Question 1
Question
The reason the Scrum Master is at the Daily Scrum is:
Answer
-
To make sure everyone answers the three questions in order of seniority
-
He or she does not have to be there; he or she only has to ensure the Team has a Daily Scrum
-
To write down any changes to the Sprint Backlog, including adding new items, and tracking progress on the burndown.
-
So he or she knows what to report to management
Question 2
Question
The timebox for a Daily Scrum is?
Question 3
Question
Since no new work can be added to a Sprint, what is the appropriate characteristic of the Sprint Backlog during the Sprint?
Answer
-
The Sprint backlog never changes.
-
The Sprint Backlog can only change with the approval of the Product Owner.
-
The Sprint Backlog is defined based on the work necessary to build the selected Product Backlog items.
-
The Sprint Backlog is created during the Sprint Planning meeting and should not need to be changed afterward
Question 4
Question
An organization has decided to adopt Scrum, but management want to change the terminology to fit with terminology already used. What will likely happen if they do so?
Answer
-
Without a new vocabulary as a reminder of the change, very little change may actually happen.
-
The organization may not understand what has changed within Scrum and the benefits of Scrum may be lost.
-
Management may feel more anxious.
-
All answers apply.
Question 5
Question
Is Sprint a PDCA Cycle?
Question 6
Question
Frank is the Scrum Master and decided to cancel the Sprint. What should be the PO response?
Question 7
Question
What event does development team present the work and receives feedback(product)?
Answer
-
Planning
-
Daily
-
Review
-
Retro
Question 8
Question
The product owner can not participate in the planning, what should we do?
Question 9
Question
) HOW CAN PRODUCT OWNER HELP TIME DELIVER VALUE ON EACH SPRINT?
Question 10
Question
Your product does not have a product owner, what would be the criteria you would use to choose?
Question 11
Question
During the review the Product Owner rejected two user stories. Should we increase the size of the current sprint?
Question 12
Question
When should a sprint be canceled?
Answer
-
when the goal does not make any sense
-
when the deadline is insufficient
-
when the staff asks for the cancellation
-
All
Question 13
Question
What is planning poker?
Question 14
Question
What is not part of the product backlog?
Answer
-
administrative tasks
-
meetings
-
detailed tasks
-
All
Question 15
Question
What best defines the role of Scrum Master?
Answer
-
auditor
-
manager
-
Project manager
-
facilitator
Question 16
Question
What main activity should the product owner perform in a Scrum team?
Question 17
Question
What is the purpose of product backlog refinement?
Question 18
Question
After identifying that a user story does not have enough details to enter the next sprint, what should the product owner do?
Answer
-
inserts the story anyway
-
Do not insert the story.
-
cancel sprint
-
All
Question 19
Question
During the sprint, a dev team member has a question. When requesting help from the product owner, you receive the following response: "I am not available". How can Scrum Master help?
Answer
-
Scrum Master can not help
-
the Scrum Master explains to the product owner that he needs to clarify the doubts of the team, and helps the product owner find the time.
-
The Scrum Master says that the doubt is not important
-
none of the answers
Question 20
Question
During the retrospective, what is the role of the product owner?
Question 21
Question
The product backlog needs to be fully detailed?
Question 22
Question
During planning is the sprint backlog fully identified?
Question 23
Question
The product owner did not detail the items for the next sprint, can we start this way?
Question 24
Question
How can Scrum Master help the product owner?
Question 25
Question
What does not happen in part 1 of the planning?
Question 26
Question
In a one-month sprint, what is the Daily timebox?
Answer
-
15 minutes
-
30 minutes
-
60 minutes
-
45 minutes
Question 27
Question
When does the daily end?
Question 28
Question
Why cancel a sprint?
Question 29
Question
Can the Product Owner question an estimate of the Dev Team?
Question 30
Question
Can the Sprint backlog be changed by the product owner at what time?
Answer
-
When the product owner needs it, he must inform the team and negotiate the new item
-
Can not change
-
Can only be changed in case of cancellation
-
Scrum Master must authorize