Zusammenfassung der Ressource
T017 L&AD
- contractor late completing a contract is
in breach and may need 2 pay damages
- 2 types
- liquidated
- unliquidated
- Damages in contracts
- JCT
- JCT SBC/IC/Prime Cost
- LD's are inputted into the contract particulars
- inc 4 sectional completion damages
- no cap on LD's
- ddt from sums due to contractor/
- Non-completion cert must be issued
as must appropriate payment notices
- JCT Management Bdg contract
- LD's are inputted into the contract particulars
- inc 4 sectional completion damages
- no cap on LD's
- ddt from sums due to contractor
- Non-completion cert must be
issued as must appropriate
payment notices
- JCT D&B
- LD's are inputted into the contract particulars
- inc 4 sectional completion damages
- Total liability does not apply 2 or is not affected by LD provisions
- ddt from sums due to contractor
- Non-completion cert must be issued as must appropriate payment notices
- JCT MW
- LD's are inputted into the contract particulars
- No sectional completion damages
- no cap on LD's
- ddt from sums due to contractor
- No provision 4 partial possession
& non-completion certificate if NOT
REQUIRED
- JCT Mgm contract
- Damages are Unliquidated
- LD's not entered into the contract
- No sectional completion damages
- Cap on LD is irrelevant
- ddt from sums due to contractor
- No provisional for partial posession
- NCE ECC
- NEC ECC Option A to F
- Delay damages are inputted in contract data Pt 1
- inc 4 sectional completion damages
- no cap on DD's the guidance book
implies the standard contract data can
be amended
- Inc in PM certificate 2 MC & emp.
- interest applicable if damages deducted and sub the completion date
is revised. if delay damages is an optional clause is NOT selected then
damages will be unliquidated
- FIDIC
- FIDIC red book
- Delay damages are inputted in appendix to tende
- inc 4 sectional completion damages
- Enter text here
- FIDIC Orange