ASAP 8 Methodology Cut Over Management Work Stream Quiz
Description
Diploma ASA380 - ASAP Implementation Methodology Quiz on ASAP 8 Methodology Cut Over Management Work Stream Quiz , created by kim.t.dowling on 16/03/2016.
What is the purpose of the Cut Over work stream in the Realisation phase?
(One answer)
Answer
To simulate the cut over procedure in the development environment and to provide support for the solution during the period immediately following production cutover.
To execute the SAP Going Live Check service
To begin documenting the timing, steps, and logistics for moving from the as-is solution to the to-be solution and to complete the Technical Integration Check service.
To execute the functional testing and performance testing.
To plan the production cutover weekend party
Question 3
Question
What is the purpose of the preliminary cutover plan?
(One answer)
Answer
To setup the schedule transfer of data from the SAP development system and legacy systems to the SAP production system.
To document the strategy, scope and timelines for moving from the as-is solution to the to-be solution and the hyper care period immediately following go-live.
To identify which named users from the customer organisation that will drive the cutover process according to the working schedule.
To execute communication activities to project stakeholders during cut-over and go live.
To document the instructions on how to slice the cake after a successful go-live.