Throughput Accounting

Beschreibung

Mindmap am Throughput Accounting, erstellt von Sue Evans am 21/05/2017.
Sue Evans
Mindmap von Sue Evans, aktualisiert more than 1 year ago
Sue Evans
Erstellt von Sue Evans vor mehr als 7 Jahre
729
0

Zusammenfassung der Ressource

Throughput Accounting
  1. Key Concepts
    1. Throughput = Sales revenue less material cost
      1. All costs other than materials are assumed to be fixed in the short term.
        1. Inventory is BAD - ideal inventory is zero
          1. Sales = Profit (No demand = no production)
          2. Theory of Constraints
            1. Goldratt’s proposed five-step process for ongoing improvement:
              1. Step 1 Identify the bottleneck/binding constraint.
                1. Step 2 Exploit. Obtain highest possible output from constraint.
                  1. Step 3 Subordinate. Operations prior to constraint should operate as same speed as constraint to avoid build up of WIP.
                    1. Step 4 Elevate the constraint/ bottleneck. Take steps to improve its efficiency.
                      1. Step 5 Return to step 1.
            2. TPAR
              1. Return per factory hour/Cost per factory hour
                1. Sales – Direct Material costs /Product’s time on the bottleneck resource
                  1. Total Factory Cost/Total bottleneck resource time available
                  2. Interpretation
                    1. Viable products/divisions should have a TPAR >1
                      1. TPAR>1 would suggest that throughput exceeds operating costs so the product should make a profit. Priority should be given to the products generating the best ratios.
                        1. TPAR<1 would suggest that throughput is insufficient to cover operating costs resulting in a loss.
                    2. Improving the TPAR
                      1. 1) Increase the sales price for each unit sold to increase the throughput per unit. 2) Reduce materials costs per unit (change materials or suppliers) to increase the throughput per unit. 3) Reduce total operating expenses to reduce the cost per factory hour. 4) Increase capital investment in equipment, machines 5) Improve the productivity of the bottleneck e.g. the assembly workforce or the bottleneck machine, thus reducing the time required to make each unit. Throughput per factory hour would increase and consequently the TPAR would increase.
                      2. Criticisms of TPAR
                        1. It concentrates on the short term when a business has a fixed supply of resources (i.e. a bottleneck) and operating expenses are largely fixed. However, most businesses can’t produce products based on the short term only.
                          1. It is more difficult to apply TA concepts in the long term, when all costs are variable and vary with the volume of production and sales. The business should consider this long term view before rejecting products with a TPAR<1
                        2. Multi-Product Decision Making
                          1. Step 1: Identify the bottleneck constraint
                            1. Step 2: Calculate the throughput per unit for each product
                              1. Step 3: Calculate the throughput per unit of the bottleneck resource for each product
                                1. Step 4: Rank the products in order of the throughput per unit of bottleneck resource
                                  1. Step 5: Allocate resources using this ranking and answer the question e.g. calculate the total throughput/profit of this optimum production level
                          2. Bottleneck resource or binding constraint = an activity which has a lower capacity than preceding or subsequent activity thereby limiting throughput
                            1. Optimised Production Technique
                              1. OPT is based on the principle that profits are increased by increasing the throughput of the organisation. The OPT approach identifies what prevents throughput being higher by distinguishing between bottleneck and non-bottleneck resources. The OPT philosophy therefore advocates that non-bottleneck resources should not be operating at 100% as this will result in inventories increasing. Thus idle time in a non-bottleneck resource is not considered to be detrimental to the company’s operations as increased inventory would result without a corresponding increase in throughput for sale.
                              Zusammenfassung anzeigen Zusammenfassung ausblenden

                              ähnlicher Inhalt

                              Throughput Accounting
                              Nathan Waghorn
                              2D alte Klausurfragen
                              Anni T-Pünktchen
                              Historische Quellenanalyse für Abitur & Matura
                              Elena Koch
                              Der erste Weltkrieg - Mindmap
                              andmitterdorfer
                              PAED
                              M T
                              Vetie - Tierzucht & Genetik - S III
                              Fioras Hu
                              Vetie Immunologie - Klausur 2016
                              Janneke Bosse
                              Vetie Tierseuchenbekämpfung 2015
                              Johanna Müller
                              MS-1.3 Folienpaket 2
                              Markus Voßmann
                              Vetie - Milchhygiene 2012
                              steff Müller
                              Vetie - Lebensmittelkunde 2020/2019
                              Valerie Nymphe