ASAP 8 Methodology Cut Over Management Work Stream Quiz

Description

Diploma ASA380 - ASAP Implementation Methodology Quiz on ASAP 8 Methodology Cut Over Management Work Stream Quiz , created by kim.t.dowling on 16/03/2016.
kim.t.dowling
Quiz by kim.t.dowling, updated more than 1 year ago
kim.t.dowling
Created by kim.t.dowling over 8 years ago
29
1

Resource summary

Question 1

Question
What are tasks of the Production Cutover deliverable? (More than one answer is correct. Please choose the correct answers.)
Answer
  • Initiate Solution Manager Update - Solution Documentation
  • Execute Go Live Simulations 1 - n
  • Conduct Data Quality Readiness Check
  • Final Check of Production Readiness and Sign-Off
  • Provide Post Go Live Support

Question 2

Question
What is the purpose of the Cut Over work stream in the Realisation phase? (One answer)
Answer
  • To simulate the cut over procedure in the development environment and to provide support for the solution during the period immediately following production cutover.
  • To execute the SAP Going Live Check service
  • To begin documenting the timing, steps, and logistics for moving from the as-is solution to the to-be solution and to complete the Technical Integration Check service.
  • To execute the functional testing and performance testing.
  • To plan the production cutover weekend party

Question 3

Question
What is the purpose of the preliminary cutover plan? (One answer)
Answer
  • To setup the schedule transfer of data from the SAP development system and legacy systems to the SAP production system.
  • To document the strategy, scope and timelines for moving from the as-is solution to the to-be solution and the hyper care period immediately following go-live.
  • To identify which named users from the customer organisation that will drive the cutover process according to the working schedule.
  • To execute communication activities to project stakeholders during cut-over and go live.
  • To document the instructions on how to slice the cake after a successful go-live.
Show full summary Hide full summary

Similar

Respiratory System
Addeana
Plastics
fampulli
An Gnáthrud
xlauramartinx
Spanish connectives and a few key phrases
emdrakeley
Macbeth Notes
Bella Ffion Martin
An Inspector Calls - Quotes
jaynejuby
Why the Nazis Achieved Power in 1933 - essay intro/conclusion
Denise Draper
'Love and Relationships' Poem Themes
Lindis Dixon
Mapa Mental Planificación estratégica
Verny Fernandez