Zusammenfassung der Ressource
Throughput Accounting
- Key Concepts
- Throughput = Sales revenue less material cost
- All costs other than materials are assumed to be fixed in the short term.
- Inventory is BAD - ideal inventory is zero
- Sales = Profit (No demand = no production)
- Theory of
Constraints
- Goldratt’s proposed five-step process for ongoing
improvement:
- Step 1 Identify the bottleneck/binding constraint.
- Step 2 Exploit. Obtain highest possible output from constraint.
- Step 3 Subordinate. Operations prior to constraint should operate as same speed as
constraint to avoid build up of WIP.
- Step 4 Elevate the constraint/ bottleneck. Take steps to improve its efficiency.
- Step 5 Return to step 1.
- TPAR
- Return per factory hour/Cost per factory hour
- Sales – Direct Material costs /Product’s time on the bottleneck resource
- Total Factory Cost/Total bottleneck resource time available
- Interpretation
- Viable products/divisions should have a TPAR >1
- TPAR>1 would suggest that throughput exceeds operating costs so the product should make a profit.
Priority should be given to the products generating the best ratios.
- TPAR<1 would suggest that throughput is insufficient to cover operating costs resulting in a loss.
- Improving the TPAR
- 1) Increase the sales price for each unit sold to increase the throughput per unit. 2) Reduce materials
costs per unit (change materials or suppliers) to increase the throughput per unit. 3) Reduce total
operating expenses to reduce the cost per factory hour. 4) Increase capital investment in equipment,
machines 5) Improve the productivity of the bottleneck e.g. the assembly workforce or the bottleneck
machine, thus reducing the time required to make each unit. Throughput per factory hour would
increase and consequently the TPAR would increase.
- Criticisms of TPAR
- It concentrates on the short term when a business has a fixed supply of resources (i.e. a bottleneck)
and operating expenses are largely fixed. However, most businesses can’t produce products based
on the short term only.
- It is more difficult to apply TA concepts in the long term, when all costs are variable and vary with the
volume of production and sales. The business should consider this long term view before rejecting
products with a TPAR<1
- Multi-Product Decision Making
- Step 1: Identify the bottleneck constraint
- Step 2: Calculate the throughput per unit for each product
- Step 3: Calculate the throughput per unit of the bottleneck resource for each product
- Step 4: Rank the products in order of the throughput per unit of bottleneck resource
- Step 5: Allocate resources using this ranking and answer the question e.g. calculate
the total throughput/profit of this optimum production level
- Bottleneck resource or binding constraint = an activity which has a lower capacity than preceding or
subsequent activity thereby limiting throughput
- Optimised Production Technique
- OPT is based on the principle that profits are increased by increasing the throughput of the organisation. The OPT
approach identifies what prevents throughput being higher by distinguishing between bottleneck and
non-bottleneck resources. The OPT philosophy therefore advocates that non-bottleneck resources should not be
operating at 100% as this will result in inventories increasing. Thus idle time in a non-bottleneck resource is not
considered to be detrimental to the company’s operations as increased inventory would result without a
corresponding increase in throughput for sale.