PMP Midterm 2 Third 20 Q

Description

Third 20 Q
abdulaziz zaid
Quiz by abdulaziz zaid, updated more than 1 year ago
abdulaziz zaid
Created by abdulaziz zaid almost 7 years ago
264
4

Resource summary

Question 1

Question
You are negotiating a contract with a seller. You want to go in for a Fixed price type of contract. The seller uses a different terminology for the fixed price type of contract. He is most probably referring to it as a:
Answer
  • Cost-Plus-Fixed-Fee contract
  • A Time and material contract
  • Lump sum contract
  • Cost-Plus-Fee contract

Question 2

Question
Product scope is measured against the product requirements whereas project scope is measured against:
Answer
  • The WBS and WBS dictionary
  • The project scope statement and its associated WBS and WBS dictionary
  • The project requirements and WBS.
  • The acceptance criteria

Question 3

Question
A first-time project manager created a Work Breakdown Structure (WBS) where the deliverables had different levels of decomposition. What would your comment on this be?
Answer
  • This is incorrect. All deliverables need to have the same level of decomposition.
  • This is incorrect. Only deliverables under different branches can have different levels of decomposition.
  • This is fine. Different deliverables can have different levels of decomposition depending on the work involved.
  • This is fine. The focus of the WBS is not the deliverables, but the tasks involved.

Question 4

Question
On obtaining the project charter, the Project Manager of a project immediately starts acquiring the project team. Is this correct?
Answer
  • Yes. Acquisition of the project team is primarily an Initiating Process Group activity.
  • Yes. The project manager needs to get the team together as soon as the project starts.
  • No. It is the responsibility of the project sponsor to provide the team for execution.
  • No. Acquisition of the project team is primarily an Executing Process Group activity.

Question 5

Question
A project manager in a seller organization discovered that certain deliverables had been handed over to the buyer without undergoing proper testing. Recalling the deliverables will result in a cost overrun to the project. What should the project manager do in such a case?
Answer
  • Recall the deliverables even though there will be a cost overrun.
  • Terminate the project.
  • Approach management to obtain additional funding to handle the potential cost overrun.
  • Wait for the procuring organization to get back with their list of defects in the deliverables.

Question 6

Question
Jane is managing a project in a Functional organization. In this organization, she can expect to find that:
Answer
  • She wields considerable authority and can make independent decisions related to the project.
  • Management systems are designed to support projects and project management is easy.
  • Management systems are not designed to support project needs efficiently, and project management is difficult.
  • There are no barriers to communication between cross-functional teams. She is able to easily reach out to other teams without needing to go through the Functional manager.

Question 7

Question
A measure taken to bring future results in line with the project plan BEST describes?
Answer
  • Change request
  • Preventive action
  • Corrective action
  • Defect repair

Question 8

Question
A first-time project manager was assigned to a project that had a duration of 3 months. In order to gain a head start in the project, she took an older, completed project and incorporated all the tools, techniques and checklists from that project in their entirety into the current one. The older project had been completed in 14 months’ time and was very similar in nature. The most appropriate comment on this would be:
Answer
  • This is an excellent example of reuse of artifacts from prior projects.
  • This may be unnecessary. The project management team needs to decide what is appropriate for the project.
  • This is not the correct procedure. The project manager should always create processes and documents afresh for new projects.
  • This is not correct. The project manager is violating copyright and intellectual property rights of the organization’s prior customers.

Question 9

Question
Your project team has recently identified a risk in the software development project and decided not to change the project management plan to deal with the risk. The risk response strategy your team used in this scenario is an example of:
Answer
  • Mitigate
  • Transfer
  • Avoid
  • Acceptance

Question 10

Question
Which of the following should you NOT use as an input into creating the WBS structure?
Answer
  • Bill of Material (BOM)
  • Project scope statement
  • Organizational process assets
  • Requirements documentation

Question 11

Question
You have just completed the first phase of a multi-phase project. You have performed the earned value measurements and found out that the current CPI is 0.79, the current SPI is 0.98. Your next phase plan should focus first on which element of the project?
Answer
  • Quality
  • Resources
  • Schedule
  • Cost

Question 12

Question
A detailed milestone list is created as an output of what process?
Answer
  • Sequence Activities
  • Define Activities
  • Develop Project Charter
  • Develop Schedule

Question 13

Question
Which of the following is not a general management technique used to generate different approaches to execute and perform the project work?
Answer
  • Lateral thinking
  • Analysis of alternatives
  • Map Out
  • Brainstorming

Question 14

Question
You have been assigned as project manager of a software development project. One of the requirements is to use a remote team and you find that that the remote team has limited technical communications capabilities. This is an example of:
Answer
  • An assumption
  • A hindrance
  • A show-stopper
  • A constraint

Question 15

Question
Breaking down project activities into smaller components in order to obtain a more accurate cost estimate is called:
Answer
  • Work breakdown structure
  • Analogous estimating
  • Decomposition
  • Bottom-up estimating

Question 16

Question
Most project management software packages use a method of constructing a project schedule network diagram known as:
Answer
  • Activity Diagramming Method
  • Precedence Diagramming Method
  • Project Diagramming Method
  • Critical Diagramming Method

Question 17

Question
A project manager included contingency reserves and management reserves in the total budget of a high-risk project. He also made certain earned value measurement calculations. Which of the following is incorrect?
Answer
  • Contingency reserves are not part of the project cost baseline.
  • Management reserves are not part of the project cost baseline.
  • The project manager needs to get approval before spending management reserve.
  • Reserves are usually included in the total budget of a project

Question 18

Question
Alan is managing a software development project. The buyer of the product is an external entity. During the execution of the project, Alan finds out that a new operations manager has been hired in the customer organization. The new manager is now a key stakeholder of the project. Which of the following documents is least likely to get updated as a result of the addition of this new stakeholder?
Answer
  • Stakeholder register
  • Risk register
  • Stakeholder management plan
  • Issue log

Question 19

Question
Your manager is presenting a status report of all projects being run in his division. He reports that all projects are showing a positive CV. However, you know that your status reports for the last several weeks have been reporting a negative CV. What do you do?
Answer
  • Do nothing.
  • Offer to review all your manager’s combined status reports before he presents them.
  • Notify the appropriate management immediately.
  • Ask your manager if that information was simply a typographical error.

Question 20

Question
As part of a strategy to handle negative risk, a project manager decided to adopt less complex processes, conduct more tests and choose a more stable supplier. What strategy would this be classified as?
Answer
  • Acceptance
  • Transference
  • Mitigation
  • Avoidance
Show full summary Hide full summary

Similar

Spanish Questions
Niat Habtemariam
Frankenstein by Mary Shelley
nina.stuer14
TOEFL English Vocab (A - M)
Ali Kane
NEW: ExamTime's Mind Map Maker
Andrea Leyden
AQA - English Language Unit 1
Alice Love
Unit 1: Business Studies GCSE
Libby Rose
Mind Maps with GoConqr
Elysa Din
Continents & Oceans
Thomas Yoachim
Periodic table - full deck of element symbols
Derek Cumberbatch
GCSE AQA Physics 2 Circuits
Lilac Potato
Diseño de Software
Verny Fernandez