Questão 1

Questão
Construction companies internationally including Singapore are using BIM extensively, not only during design phase but also construction phase
Responda
  • True
  • False

Questão 2

Questão
Companies are reaping the benefit of low hanging fruits - BIM 3D, and are embracing and adopting 4D and 5D BIM now
Responda
  • True
  • False

Questão 3

Questão
Following are applications of BIM in construction planning
Responda
  • Site utilisation
  • safety planning
  • logistics
  • materials planning and management
  • identify time-based clashes
  • Virtual Mock-ups

Questão 4

Questão
BIM 4D = 3D + [blank_start]?[blank_end]
Responda
  • Time

Questão 5

Questão
Benefits of doing BIM 4D:
Responda
  • Improved site use planning and coordination
  • Improved constructability and safety issue identification
  • Greatly improve ability to monitor actual progress vs. planned progress and to identify and resolve issues more quickly, thereby reducing claims
  • Enhanced visualization and better communication of work through actual simulation
  • To ensure buildings are designed to be sustainable

Semelhante

Revisão Para o ENEM em 20 dias
Alessandra S.
PROCESSOS DE FORMAÇÃO DAS PALAVRAS - Morfologia
Viviana Veloso
Tipos de sujeito
Roberta Souza
Citologia
rcminitori
Aprenda português brincando
Luís Fernando Olivei
Guia de Estudos para o ENEM
GoConqr suporte .
Glossário de Direito Empresarial
Daniella Paulino
Músculos e ossos - Nível fácil
Daniel Pereira
Resumo para o exame nacional - Fernando Pessoa Ortónimo, Alberto Caeiro , Ricardo Reis e Álvaro Campos
marisacampos.ave
SIMULADO 2 - CTFL - AT
Jorge Ricardo
Organização Administrativa
Arthur Souza