Question 1
Question
John is the Product Owner, during the Daily he realized that the work is delayed. What should he do?
Answer
-
Nothing
-
Notify the CEO
-
Negotiate a reduction of the scope, guiding the team to focus on the goal
-
Cancel the sprint and change the team of developers
Question 2
Question
Frank is the Scrum Master and decided to cancel the Sprint. What should be the PO response?
Question 3
Question
Peter is a developer, tested in the user story and noticed a problem. Which action should Peter
Question 4
Question
Is Product owner and Scrum master possible in the same person for the same project?
Question 5
Question
According to the Scrum guide, can we use parts of Scrum?
Question 6
Question
Can we change the size of the sprint during its execution?
Question 7
Question
The best scenario for using Scrum is?
Question 8
Question
The maximum length of the Sprint Retrospective(its time box) is:
Answer
-
3 hours for a monthly Sprint, proportionally less for shorter Sprints
-
4 hours for a monthly Sprint, proportionally less for shorter Sprints
-
As long as needed
-
1 day
Question 9
Question
How many meetings are defined in Scrum?
Question 10
Question
What is the purpose of the daily meeting?
Answer
-
Team meeting for inspection and adaptation
-
A formality of Scrum
-
To inform the Product Owner
-
None of the given answers
Question 11
Question
When does the development team create the sprint backlog?
Answer
-
daily
-
planning
-
review
-
retrospective
Question 12
Question
At the end of the sprint is a product increment that will go into production?
Question 13
Question
After the start of the sprint, what product owner will do?
Question 14
Question
Is it true that the Scrum Master is responsible for the ROI of the product?
Question 15
Question
What is the role of the project manager in the Scrum framework?
Question 16
Question
When to cancel a sprint?
Question 17
Question
Scrum master ensures that Scrum is being applied correctly?
Question 18
Question
How does the product owner help the development team?
Answer
-
Detailed all product backlog
-
Clearing up doubts about backlog items
-
With the help of requirements analyst
-
He does not help the team.
Question 19
Question
When a backlog item was set to high priority, for what situation should it be considered?
Answer
-
Definition of done
-
Definition of Timebox
-
Definition of ready
-
None of the answers
Question 20
Question
Does the development team need to be multifunctional?