SCP110 BIM 7B

Description

Quiz on SCP110 BIM 7B, created by Stanley Chia on 21/03/2016.
Stanley Chia
Quiz by Stanley Chia, updated more than 1 year ago
Stanley Chia
Created by Stanley Chia over 8 years ago
291
4

Resource summary

Question 1

Question
Suggested BIM uses for tender phase (for contractor) are:
Answer
  • Cost Estimation

  • Site Planning (Logistic Planning)

Question 2

Question
Suggested BIM uses for Pre-Construction phase (for contractor) are:
Answer
  • Reviewing Consultant Models

  • Model-based Project Planning and Scheduling

Question 3

Question
Suggested BIM uses for Construction phase (for contractor) are:
Answer
  • Construction Coordination

  • Modelling and Shop Drawings

  • Sequence Complex Construction
  • Setting Out and Verification on Site
  • Prefabrication
 Proposal
  • As-Built models

  • Model for Facility Management

Question 4

Question
The contractor use site model to
Answer
  • Model the site topography
  • Add hoardings along the boundary 
with site access (gates)
  • Plan and model construction access and 
pedestrian access inside the site
  • Model the site offices, storage areas and utilities
  • Plan the vehicle movements and mobile crane movements
  • Plan locations of Tower Cranes

Question 5

Question
Once the site plan model is developed, the main contractor could communicate the site plan to his sub-contractors/workers using: 3D model walk-through 4D simulations or animation videos
Answer
  • True
  • False
Show full summary Hide full summary

Similar

To Kill A Mockingbird Complete Notes
jessica.moscrip
States of Matter
lauren_nutty
Statistics Key Words
Culan O'Meara
A-level Psychology Revision
philip.ellis
Anatomy and Physiology - BIO 111 - Test #1 Flashcards
ajudkins
IB Biology Topic 4 Genetics (SL)
R S
Meiosis vs. Mitosis
nvart00
Causes of World War 1
Rahul Panikker
NSI Test First day
Adedipe Odunayom
Repaso Revalida PR 2016
Rodrigo Lopez
PSBD/PSCOD Model EXam - 2
VS Manikkuttan