
Responda
  • A Work breakdown structure.
  • B Project management plan.
  • C Project scope statement.
  • D Requirements traceability matrix.

Questão 10

Questão
You are the project manager for a 400 million dollar project. You and your team have just completed a product analysis. The NEXT step is to:
Responda
  • A Request the project charter from senior management.
  • B Write the project scope statement.
  • C Create the scope baseline.
  • D Request formal acceptance from the buyer

Questão 11

Questão
In order to generate a WBS for a new project, it would be helpful to:
Responda
  • A Know the project's cost baseline.
  • B Review the variance analysis.
  • C Start with a work breakdown structure template.
  • D Use a reputable project management software product and then publish the final result for the team members to receive their assignments.

Questão 12

Questão
An output of Control Scope is:
Responda
  • A Accepted deliverables.
  • B Project charter.
  • C Project management plan updates.
  • D Project scope statement.

Questão 13

Questão
The development of requirements begins with an analysis of information contained in the:
Responda
  • A Project charter and stakeholder register.
  • B Project management plan and requirements traceability matrix.
  • C Project charter and organizational process assets.
  • D Project management plan and change requests.

Questão 14

Questão
In Project Scope Management, which tool or technique could be used with both Collect Requirements and Define Scope?
Responda
  • A Alternatives identification
  • B Interviews
  • C Group creativity techniques
  • D Facilitated workshops

Questão 15

Questão
Which of the following is NOT an input to Define Scope?
Responda
  • A WBS dictionary
  • B Requirements documentation
  • C Project charter
  • D Organizational process assets

Questão 16

Questão
Which of the following CANNOT be an output of Control Scope?
Responda
  • A Lessons learned
  • B WBS updates
  • C Variance analysis
  • D Scope variances and causes

Questão 17

Questão
An input to Validate Scope is:
Responda
  • A Define Scope.
  • B Inspection.
  • C Requirements traceability matrix.
  • D Accepted deliverables.

Questão 18

Questão
What is the BEST Collect Requirements tool or technique to use to obtain requirements from product users that have difficulty or are reluctant to articulate their requirements?
Responda
  • A Brainstorming
  • B Questionnaires and surveys
  • C Focus groups
  • D Observations

Questão 19

Questão
All of the following are NOT examples of a project requirement classification EXCEPT:
Responda
  • A Pareto chart.
  • B Relationship with the seller.
  • C Business requirements, transition requirements, project requirements.
  • D Funding limitation.

Questão 20

Questão
Your team needs to verify that the deliverables being produced and accepted are included in the approved project scope. Which of the following will be MOST helpful?
Responda
  • A Work breakdown structure dictionary
  • B Risk register
  • C Project scope statement
  • D Scope baseline

Semelhante

Geologia 10ºANO
catarinacusca
Mapa da prova da OAB 1a Fase-Distribuição de Questões
Treinador OAB
Phrasal Verbs - Inglês #10
Eduardo .
Equações estatísticas
Luiz Fernando
Vestibular - Roteiro de Estudos
GoConqr suporte .
Dir. Constitucional - Classificação das Constituições
Lucas Ávila
Sistema Endócrino
Gabriel Paes
Guia - 2ª Fase do Exame da Ordem
Alice Sousa
Por que 8 de março é o Dia Internacional da Mulher?
GoConqr suporte .
Tabela Periódica
Fael Berranteiro
Questões Estatuto dos Militares lei n°. 6.880
Alan Amanthea