Frage 1
Frage
Identify the example that would not usually be considered a project.
Antworten
-
building a house
-
developing a computer software application program
-
hosting a wedding reception
-
assembly line manufacturing of automobiles
Frage 2
Frage
According to the authors, the prime objectives of project management are
Antworten
-
scope, cost, time
-
quality, scope, schedule
-
customer satisfaction, budget, schedule
-
cost, quality, customer satisfaction
Frage 3
Frage
In a conventional project lifecycle, as work progresses, uncertainty about the expected outcome should
Antworten
-
become a constant
-
decrease
-
increase
-
be fully removed
Frage 4
Frage
The attributes that characterize a project are
Antworten
-
purpose, repetition, inter-dependencies, consistency, uncertainty, conflict, and one¬time occurrence
-
life cycle, schedule, cost, uncertainty, independence, uniqueness, and purpose
-
resources, uniqueness, conflict, inter-dependencies, one-time occurrence, and finite duration,
-
purpose, life cycle, conflict, certainty, independence, performance, and finite duration
Frage 5
Frage
The "stretched-5" pattern observed during the project lifecycle, for the most part, is a result of the
Antworten
-
changing levels of resources used during successive stages of the project lifecycle
-
changing attitudes of the people who work in the project
-
difficulty in performing the individual activities of a project
-
principle that work expands to fill the allotted time
Frage 6
Frage
The desired outcomes or results of a project are called
Antworten
-
subgroups
-
work packages
-
subprojects
-
deliverables
Frage 7
Frage
Earned value is based on the concept that the percentage of project completion is closely correlated with
Antworten
-
the number of levels in the project
-
relevance of the project
-
cost or the use of resources
-
final assembly of the output
Frage 8
Frage
Which of the following is not one of the four dimensions of project success?
Antworten
-
opening new opportunities for the future
-
number of people working on the project
-
impact on the customer
-
business impact on the organization
Frage 9
Frage
The project to construct a highway is unique because
Antworten
-
the characteristics of terrain will be different for different segments
-
consistency of the concrete will vary for different segments
-
different types of laborers will be used to build various segments of the highway
-
different people manage different sections of the highway
Frage 10
Frage
Projects often interact with other projects being carried out simultaneously within the organization and these interactions take the form of competition for scarce resources between project. This is an example of project
Antworten
-
bottleneck
-
breakdown
-
interdependencies
-
malfunctioning
Frage 11
Frage
When done properly, project management begins with
Frage 12
Frage
The chance that project processes or outcomes will not turn out as planned is called
Antworten
-
risk
-
projecting
-
effort
-
negative outcome
Frage 13
Frage
Having only partial or no information about the situation or outcomes is called
Antworten
-
uncertainty
-
risk
-
effort
-
cluelessness
Frage 14
Frage
Relations between organizational functions, where one function or task is dependent on others, are known as
Antworten
-
interdependencies
-
links
-
projects
-
tasks
Frage 15
Frage
The of the project team is a crucial but unstated element of ancillary trade-
offs that the project manager must consider.
Frage 16
Frage
The project is generally credited with beginning the era of modern project
management
Antworten
-
Manhattan
-
Chicago
-
Great Wall of China
-
Egyptian pyramids
Frage 17
Frage
is a subset of a project consisting of work packages
Antworten
-
task
-
program
-
project
-
process
Frage 18
Frage
Projects are bound by the three objectives of scope, time, and cost. These are collectively referred to as the
Antworten
-
Triple Constraint
-
Triple Factors
-
Three Constraints
-
Triple Play
Frage 19
Frage
Individuals or groups with a special interest in a project are called
Antworten
-
stakeholders
-
project managers
-
leaders
-
directors
Frage 20
Frage
The production of weekly employment reports or the delivery of mail could be considered a
Antworten
-
project
-
non-project
-
quasi-projects
-
triple projects
Frage 21
Frage
Which of the following demonstrates the quality of flexibility required of a project selection model?
Antworten
-
It does not require special interpretation, data that are difficult to acquire, or excessive personnel.
-
It gives valid results within the range of conditions that the firm might experience.
-
It reflects the multiple objectives of both the firm and its managers.
-
It deals with situations both internal and external to the project.
Frage 22
Frage
The two basic types of project selection models identified in the text are
Antworten
-
biased and unbiased
-
numeric and nonnumeric
-
active and passive
-
numeric and qualitative
Frage 23
Frage
If a system is being updated due to operating necessity, the project was selected because
Antworten
-
the system is worth saving at any cost
-
the system is worth saving at the estimated cost of the project
-
the dimension of cost is not relevant to execution of the project
-
the cost overruns can be hidden in someone else's budget
Frage 24
Frage
The drawback of the ___________ model is that it fails to consider cash flows obtained once the initial investment has been recovered.
Antworten
-
payback period
-
average rate of return
-
discounted cash flow
-
profitability index
Frage 25
Frage
If the NPV for a project is < 0, it indicates that the project will
Frage 26
Frage
Scoring models are most often used to overcome this disadvantage of profitability models.
Antworten
-
The inability to account for the time value of money
-
The inability to account for project results beyond the payback period
-
The inability to account for multiple decision criteria
-
The inability to account for cash flow
Frage 27
Frage
Firms usually have two or more projects and this collection of projects is referred to as
Antworten
-
a portfolio
-
an initiation
-
a program
-
a stochastic model
Frage 28
Frage
A technique useful for developing numeric values that are equivalent to subjective, verbal measures of relative value is the
Antworten
-
Delphi system
-
expert system
-
portfolio
-
simulation
Frage 29
Frage
Which of the following is a type of numeric model?
Frage 30
Frage
The _________ is the value of an opportunity foregone
Antworten
-
real option
-
profit
-
opportunity cost
-
revenue
Frage 31
Frage
The _________ is the interest rate set by an organization as the minimum acceptable rate of return for a project
Antworten
-
hurdle rate
-
acceptable rate
-
internal rate of return
-
net present value
Frage 32
Frage
In a project portfolio, _______________ projects have objectives or deliverables that are only
incrementally different in both product and process from existing offerings.
Antworten
-
breakthrough
-
R&D
-
platform
-
derivative
Frage 33
Frage
In a project portfolio, a project that involves a new technology or even a disruptive technology that is known to the industry would serve as an example of a project
Antworten
-
breakthrough
-
R&D
-
platform
-
derivitive
Frage 34
Frage
The set of documents submitted when evaluating a project is referred to as the
Antworten
-
project proposal
-
evaluation set
-
evaluation criteria
-
project manual
Frage 35
Frage
When the decision maker's information is not complete, he/she will have to make a decision under conditions of
Antworten
-
proof
-
uncertainty
-
management
-
risk mitigation
Frage 36
Frage
The discounted cash flow method determines the net present value of all cash flows by discounting them by the
Antworten
-
hurdle rate
-
acceptable rate
-
internal rate of return
-
net present value
Frage 37
Frage
Financial forecasts are reported as __________ financial statements.
Antworten
-
final
-
initial
-
pro forma
-
hypothetical
Frage 38
Frage
A project selection criteria that focuses on how well new products would fit the firm's existing product line would be
Frage 39
Frage
According to research by Sanchez and Robert (2010), which of the following is not a reason why strategic benefits may be difficult to appraise?
Frage 40
Frage
________ is a modeling technique for emulating a process, usually conducted a
considerable number of times to understand the process better and measure its outcomes under different policies.
Antworten
-
Simulation
-
Project management
-
Projectizing
-
Modeling
Frage 41
Frage
According to the authors, the analytic method, when applied to systems, focuses on
Antworten
-
assembling the components of a system into an integrated package
-
building an array of individually designed and manufactured components
-
calculating the cost and schedule requirements
-
dividing the components of a system into smaller and smaller elements
Frage 42
Frage
The ideal project manager should be
Antworten
-
a direct, technical supervisor knowledgeable in the technology of the process being used
-
both generalist/facilitator and have a high level of technical competence in the science of the project
-
a facilitator and specialist with technical credibility
-
a technical specialist competent in principles of robust design
Frage 43
Frage
The project manager must make trade-offs between project progress and process. Conceptually, this involves trade-offs between the _______ functions.
Antworten
-
technical and managerial
-
schedule and cost
-
performance and schedule
-
cost and performance
Frage 44
Frage
According to the authors the project manager should be more skilled at
Antworten
-
general management
-
technology
-
synthesis
-
analysis
Frage 45
Frage
The project manager needs _______ credibility.
Frage 46
Frage
Projects are conducted in four important environments. They are
Antworten
-
economic, political, legal, and sociotechnical
-
internal, external, transitional, and multicultural
-
routine, unique, fast-paced, and complex
-
profit, not for profit, government, and industry
Frage 47
Frage
According to the authors, the key to coping with uncertainty at the end of a project (a common obstacle for project managers) is
Antworten
-
discipline
-
communication
-
planning
-
supervision
Frage 48
Frage
During the buildup phase, the project goals, in order of importance, are
Antworten
-
schedule, scope, cost
-
cost, schedule, scope
-
schedule, cost, scope
-
cost, scope, schedule
Frage 49
Frage
Resources initially budgeted for a project are frequently _________ for the task, partly because of natural optimism by the proposer about how many resources are needed.
Antworten
-
sufficient
-
delayed
-
insufficient
-
hindrances
Frage 50
Frage
Most of the time spent by a project manager is spent
Frage 51
Frage
11. The functional manager uses the ________ approach and the PM uses the ________ approach
Antworten
-
systems; analytic
-
numerical; nonnumeric
-
analytic; systems
-
nonnumeric; numerical
Frage 52
Frage
The project manager's responsibility to the project and to the client is met by ensuring that the _______ of the project is preserved in spite of conflicting demands made by stakeholders.
Antworten
-
management
-
integrity
-
analysis
-
synthesis
Frage 53
Frage
During the final or phaseout stage of the project lifecycle, ___________ is the dominant goal of many project managers.
Antworten
-
schedule
-
cost
-
scope
-
quality
Frage 54
Frage
The structure of a society is determined by its
Antworten
-
institutions
-
wages
-
jobs
-
enemies
Frage 55
Frage
Which of the following is not a phase in the Tuckman ladder?
Antworten
-
forming
-
defining
-
norming
-
mourning
Frage 56
Frage
The _________ is a person who spearheads an idea or action and sells it throughout the organization.
Antworten
-
stakeholder
-
champion
-
interviewer
-
coach
Frage 57
Frage
The ______________ is an alternative action if the expected result fails to materialize.
Antworten
-
trade-off
-
system plan
-
feedback
-
contingency plan
Frage 58
Frage
The __________ represents everything outside the system that delivers inputs or
receives outputs from the system.
Antworten
-
environment
-
feedback
-
culture
-
system
Frage 59
Frage
The __________ is the "corporate culture" within the organization, or even within the
project
Antworten
-
cultural anomaly
-
microculture
-
multiculture
-
interfirm culture
Frage 60
Frage
The project manager makes a ___________ by allowing one aspect of the project to get
worse in return for allowing another aspect of the project to get better.
Antworten
-
decision
-
turnaround
-
trade-off
-
chart
Frage 61
Frage
A party to a conflict will usually be satisfied when the level of frustration has been
Antworten
-
increased by the domination of the other party
-
lowered to the point where no action against the other party is contemplated
-
lowered because the party realizes the hopelessness of continuing the conflict
-
eliminated because the party has surrendered to the other party
Frage 62
Frage
Most of the conflicts that involve the organization and outsiders have to do with
Antworten
-
interpersonal differences
-
cultural differences and status differences
-
technical differences
-
property rights and contractual obligations
Frage 63
Frage
During project formation, the organizational structure selected will have a major impact on the ways in which conflicts are handled. Lack of clarity about the relative power/influence/authority of the PM and the functional managers is a major component of all conflicts involving
Frage 64
Frage
If a resource conflict arises between two high-priority projects, precedence is typically given to the project with the
Antworten
-
earliest due date
-
fastest completion time
-
biggest revenue stream
-
lowest cost to complete
Frage 65
Frage
During project build-up, the project should move from a general concept to
Frage 66
Frage
During project build-up, if the project is independent and standalone, the project manager seeks a commitment of __________ from the functional departments.
Antworten
-
work
-
materials
-
people
-
budgets
Frage 67
Frage
During project build-up, if the project is functionally tied down, the project manager seeks a commitment of _________ from the functional departments.
Antworten
-
work
-
materials
-
people
-
budgets
Frage 68
Frage
Personality conflicts during project phase-out are often caused by
Antworten
-
the absence of deadlines
-
the influx of newer technology
-
pressure to complete the project and anxiety about leaving the project
-
distribution of expenses charged to the project
Frage 69
Frage
According to the authors, the nature of negotiation as it applies to project management is the realization that few of the conflicts arising in projects have to do with
Antworten
-
whether or not the task will be done
-
the precise design of the deliverable
-
how the design will be achieved
-
who will do the work, when, and at what cost
Frage 70
Frage
When dealing with conflict between parties, it is recommended that one _______ in order to avoid the conflict becoming interpersonal.
Frage 71
Frage
Partnering is an attempt to _________ the risk associated with sub-contracting.
Antworten
-
mitigate
-
Increase
-
absorb
-
allow
Frage 72
Frage
_________ is the process which begins when one party perceives that the other has frustrated, or is about to frustrate, some concern of his.
Antworten
-
conflict
-
happiness
-
contentment
-
utility
Frage 73
Frage
According to the authors, the favored technique for resolving conflict is
Antworten
-
negotiation
-
mitigation
-
avoidance
-
collaboration
Frage 74
Frage
The process through which two or more parties seek an acceptable rate of exchange for items they own or control is called
Antworten
-
negotiation
-
mitigation
-
compromising
-
collaboration
Frage 75
Frage
During the early program phases of the project lifecycle, Thamhain et al say that conflict intensity is the greatest with respect to
Antworten
-
cost
-
schedules
-
scope
-
quality
Frage 76
Frage
During the main program phases of the project lifecycle, Thamhain et al say that conflict intensity is the greatest with respect to
Antworten
-
cost
-
schedules
-
scope
-
quality
Frage 77
Frage
Toward the end of the project lifecycle, Thamhain et at say that conflict intensity is the greatest with respect to
Antworten
-
cost
-
schedules
-
scope
-
quality
Frage 78
Frage
Negotiating to a(n) __________ solution is the key to conflict resolution in project management.
Antworten
-
win-lose
-
win-win
-
avoidance
-
confrontation
Frage 79
Frage
The total level of conflict in the project lifecycle is highest during the _________ stage
Antworten
-
closing
-
main program
-
project build-up
-
project formation
Frage 80
Frage
The ___________ approach to negotiation aims to achieve a win-win result.
Antworten
-
principled
-
posititional
-
stakeholder
-
paretto
Frage 81
Frage
If the project manager controls when and what people do while the functional managers control who will be assigned to the project and what technology will be used, the ______organizational form is probably being used.
Antworten
-
projectized
-
pure project
-
matrix
-
weak project
Frage 82
Frage
In the systems approach to design, one organization would have to take responsibility for
Antworten
-
manufacturing everything in the system
-
the integrity of the project design
-
the integrity of the subcontractors
-
product warranties
Frage 83
Frage
The process of dealing with uncertainties in projects that may affect the project for better or for worse has come to be known as
Antworten
-
scope management
-
risk management
-
quality management
-
procurement management
Frage 84
Frage
A common objective of an organization's PM is often created by organizations to
Antworten
-
establish consistent project management standards and methods
-
deal with technological obsolescence
-
train process managers
-
administer application software
Frage 85
Frage
A major purpose of the project management office should be to serve as
Antworten
-
the central location for all clerical support
-
the critical disaster recovery support
-
a link between strategic management and project management
-
maintenance for the project management library
Frage 86
Frage
This member of the project team is in charge of product design and development and is responsible for functional analysis, specifications, drawings, cost estimates, quality/reliability, engineering changes, and documentation
Antworten
-
systems architect
-
manufacturing engineer
-
project controller
-
support services manager
Frage 87
Frage
This member of the project team is responsible for the efficient production of the product of the process, including the manufacturing engineering, design and production of tooling, production scheduling, and other production tasks
Antworten
-
project engineer
-
development engineer
-
contract administrator
-
support services manager
Frage 88
Frage
This person is responsible for the installation, testing, and support of the product (process) once its engineering is complete.
Antworten
-
development engineer
-
systems architect
-
test engineer
-
project controller
Frage 89
Frage
One of the main technical problems faced by the project manager is meeting ________ without compromising performance.
Antworten
-
supplier's targets
-
schedule and cost goals
-
technical specifications
-
cost and conflict goals
Frage 90
Frage
A major advantage of using a _________ placement for a project is that individual
experts can be utilized by many different projects.
Antworten
-
standard
-
virtual
-
projectized
-
functional
Frage 91
Frage
Virtual teams, when composed, should consist of "boundary spanners" who number about one in every _________ team members
Frage 92
Frage
When a firm engages in a large number of similar projects, the ___________ organizational form is apt to be preferred.
Antworten
-
pure project
-
partial matrix
-
functional
-
mixed matrix
Frage 93
Frage
When the standard departments of the organization represent individual disciplines such as engineering, marketing, purchasing, and so on, the organization follows
Antworten
-
projectized management
-
matrixed management
-
functional management
-
mixed management
Frage 94
Frage
The firm or organization within which the project is being conducted is known as the
Antworten
-
parent organization
-
consulting firm
-
project team
-
stakeholder company
Frage 95
Frage
______________ engineering refers to the use of a design team that includes design and manufacturing engineers as well as staff from other relevant areas of the business.
Antworten
-
Concurrent
-
Alignment
-
Matrix
-
Social
Frage 96
Frage
The _________ is a basic project document that describes all the work that must be done to complete the project and forms the basis for costing, scheduling, and work
Antworten
-
WBS
-
OBS
-
PMO
-
project charter
Frage 97
Frage
The approach to organizing that includes both functions (disciplines) and projects in its hierarchy is known as the
Antworten
-
mixed organization
-
functional organization
-
projectized organization
-
matrix organization
Frage 98
Frage
This person's task is the efficient production of the product or process the project engineer has designed, including responsibility for manufacturing engineering, design and production of code, unit testing, production scheduling, and other production tasks.
Antworten
-
test engineer
-
contract administrator
-
development engineer
-
systems architect
Frage 99
Frage
TQM and Six Sigma are good examples of ____________ programs
Antworten
-
participative
-
exclusive
-
frequency
-
inclusive
Frage 100
Frage
If both functional and projectized divisions coexist in a firm, this would result in the __________ organizational structure.
Antworten
-
composite
-
objective
-
encompassing
-
free-form
Frage 101
Frage
The _________ is a specialized view of the action plan that focuses on who has what
responsibility for each project task.
Frage 102
Frage
The success of the project launch meeting is dependent on the existence of
Antworten
-
a project charter
-
the project's scope statement
-
a well-defined set of objectives for the project
-
project planning templates
Frage 103
Frage
This project plan element describes both the managerial and the technical approaches to the work. The technical discussion describes the relationship of the project to available technologies.
Antworten
-
overview
-
objectives
-
general approach
-
contractual aspects
Frage 104
Frage
This project plan element should include profit and competitive goals as well as technical goals.
Antworten
-
overview
-
objectives
-
general approach
-
contractual aspects
Frage 105
Frage
The _______ of a project includes the objectives of the project as well as the time and cost required to complete the project to the customer's satisfaction.
Antworten
-
scope
-
change order
-
outcome
-
purpose
Frage 106
Antworten
-
responsive, accountable, consult, inform
-
responsible, accountable, consult, inform
-
responsive, accountable, consult, integrate
-
responsible, admissible, consult, integrate
Frage 107
Frage
The set of physical elements required to build a project is called the
Antworten
-
bill of materials
-
deliverable
-
milestone list
-
work statement
Frage 108
Frage
___________ is an approach that breaks the planning task down into the activities that must be done in each managerial level of the organization. Typically, the upper level sets the objectives for the next lower level.
Antworten
-
Strategic planning
-
Organizational planning
-
Hierarchical planning
-
Agile planning
Frage 109
Frage
The major tool that a project manager uses during the planning phase is called the
Antworten
-
WBS
-
change request
-
scope statement
-
project plan
Frage 110
Frage
___________is the tendency for the project objectives to be changed with little or no discussion with other parties actively engaged in the project
Antworten
-
Scope reference
-
Scope creep
-
Effectiveness
-
Hierarchical planning
Frage 111
Frage
_______________ is a visual approach that closely mirrors how the human brain records and stores information that can help tap the creative potential of the entire project team
Antworten
-
WBS generation
-
Project planning
-
Risk response planning
-
Mind mapping
Frage 112
Frage
When using a WBS, all of the work should roll up to the next level such that no extra work is required. This is referred to as the
Antworten
-
Development rule
-
All-inclusive rule
-
100% rule
-
WBS rule
Frage 113
Frage
For projects that are constantly changing, the __________ methodology is recommended
Antworten
-
waterfall
-
agile
-
adaptable
-
organic
Frage 114
Frage
Having key stakeholders involved early in the project tends to
Frage 115
Frage
When using the mind mapping process, you should designate one team member as the ___________ to ensure that all team members are involved and contributing, and to ensure that team members are focusing on the work that must be done.
Antworten
-
planner
-
facilitator
-
contractor
-
manager
Frage 116
Frage
A useful tool for facilitating the management of changes to a project's scope is the
Frage 117
Frage
A project manager must ___________ as a type of risk response planning in order to soften the danger of a threat by reducing the likelihood that it will occur or by reducing its impact if it does occur.
Antworten
-
avoid
-
transfer
-
accept
-
mitigate
Frage 118
Frage
The ____________ is a list of the project activities with major activities broken down into subactivities.
Frage 119
Frage
The process of coordinating the work and timing of the different groups working on multidisciplinary teams is called
Antworten
-
procurement management
-
integration management
-
vertical management
-
matrix management
Frage 120
Frage
This element of the project plan contains a brief description of the procedure to be followed in monitoring, collecting, storing, and evaluating the history of the project
Antworten
-
schedule
-
resources
-
personnel
-
evaluation methods
Frage 121
Frage
If a project budget is under funded, it will often
Antworten
-
stimulate increased performance
-
improve utilization of resources
-
frustrate committed stakeholders
-
reduce costs
Frage 122
Frage
The project's budget should
Antworten
-
associate resource use with the achievement of organizational goals
-
allow funds to be spent without linkage to achievement
-
not reflect the timing of expenses associated with the use of resources
-
never be changed during project execution
Frage 123
Frage
In order to develop a budget, the PM must forecast
Frage 124
Frage
A work element whose cost is fully developed would
Antworten
-
exclude the cost of labor and resources
-
include only the profit and direct costs
-
exclude the cost of special machinery and overheads
-
include direct costs plus overhead and G&A charges
Frage 125
Frage
The traditional organizational budget is
Frage 126
Frage
__________ budgeting allows income and expenditures to be aggregated across projects.
Antworten
-
Category-oriented
-
Activity-oriented
-
Project-oriented
-
Expense-oriented
Frage 127
Frage
The authors identify ____________ estimation errors as the two types of generic estimation errors.
Antworten
-
small and large
-
random and planned
-
certain and uncertain
-
random and biased
Frage 128
Frage
The pattern of deviations in cost and usage used for exception reporting to management is called
Antworten
-
simulations
-
assumptions
-
variances
-
summaries
Frage 129
Frage
___________ costs vary with output.
Frage 130
Frage
Unless the project manager is familiar with the firm's ______________ it will be very difficult to exercise budget control.
Antworten
-
accounting system
-
budget plans
-
marketing procedure
-
cost accounting
Frage 131
Frage
The __________ form of budgeting has the advantage of using individuals closer to the work to provide estimates of resource requirements.
Antworten
-
top-down budgeting
-
work element costing
-
bottom-up budgeting
-
iterative budgeting
Frage 132
Frage
The ___________ charge is composed of the costs of senior management, the various data functions, and any other expenses not included in overhead. Often, these charges are a fixed percentage of either the direct costs or the total of all direct and indirect costs.
Antworten
-
salary
-
project management
-
ethical
-
G&A
Frage 133
Frage
Each time the output doubles, the worker hours per unit decrease to a fixed percentage of their previous value. That percentage is called the ___________ rate.
Antworten
-
inflation
-
hurdle
-
interest
-
learning
Frage 134
Frage
Suppose that a person requires 60 minutes to complete a work element on the first attempt. On the second attempt, the work element is completed in 48 minutes. The learning rate for this person is _________% for this work element
Frage 135
Frage
_____________ relies on well-known statistical correlations between various factors such as the total cost of a house relative to the square feet of living area.
Antworten
-
Parametric estimating
-
Statistical equivalence
-
Bottom-up estimating
-
Top-down estimating
Frage 136
Frage
A budget strategy that is based on collecting the judgments and experiences of top and middle managers is referred to as the ___________ approach or method.
Antworten
-
parametric estimating
-
statistical equivalence
-
bottom-up estimating
-
top-down estimating
Frage 137
Frage
________________ are where the defined responses to the risks are detailed, but their amounts are not
yet precisely known.
Antworten
-
Known-unknowns
-
Unknown-knowns
-
Known-knowns
-
Unknown-unknowns
Frage 138
Frage
Unknown-unknowns are not part of the baseline budget and are referred to as
Antworten
-
management reserves
-
contingency reserves
-
PMBOK reserves
-
Buffered reserves
Frage 139
Frage
The advantage of the ____________ process is that it is generally associated with participative management
Antworten
-
bottom-up
-
top-down
-
Murphy's
-
Efficient
Frage 140
Frage
______________ issues are present when bidders "low-ball" a bid or when some bidders get a "last look."
Antworten
-
Ethical
-
Strategic
-
Efficient
-
Effective
Frage 141
Frage
The authors recommend preparing a schedule for each
Frage 142
Frage
In the AOA network, circles depict
Antworten
-
networks
-
events
-
logical dependencies
-
dummy activities
Frage 143
Frage
The shortest time in which the entire network can be completed is referred to as the
Antworten
-
critical time of the network
-
real duration of the network
-
elapsed time of the network
-
slack time of the network
Frage 144
Frage
A precedence relationship where the completion of a successor activity depends on the completion of a predecessor activity is called a
Antworten
-
start to finish dependency
-
finish to start dependency
-
finish to finish dependency
-
start to start dependency
Frage 145
Frage
A precedent relationship where the completion of a predecessor activity depends on the initiation of a successor activity is called a
Antworten
-
start to finish dependency
-
finish to start dependency
-
finish to finish dependency
-
start to start dependency
Frage 146
Frage
The difference between the late start and early start for an activity is called its
Antworten
-
critical path
-
task
-
progress
-
float
Frage 147
Frage
A(n) __________ is the conversion of the project work breakdown structure into an operating timetable.
Antworten
-
chart
-
application
-
crash
-
schedule
Frage 148
Frage
A(n) _________ is a specific task or set of tasks that are required by the project, use up resources, and take time to complete
Antworten
-
milestone
-
activity
-
node
-
path
Frage 149
Frage
The arrangement of all activities (and, in some cases, events) in a project arrayed in their logical sequence and represented by arcs and nodes is called a
Antworten
-
network
-
critical path
-
path
-
crashed path
Frage 150
Frage
In a network, if the delay of an activity will delay completion of the project, the activity is called a(n)
Antworten
-
valuable
-
efficient
-
critical
-
noteworthy
Frage 151
Frage
In AOA networks, an activity of zero duration is called a(n)
Antworten
-
dummy activity
-
critical
-
important
-
critical activity
Frage 152
Frage
The _____________ chart shows planned and actual progress for a number of tasks displayed against a horizontal timescale.
Antworten
-
PERT
-
timeline
-
critical
-
Gantt
Frage 153
Frage
A clearly identifiable point in a project or set of activities that commonly denotes a reporting requirement or completion of a large or important set of activities is called a(n)
Antworten
-
milestone
-
anniversary
-
node
-
dummy activity
Frage 154
Frage
In AON diagrams, a(n) ________________ is a point where one or more lines (arrows) begin or terminate, commonly used for depicting an event or activity.
Frage 155
Frage
______________ is the amount of one factor that must be sacrificed in order to achieve more or less of another factor.
Antworten
-
trade-off
-
synergy
-
barter limit
-
limiting quantity
Frage 156
Frage
A _____________ is a combination of interrelated activities and events depicted with arcs and nodes.
Antworten
-
linked plan
-
chain of events
-
critical chain
-
network
Frage 157
Frage
____________ law suggests that work expands to fill the allotted time.
Antworten
-
Parkinson's
-
Murphy's
-
Brooks'
-
Federal
Frage 158
Frage
In application, PERT has primarily been used for
Frage 159
Frage
The authors define _________ as the time an activity can be delayed without affecting the start time of any successor activity
Antworten
-
free slack
-
total slack
-
project slack
-
overhead slack
Frage 160
Frage
__________ is one possible way to check the nature and impacts of interactions between probabilistic paths in a network.
Frage 161
Frage
If deterministic time estimates are used, and if project deadlines are firm, there is a high likelihood that it will
Antworten
-
not be necessary to crash any activities in projects
-
be necessary to crash the last few activities of most projects
-
be completed on time and within budget
-
be completed as per schedule
Frage 162
Frage
Assume two activities, printing and binding. Printing is a predecessor of binding. If printing is _______, then binding will start late by whatever amount of lateness is bequeathed to it by printing.
Antworten
-
necessary
-
early
-
late
-
time-neutral
Frage 163
Frage
________ aims to minimize the period-by-period variations in resource loading by shifting tasks within their slack allowances. The purpose is to create a smoother distribution of resource usage.
Antworten
-
Resource loading
-
Resource leveling
-
Scope loading
-
Resource succeeding
Frage 164
Frage
A project task is said to be __________ if it requires a fixed amount of time and known quantities of resources
Antworten
-
scope constrained
-
time constrained
-
resource constrained
-
system constrained
Frage 165
Frage
One of the problems that Goldratt observed was that if an activity has slack time, the task might become delayed until the slack is removed. This is referred to as
Antworten
-
Goldratt's Law
-
Murphy's Law
-
the delay game
-
the student syndrome
Frage 166
Frage
The points between the extreme points of the relationship between time use and resource use represent
Antworten
-
time constrained projects
-
resource constrained projects
-
alternative trade-offs between time and resources
-
a non-feasible solution space of trade-off alternatives related to time and resource use
Frage 167
Frage
The _________ technique overlaps the design and build phases of a project to expedite its completion.
Antworten
-
crashing
-
fast-tracking
-
leading
-
blitzing
Frage 168
Frage
Most heuristic solution methods start with the _____________ and analyze resource usage period by period, resource by resource.
Antworten
-
GERT schedule
-
Gantt chart
-
PERT/CPM schedule
-
Master schedule
Frage 169
Frage
The use of ______________ activity time estimates may reduce the chance that crashing the
project will be needed.
Antworten
-
one probabilistic
-
two probabilistic
-
three probabilistic
-
four probabilistic
Frage 170
Frage
The standard practice with AOA and AON is to estimate activity times under the assumption of resource loadings that are
Antworten
-
probabillistic
-
crashed
-
normal
-
dynamic
Frage 171
Frage
With respect to project scheduling, __________ is the amount of work waiting to be processed because there is a shortage of some resource.
Antworten
-
in-process inventory
-
schedule slippage
-
resource utilization
-
management delay
Frage 172
Frage
If the appropriate scheduling equation for task A of a project were W = D * U, and it was initialized so that W = 40d, D = 10d, and U = 4 resources, and task A is an effort-driven activity, correctly balance this equation if the value for U is changed from 4 to 5. To balance the equation, the altered variable and its new value are
Antworten
-
D = 6w
-
W = 6d
-
D = 8d
-
W = 8d
Frage 173
Frage
The principal reason why a project manager is surprised by resource constraints on a project is the failure to include _________ in risk identification activities.
Antworten
-
resource availability
-
resource cost
-
resource mobility
-
resource skill
Frage 174
Frage
Which of the following describes a situation where priorities are assigned to activities according to some rule not associated with task length, slack, or resource requirements?
Antworten
-
student's syndrome
-
arbitrary
-
most successors
-
most resources
Frage 175
Frage
The two fundamental approaches to constrained allocation problems are
Antworten
-
heuristic approaches and rules of thumb
-
linear programming approaches and optimization models
-
heuristic approaches and optimization models
-
goal programming and trial and error
Frage 176
Frage
When crashing a project, our first task is to develop
Antworten
-
a table or graph of the cost of a project as a function of the project's possible completion dates
-
a schedule that shows the risks associated with each activity in the project
-
a list that shows the activities and the events of a project without referring to the costs
-
a table showing the noncritical activities and the cost associated with each of those activities
Frage 177
Frage
In some situations, two activities are scheduled to be carried out in parallel and using the same scarce resource. If the supply of the scarce resource is not sufficient to allow both activities to be carried out simultaneously, then whichever of the two is given priority immediately lengthens the other activity's path but not its actual
Antworten
-
duration
-
slack
-
float
-
buffer
Frage 178
Frage
The two principles to follow when crashing a project focuses on the
Antworten
-
critical path and selects the least expensive alternative
-
critical path and selects the most expensive alternative
-
shortest path and selects the least expensive alternative
-
shortest path and selects the most expensive alternative
Frage 179
Frage
Using Goldratt's meaning of the word "dependent," the activities of a project can be ordered into paths based on their resource dependencies as well as on their technological precedence requirements. The longest of these paths of sequentially time-dependent activities is known as the
Antworten
-
priority chain
-
critical chain
-
dependency path
-
heuristic path
Frage 180
Frage
The ___________ heuristic provides a general solution for critical path and time and is usually the default rule for a schedule.
Antworten
-
as soon as possible
-
as late as possible
-
minimum slack first
-
shortest task first
Frage 181
Frage
Monitoring, as an activity, should be kept distinct from __________, which uses data supplied by monitoring to bring actual performance into approximate congruence with planned performance.
Antworten
-
recording
-
controlling
-
collecting
-
reporting
Frage 182
Frage
An appropriate and common secondary user for monitoring includes
Antworten
-
auditing, learning from mistakes, and reporting progress and status
-
exercising effective control over the project
-
evaluating current status of the project
-
fixing the blame when things go wrong
Frage 183
Frage
According to the authors, the key items to be planned, monitored, and controlled are
Antworten
-
schedule, budget, and financial stability
-
schedule, quality, performance, and customer satisfaction
-
schedule, budget, and feasibility
-
schedule, budget, and performance
Frage 184
Frage
According to the authors, in the planning - monitoring - controlling cycle, the directions of the flows indicate that
Antworten
-
information flows from the top to bottom and authority flows from the bottom to the top
-
information flows from the bottom to the top and authority flows from the top to the bottom
-
authority flows from the bottom to the top
-
information flows from the top to the bottom
Frage 185
Frage
The first step in setting up a monitoring system is to
Antworten
-
collect existing data to see what data is relevant and available
-
collect every available piece of information so it can be analyzed
-
use whatever information is available
-
identify the key factors to be controlled
Frage 186
Frage
In earned value analysis, the 50-50 rule assumes that
Antworten
-
50 percent is earned when the task is half done and 50 percent is earned at completion
-
50 percent is earned when the task begins and 50 percent is earned at completion
-
50 percent is earned when the task begins and 50 percent is earned at the halfway stage
-
50 percent is earned when the project is planned and 50 percent is earned when the project is over
Frage 187
Frage
In earned value analysis, if the cost variance is (-$10,000),
Antworten
-
the cost variance is favorable
-
the cost variance is unfavorable
-
the scheduled variance is favorable
-
the scheduled cost avoidance is unfavorable
Frage 188
Frage
One of the most common errors when collecting data is
Antworten
-
collecting rapidly changing data frequently
-
collecting data infrequently because data collection is so time consuming
-
collecting data that rarely changes
-
reporting to management after collecting data
Frage 189
Frage
Reports for ______________ have a need for detailed information about individual tasks and the factors affecting such tasks.
Antworten
-
top executives
-
lower-level personnel
-
all the stakeholders
-
project managers
Frage 190
Frage
The project control process should be viewed as a(n) ________________, with revised plans
and schedules (if warranted) following corrective actions. The project control process should run continuously until the project is completed.
Antworten
-
closed loop system
-
open loop system
-
open environment
-
earned value plan
Frage 191
Frage
Ordinal rankings of performance are examples of a _________ type of measure.
Frage 192
Frage
____________ are used when some aspect of system performance cannot be measured
directly
Antworten
-
Indicators
-
Frequency counts
-
Raw numbers
-
Verbal measures
Frage 193
Frage
____________ can often give the project manager early warning signals of potential problems in a project and help understand the relationships of individual tasks to one another and to the overall project.
Frage 194
Frage
The earned value rule that divides the actual task time-to-date by the scheduled time for the task to calculate percent complete is called the _________ rule.
Antworten
-
50-50
-
0-100 percent
-
critical input use
-
proportionality
Frage 195
Frage
In earned value analysis, EAC refers to the
Frage 196
Frage
In earned value analysis, BAC refers to the
Antworten
-
budgeted annual cost
-
budget at completion
-
budget at close-out
-
big annual cost
Frage 197
Frage
If EV= $500, AC = $475, PV = $450; SV =
Frage 198
Frage
If CSI is less than 1, it is indicative of a(n)
Antworten
-
problem
-
good project
-
efficient project
-
budget error
Frage 199
Frage
Conceptually, EAC represents the amount spent to date
Antworten
-
plus the delay costs
-
BAC
-
CV
-
ETC
Frage 200
Frage
In earned value analysis, the 0 - 100 percent rule allows
Antworten
-
100 percent credit before starting work and 0 percent credit after the completion
-
0 percent credit when work begins and 100 percent credit when the project is complete
-
0 percent credit when work begins and 100 percent credit at completion of the activity
-
0 percent credit at completion of the activity and 100 percent credit at formal acceptance during scope verification