Which of the following tasks are part of the Approved Technical System Test deliverable in the Final Preparation phase ?
(More than one answer is correct. Please choose the correct answers.)
Answer
Final Integration test.
Execute Technical System Tests.
Going Live Check..
Test of the individual interface programs.
Obtain System Test Results Sign-off
Question 3
Question
Which of the following statements about User Acceptance testing is true?
(More than one answer is correct. Please choose the correct answers.)
Answer
The main objective of the Organisational Change Management work stream is to achieve a successful User acceptance testing.
The emphasis of User acceptance testing is to demonstrate that the system user roles and authorisations have been configured correctly.
User acceptance testing is the last test cycle of an SAP solution implementation, occurs at the end of the realisation phase subsequent to integration testing cycles and aims at ensuring that the system has been tested thoroughly by the project team and is ready to be released to the end-user community.
User acceptance testing means that all test cases have to be approved and signed by the key users for the related business processes.
User acceptance testing is the first test cycle of an SAP solution implementation, to make sure the users have the first say in how the user front end is designed.
Question 4
Question
Testing is an integral part of building and deploying a fully functional and stable system in a timely manner. Which are the two general test categories that need to be addressed?
(One answer)
Answer
Unit Testing and Integration Testing
Business Process Testing and Business Scenario Testing
Functional Testing and Data Load Testing
Functional Testing and Performance Testing
Business Process Testing and Performance Testing
Question 5
Question
Which are testing-focusing accelerators provided in ASAP?
(More than one answer is correct. Please choose the correct answers.)
Answer
Test Case Template
Functional Testing Close Template
Functional Specification Template
Final Configuration Plan
Performance Test Plan Template
Question 6
Question
Which of the following test types is performed in the production environment?
(One answer)
Answer
Functional testing
Regression testing
Performance testing
Data Conversion simulation
Question 7
Question
In Realisation, during baseline and final configuration, the project team needs to test chains of transactions that represent business processes and scenarios. What do you call the test that is focused on multiple transactions within one defined business scenario?