Zusammenfassung der Ressource
Contract Practice JCT OVERVIEW
- Which form of Contract?
- Traditional Procurement - re-measurement
- SBC 2011 - with Approx Qts (SBC/AQ)
- Measured Term
Contract (MTC)
- Infrastrucuture Conditions of
Contract 2011
(measurement Version)
- Traditional Procurement - Lump Sum
- SBC 2011 - with
or without
Quantities
SBCXQ or SBCQ
- IBC 2011
(IC & ICD)
- MW Comntract
2011 (MW &
MWD)
- Major Project
Construction Contract
2011 MP
- Building Contract for
Home Owner/Occupier
(HO/B) 2005 rev 2009
- Buildig contract and consultancy
agreement for home owner/occupier
(HO/C & HO/CA) 2005 rev 2009
- Home repair and
maintainance contract
(HO/RM) 2006
- Repair and
maintainance
contract (RM)2011
- Traditional Procurement - cost plus
- Prime cost building contract 2011 (PCC)
- Design and Build
- D&B contract 2011 (DB)
- Infrastructure conditions
of contract 2011 (design
and construction
version)
- Employers Requirements
- the brief e.g. floor
area/ lighting etc
- statement of facts
- site conditions
- services
- contract
information
- form of content of
CP and CSA
- specific
function of
employers
agent, QS and
CoW if required
- Contractors Proposals
- the response to the ER
- drawings, spec, models,
perspectives, videos, method
statement, programmees etc.
- Prov Sums
- Key roles by emp
- payment
- matters relating to valuation
and payment driven by
contractor
- Stage payments (alternative
A) or periodic payments
(Alternative B)
- EOT
- L&E
- Not 'variations'
but 'changes'
- There is no
- A/CA or independent certifier
- certificates (statement & Notices)
- Contract administrated by emp/ EA
- identified in article 3
- EA referred to in
- Clause 2.7.3 (contract docs on site)
- Clause 3.1 (access to site)
- acting for emp as set out in writing
- Contract Sum Analysis
- required form?
- basis of valuation of 'changes' and fluctuations
- can be BQ
- should inc/identify costs (fees) for design wrk
- Management forms
- Management Building
Contract (MC) 2011
- management wks contract agreement
tender agreement (MCWC/A) and the
management works contract conditions
(WCWC/C) 2011
- Construction Mangement
- Construction management appointment 2011 (CM/A)
- Construction management trade contract (CM/TC) 2011
- What type of contract?
- Traditional
- Lump-sum
- Re-measurement
- Prime Cost
- Design and Build
- Mangement
- Mangement Contracting
- contractural relationship
- Management contractor
- employer
- consultants
- contract between Emp and MC include:
- MC 2011
- WP contractor
- WP Contractor
- WP contractor
- Contract between MC and WP contractor include:
- MCWC/A 2011 & MCWC/C 2011
- Construction Management
- Contractural relationships
- Employer
- Construction Manger
- WP Contractor
- WP Contractor
- WP Contractor
- Consultants
- Contract between emp and CM include:
- CM/A 2011
- contract between Emp & WP contractors include:
- CM/T 2011
- Other Standard forms of contract not JCT
- NEC
- GC/Works
- CA form of building
agreement 1982 (3rd ed
2000) 2011
amendments
- conpletion in sections?
- applies to
- SBC
- DB
- IC
- Contractors design
- seperate docs incorporating CDP
- IC/D 2011
- MW/D 2011
- One version of SBC 2011 with CDP incorporated
- DB 2011 design contractors responsibility
except as set out in ER (2.11)
- Contract Structure Generally
- 1.Recitals
- 2. Articles
- 3. Contract Particulars
- 4. Attestation Provision
- 5. COnditions
- 6. Scedules
- Contract conditions fro SBC and DB
- 1. Section 1 - definitions and interprutations
- 2. Section 2 - Carrying out the Works
- 3. Section 3 - Control of the works
- Section 4 - Payment
- Section 5 - Variations (DB Changes)
- Section 6 - Injury, damage and insurance
- Section 7 - Assignment, 3rd party rights and collateral warranties
- Section 8 - Termination
- Section 9 - Settlement of disputes
- Schedule for SBC and DB
- Schedule 1 - contractors design
submission procedure
- Schedule 2 - variation and
acceleration quotation
procedure (DB supplemental
provision)
- Schedule 3 -
insurance
options
- Schedule 4 -
code of practice
- Schedule 5 - third
party rights
- Schedule 6 -
forms of
bonds
- Schedule 7 - fluctuation
options
- Schedule 8 -
supplementary
provisions
- JCT IC and ICD Conditions
- Section 1-
definitions &
interprutations
- Section 2 - Carrying out the
works
- Section 3 - control
of the works
- Section 4 - Payment
- Section 5 - variations
- Section 6 - injury
damages and
insurance
- Section 7 - assignment
and collateral
warranties
- Section 8 - Termination
- Section 9 - Settlement of disputes
- JCT IC & ICD Schedules
- 1 - Insurance options
- 2 - named sub-contractors
- 3 - form of bonds
- 4 - fluctuation options
- 5 - supplementary provisions
- Versions of IC and ICD
- work of sinple content generally
recognised as basic trades of skills
without complex services or specialist
works
- contractor can be required to
design discrete parts of the works
(ICD)
- where fairly detailed
contract provisions are
required
- for use on a basis of with or
without qnts. drawings
togeeher with BQ or spec or
work sch - work can be
adeqautely specified
- non re-measurement or prime cost option
- no design and build option
- MW & MWD Conditions
- 1 - definitions and interprutations
- 2 - carrying out the works
- 3 - control of the works
- 4 - payment
- 5 - injury, damage and insurance
- 6 - termination
- 7 - settlement of disputes
- MW & MWD Schedules
- 1 - arbitration
- 2 - fluctuation options
- 3 - supplemental conditions
- SBC Versions
- With Quantities
- BQ's/ Drawings/ Conditions
- Quantities/ contract sum
- Large value works/ designed by emp
- BQ and dwgs required to specify works
- detailed contract provisions
- Administration by A/CA and QS
- Contractor can be required to design discrete parts of the works
- wks can b divided in 2 sections
- private & local Authority emp
- Without Quantities
- Specification/Work Sch/ Drawings
- quantities (?)/ C. Sum
- As SBC/Q except no bills
- Spec/ Work Sch can be used to adequately
define the quality and scope of woks (low
degree of complexity)
- With Approx Qts
- Bill of approx qt/
dwgs
- quants/ ascertained
final sum
- As SBC/Q except insufficient time/ info to
prepare/ complete design
- Re-measurement
- Administration
- Emp appoints A/CA
- Emp appoints QS
- Design by employer which is undertaken by consultants and issued under the
contract by the A/CA
- IC & ICD Generally
- lump sum contract
- employer appoints A/CA
- certificate
- employer appoints QS
- MW & MWD
- different from SBC & IC
- time
- A/CA empowered to make EOT for
'reasons beyond the control of the
contractor'
- provision of Liquidated damages
- no certificate of
non-completion
- no provision for deferred possession/ partial
possession or sectional completion
- Payment
- due dates are 4 weekly intervals
- fluctuation provisions are limited
- loss and expense limited to variations or prov sums
- Generally
- Lump sum contract
- no QS
- emp appoints A/CA
- Control
- no provision for
naming
sub-contractors
- no provision for employer 'direct works'
- No provision for testing/ opening up works
- Insurance
- contractor insures works
- no provision for emp
- works & exisitng
structures by
employer
- when to use?
- detailed contract provisions are required
- the contractor is to carry out
and complete the design and
the works