Question 1
Question
The unique ways in which organizations coordinate and organize work activities, information and knowledge to produce a product or service.
Answer
-
Estimate
-
Business Processes
-
Quality
Question 2
Question
The totality of features and characteristics of a product or service that bear on its ability to satisfy stated or implied needs.
Answer
-
Quality
-
Business Processes
-
Estimate
Question 3
Question
What does QA acronym stand for?
Answer
-
Quest Assurance
-
Quality Acronym
-
Quality Assurance
-
Quality Assistant
Question 4
Question
What does DDD acronym stand for?
Question 5
Question
SRS acronym is stand for Software Requirements Specification
Question 6
Question
A temporary endeavor undertaken to create a unique product, service, or result.
Answer
-
Project
-
Functional testing
-
Kickoff process
Question 7
Question
Process that focuses on the outputs generated in response to selected inputs and execution conditions.
Answer
-
Project
-
Functional testing
-
Kickoff process
Question 8
Question
Review the output of the previous stage, go over any additional inputs required by thet particular stage, examine the anticipated activities and required outputs of the current stage.
Answer
-
Kickoff process
-
Functional testing
-
Project
Question 9
Question
What does WBS acronym stand for?
Answer
-
Well Breakdown Structure
-
Work Breakdown Simple
-
Work Breakdown Structure
-
Work Breakdown Stage
Question 10
Question
Which sequence of tasks is adequate for Risk Management
Answer
-
Identify, Plan, Classify, Monitor, Mitigate, Communicate
-
Identify, Communicate, Classify, Plan, Monitor, Mitigate
-
Identify, Classify, Plan, Monitor, Mitigate, Communicate
-
Identify, Classify, Monitor, Plan, Communicate, Mitigate
Question 11
Question
SPMP acronym is stand for Software Project Manager Plan
Question 12
Question
Which set of artifacts evenly develops on life cycle?
Answer
-
Management Set
-
Deployment Set
-
Requirement Set
-
Design Set
Question 13
Question
You are aware about artifacts of software development process; you know that there are five sets of artifacts. Please check incorrect item from the list below.
Answer
-
Management
-
Design
-
Assessment
-
Requirement
Question 14
Question
Program managers develop the overall program plan and create high-level plans to guide detailed planning at the component level - this definition is true for
Question 15
Question
Which is the numeric value for Risk?
Answer
-
Risk Exposure ( Probability * Impact)
-
Risk Exposure ( Probability * Cost)
-
Risk Exposure ( Impact * Cost)
-
Risk Exposure ( Probability * Schedule)
Question 16
Question
'Scope' of project is:
Answer
-
Only work that can be completed within project duration
-
Any work committed to orally with customer
-
Any work that customer requires to be completed
-
Only work that has to be completed to successfully finish project
Question 17
Question
Baselining of Vision, on what phase relate this activity?
Answer
-
Transition
-
Inception
-
Elaboration
-
Construction
Question 18
Question
What is a response to the negative risk?
Answer
-
Exploit
-
Mitigate
-
Share
-
Enhance
Question 19
Question
Evolution of which phase shown on picture?
Answer
-
Transition
-
Construction
-
Elaboration
-
Inception
Question 20
Question
Which of the below methods is used in reaching a group decision when using the Delphi technique?
Answer
-
Majority
-
Unanimity
-
Dictatorship
-
None of the given
Question 21
Question
1. Increases project risk
2. Decreases project risk as there are more hands to help
3. May change activity durations
4. Doesn’t affect time estimates or risks
Question 22
Question
Activity level of which workflow shown on picture?
Answer
-
Environment
-
Requirement
-
Management
-
Design
Question 23
Question
A document called ____________ is created by decomposing the project scope into smaller, more manageable elements.
Answer
-
Risk Management Plan
-
None of the given
-
Work Breakdown Structure
-
Scope
Question 24
Question
A set of software development activities, or stages that functions together to guide the development and maintenance of software product.
Answer
-
Requirements
-
SPMP
-
Detailed Design
-
Lifecycle
Question 25
Question
A Life cycle of software project has two stages: engineering and production. Which of this stage does not relate to production stage?
Answer
-
deployment
-
construction
-
design
-
test
Question 26
Question
All of you knows who is that stakeholders, just to prove you knowledge please check the more appropriate description of them (stakeholders)?
Answer
-
Individuals with decision-making authority over a project or a group of projects
-
Formally defined structure that takes recourse from the environment and processes
-
The user point-of-entry for application
-
A person or a system that interacts with the software application in support of a specific process
Question 27
Question
All of the following are usually included in a work package except
Answer
-
What will be done
-
All the costs for the work package
-
The time needed to complete the work
-
All of these are included in a work package
Question 28
Question
Baselining of Vision, on what phase relate this activity?
Answer
-
Inception
-
Construction
-
Transition
-
Elaboration
Question 29
Question
Critical path method is used in which of the following processes:
Question 30
Question
Decomposition is best described as:
Question 31
Question
DDD (in terms of Project Management) acronym is stand for Digital Design Document
Question 32
Question
DAD (in terms of Project Management) acronym is stand for Disciplined Agile Delivery
Question 33
Question
Defining and committing to a clear picture of success establishes the common ground rules for a project by making the basic project goals explicit. What is this technique?
Question 34
Question
Each and every project metric should be measurable, actionable and _______________. Finish the sentence with the most appropriate word.
Answer
-
visually understandable
-
influenceable
-
controllable
-
predictable
Question 35
Question
How many elements Networking Diagram consists of?
Question 36
Question
Having metrics can replace a good management judgment. Is this sentence true or false?
Question 37
Question
LDD (in terms of Project Management) acronym is stand for Logical Design Document
Question 38
Question
RUP(in terms of Project Management) acronym is stand for Relationship Unified Process
Question 39
Question
Most issues/problems require more than one measurement to characterize and understand. Is this sentence true or false?
Question 40
Question
PM acronym is stand for Project Manager (also Project Management)
Question 41
Question
Provides measuring units to depict values, thresholds, constraints, scope, duration, maximums, minimums, and averages. This is true about ...
Answer
-
Metrics
-
Contracts
-
Measures
-
Artifacts
Question 42
Question
A task or set of tasks that are carried out in order to create an assignable deliverable.
Answer
-
Activity
-
Stakeholder
-
Peer review
Question 43
Question
A set of conditions that is required to be met before deliverables are accepted. →
Answer
-
Acceptance Criteria
-
Optimistic Duration
-
Critical Chain Method
-
Decision Tree Analysis
Question 44
Question
Those with a particularly significant interest in the project’s outcome, including those providing funding or right of way for the project and property owners who are affected by the project
Answer
-
Activity
-
Stakeholder
-
Peer review
Question 45
Question
The review of the deliverable for technical accuracy by a qualified developer who is familiar with the software product under design or development
Answer
-
Stakeholder
-
Peer Review
-
Activity
Question 46
Question
A process that determines whether the solution under analysis is achievable, given the organization's resourses and constraints.
Answer
-
Feasibility Study
-
Hazard
-
Validation
Question 47
Question
An estimate of the shortest activity duration that takes into account all of the known variables that could affect performance. →
Answer
-
Acceptance Criteria
-
Optimistic Duration
-
Critical Chain Method
-
Decision Tree Analysis
Question 48
Question
Any source or situation with potential to couse injury or harm to workers or the public, harm to environment, incurred liability, or damage to or loss of property.
Answer
-
Feasibility Study
-
Hazard
-
Validation
Question 49
Question
A schedule method that allows the project team to place buffers to any project schedule path to account to project resources and uncertainties. →
Answer
-
Acceptance Criteria
-
Optimistic Duration
-
Critical Chain Method
-
Decision Tree Analysis
Question 50
Question
The technique of evaluating a component or product during or at the end of a phase or project to ensure it complies with the specified requirements.
Answer
-
Validation
-
Hazard
-
Feasibility Study
Question 51
Question
A management summary document giving the essentials of a project in terms of its objectives, justification, and how the objectives are to be achieved
Answer
-
Project Plan
-
Constraint
-
Milestone
Question 52
Question
A diagramming and calculation technique for evaluating the implications of a chain of multiple options in the presence of uncertainty. →
Answer
-
Acceptance Criteria
-
Optimistic Duration
-
Critical Chain Method
-
Decision Tree Analysis
Question 53
Question
The state, quality, or sense of being restricted to a given course of action on inaction. An applicable restriction or limitation, either internal or external, to the project that will affect the performance of the project or a process.
Answer
-
Project Plan
-
Constraint
-
Milestone
Question 54
Question
A significant point or event in the project.
Answer
-
Constraint
-
Project plan
-
Milestone
Question 55
Question
A critical path method technique for calculating the late start and late finish dates, by working backward through the schedule model from the project end date. →
Answer
-
Backward Pass
-
Milestone
-
Change Control
-
Change Request
Question 56
Question
Process that focuses on the outputs generated in response to selected inputs and execution conditions.
Answer
-
Functional testing
-
Kickoff process
-
Project
Question 57
Question
A temporary endeavor undertaken to create a unique product, service, or result.
Answer
-
Project
-
Functional testing
-
Kickoff process
Question 58
Question
Review the output of the previous stage, go over any additional inputs required by thet particular stage, examine the anticipated activities and required outputs of the current stage.
Answer
-
Kickoff process
-
Project
-
Functional testing
Question 59
Question
The totality of features and characteristics of a product or service that bear on its ability to satisfy stated or implied needs.
Answer
-
Quality
-
Business Processes
-
Estimate
Question 60
Question
A significant point or event in a project, program, or portfolio. →
Answer
-
Milestone
-
Change Control
-
Change Request
-
Backward Pass
Question 61
Question
The unique ways in which organizations coordinate and organize work activities, information and knowledge to produce a product or service.
Answer
-
Business Processes
-
Quality
-
Estimate
Question 62
Question
A quantitative assessment of the likely amount or outcome. Usually applied to project costs, resources, effort, and durations and is usually preceded by a modifier
Answer
-
Estimate
-
Business Processes
-
Quality
Question 63
Question
A process whereby modifications to document, deliverable, or baselines associated with project are identified, documented amd approved, or rejected. →
Answer
-
Backward Pass
-
Milestone
-
Change Control
-
Change Request
Question 64
Question
A meeting at which source code is presented for review, comment or approval.
Answer
-
Code review
-
Executable
-
Reverse Engineering
Question 65
Question
A formal proposal to modify any document, deliverable, or baseline. →
Answer
-
Change Request
-
Change Control
-
Milestone
-
Backward Pass
Question 66
Question
A binary data file that can be run by the operating system to perform a specific set of functions
Answer
-
Code review
-
Executable
-
Reverse Engineering
Question 67
Question
A process of examining an existing application that has characteristics that are similar to a desired application
Answer
-
Reverse Engineering
-
Executable
-
Code review
Question 68
Question
A task or set of tasks that are carried out in order to create an assignable deliverable. →
Answer
-
Activity
-
Baseline
-
Assumption
Question 69
Question
A set of software components and documents so that has been formerly reviewed and accepted, that serves as the basis for futher development or current production. →
Answer
-
Activity
-
Baseline
-
Assumption
Question 70
Question
An estimate of the longest activity duration, which takes into account all of the known variables that could affect performance.
Question 71
Question
A factor that, for planning purposes, are considered to be true, real, or certain without proof or demonstratio →
Answer
-
Activity
-
Baseline
-
Assumption
Question 72
Question
The series of phases that a project passes through from its initiation to its closure.
Question 73
Question
What does RUP acronym stand for?
Question 74
Question
The approved version of a schedule model that can be changed only through formal change control procedures and is used as a basis for comparasion to actual results.
Question 75
Question
The control of the evolution of complex systems, for the purpose to contribute to satisfying quality and delay constraints.
Question 76
Question
The series of phases that respresent the evolution of a product, from concept through delivery, growth, maturity, and retirement.
Answer
-
Product Life Cycle
-
Earned Value
-
Bottom-up Estimating
-
Deliverable
Question 77
Question
The measure of work performed expressed in terms of the budged authorized for that work.
Answer
-
Earned Value
-
Product Life Cycle
-
Bottom-up Estimating
-
Deliverable
Question 78
Question
A method of estimating project duration or cost by aggregating the estimates of lower-level components of the work breakdown structure
Answer
-
Bottom-up Estimating
-
Deliverable
-
Earned Value
-
Product Life Cycle
Question 79
Question
Any unique and verifiable product, result, or capability to perform a service that is required to be produced to complete a process, phase, or project.
Answer
-
Deliverable
-
Bottom-up Estimating
-
Earned Value
-
Product Life Cycle
Question 80
Question
The amount of budget deficit or surplus at a given point in time, expressed as the difference between the earned value and the actual cost.
Question 81
Question
SDS (in terms of Project Management) acronym is stand for Software Design Document
Question 82
Question
A grid that links product requirements from their origin to to the deliverables that satisfy them
Question 83
Question
..is a collection of logically-related project activities, usually culminating in the completion of a major deliverable.
Answer
-
Project Phase
-
Requirement
-
Lifecycle
Question 84
Question
The uncontrolled expansion to product or project scope without adjustments to time, cost, and resources.
Question 85
Question
The amount of budget deficit or surplus at a given point in time, expressed as the difference between the earned value and the actual cost
Answer
-
Cost Variance
-
Critical Path Activity
-
Cost Performance index
-
Gantt Chart
Question 86
Question
A collection of generally sequential, non-overlapping product phases whose names and numbers are determined by the manufacturing and control needs of the organization is a
Answer
-
Project Phase
-
Requirement
-
Lifecycle
Question 87
Question
An activity on the critical path in a project schedule
Answer
-
Critical Path Activity
-
Cost Variance
-
Cost Performance index
-
Gantt Chart
Question 88
Question
Percentage of work completed per dollar spent
Answer
-
Cost Performance index
-
Gantt Chart
-
Critical Path Activity
-
Cost Variance
Question 89
Question
Which of the following is not one of the basic classifications of project priorities?
Question 90
Question
A bar chart of schedule information where activities are listed on the vertical axes, dates are shown on horizontal axes.
Answer
-
Gantt Chart
-
Cost Performance index
-
Critical Path Activity
-
Cost Variance
Question 91
Question
Which artifact specifies the quality procedures & standards to be used?
Question 92
Question
If you talk about traditional or conventional development process for software development process, what does it mean?
Answer
-
V model
-
spiral
-
waterfall
-
iterative
Question 93
Question
A component of the project or program management plan that describes how an organization's quality polices will be implemented.
Question 94
Question
In PEAK desicion model what is the common output?
Answer
-
Solution and corresponding decision(s)
-
All of the given
-
Solution and corresponding assumption(s)
-
Solution and corresponding risk(s)
Question 95
Question
The goal of a project is to create a unique:
Answer
-
All of the given
-
Result
-
Product
-
Service
Question 96
Question
The triple constraints in project management are:
Answer
-
Scope, Time, cost
-
Scope, Time, plan
-
Time, scope, performance
-
Scope, Time, quality
Question 97
Question
Which of the below are stakeholders for a project?
Answer
-
Customers
-
Project sponsor
-
Your organization
-
All of the given
Question 98
Question
You can motivate your team members by:
Answer
-
a. All of the given
-
b. Offering bonus/compensation
-
c. Praising them in front of others making them feel accomplished
-
d. Promoting them to higher levels of responsibility if they are interested
Question 99
Question
What technique we do use to determine slack time in Schedule?
Answer
-
Backward Pass
-
Forward Pass
-
Poker Planning
-
Windband
Question 100
Question
While measuring the CV (Cost Variance CV = EV - AC) we will get the Negative value, what does it mean?
Question 101
Question
77. Which is the risk for metrics?
Answer
-
a. Support and ownership from business
-
b.Measurement period not defined
-
c.Define governance process
-
d. All of the given
Question 102
Question
76. Which is NOT an item of Risk Impact ?
Answer
-
a. Critical
-
b. Improbable
-
c. Catastrophic
-
d. Marginal
Question 103
Question
72. What should be done by the project manager to ensure that all work in the project is
Question 104
Question
69. What is NOT a response to the positive risk?
Answer
-
a. Enhance
-
b. Transfer
-
c. Exploit
-
d. Accept
Question 105
Question
68. What types of software testing can involve Users?
Question 106
Question
67. What technique we do use to determine critical path in schedule?
Answer
-
a. Forward Pass
-
b. Backward Pass
-
c. Windband
-
d. Poker Planning
Question 107
Question
65. What does SPMP acronym stand for?
Answer
-
a. Software Project Manager Plan
-
b. Software Project Management Plan
-
c. Software Process Management Plan
-
d. Software Project Management Phase
Question 108
Question
62. What does EV metric measure?
Answer
-
a. Estimated Value - The authorized budget assigned to scheduled work.
-
b. Elaborative Value - The expected cost to finish all the remaining project work.
-
c. Executive Value - The sum of all budgets established for the work to be performed.
-
d. Earned Value - The measure of work performed expressed in terms of the budget authorized for that work.