Frage 1
Frage
[blank_start]Benchmarking[blank_end] is the comparison of actual or planned products, processes, and practices to those of comparable organizations to identify best practices, generate ideas for improvement, and provide a basis for measuring performance.
Antworten
-
Benchmarking
-
Check sheets
-
Brainstorming
-
Interviews
Frage 2
Frage
Enterprise Environmental factors external to the organization such as Commercial Data bases can often include [blank_start]benchmarking[blank_end] results, standardized cost estimating data, industry risk study information, and risk databases.
Antworten
-
benchmarking
-
market research
-
check sheet
-
statistical sampling
Frage 3
Frage
Academic research can often include industry studies, publications, and [blank_start]benchmarking[blank_end] results.
Antworten
-
benchmarking
-
checklist
-
brainstorming
-
question and survey
Frage 4
Frage
Data gathering techniques such as [blank_start]benchmarking[blank_end], [blank_start]questions and surveys[blank_end], [blank_start]focus groups[blank_end], interviews, and brainstorming are all tools and techniques of the collect requirements process.
Antworten
-
benchmarking
-
market research
-
statistical sampling
-
checklist
-
questions and surveys
-
market research
-
statistical sampling
-
checklists
-
focus groups
-
statistical sampling
-
market research
-
checklists
Frage 5
Frage
In the practice of benchmarking the organizations compared can be both internal and external.
Frage 6
Frage
Data gathering techniques such as [blank_start]benchmarking,[blank_end] [blank_start]brainstorming[blank_end] and [blank_start]interviews[blank_end] are often tools and techniques of the Plan Quality Management process.
Antworten
-
benchmarking,
-
checklists
-
risk register
-
statistical sampling
-
brainstorming
-
statistical sampling
-
quality metrics
-
meetings
-
interviews
-
cost-benefit analysis
-
flow charts
-
the assumption log
Frage 7
Frage
Data gathering techniques such as [blank_start]benchmarking[blank_end] are often tools and techniques of the Plan Stakeholder Engagement process.
Frage 8
Frage
Mind-Mapping is a technique used to consolidate ideas created through individual [blank_start]brainstorming[blank_end] sessions into a single diagram to reflect commonality an differences in understanding and to generate new ideas.
Antworten
-
brainstorming
-
benchmarking
-
note taking
-
diagramming
Frage 9
Frage
Nominal Group Technique is a technique that enhances [blank_start]brainstorming[blank_end] with a voting process used to rank the most useful ideas for further [blank_start]brainstorming[blank_end] or for prioritization.
Antworten
-
brainstorming
-
meetings
-
focus groups
-
interviews
-
brainstorming
-
meetings
-
interviews
-
focus groups
Frage 10
Frage
Data gathering techniques such as [blank_start]brainstorming[blank_end], [blank_start]focus groups[blank_end], and [blank_start]interviews[blank_end] are often tools and techniques of the Develop Project Charter process group.
Antworten
-
brainstorming
-
conflict management
-
the business case
-
benchmarking
-
focus groups
-
benchmarking
-
market research
-
meeting management
-
interviews
-
meetings
-
the internet
-
check sheets
Frage 11
Frage
[blank_start]Brainstorming[blank_end] is a technique used to identify a list of ideas in a short period of time. It is conducted in a group environment and is ed by a facilitator. [blank_start]Brainstorming[blank_end] comprises two parts; idea generation and analysis.
Antworten
-
Brainstorming
-
Market research
-
Check sheets
-
Interviews
-
Brainstorming
-
Market research
-
Focus groups
-
Interviews
Frage 12
Frage
Brainstorming can be used to gather data and other solutions or ideas from stakeholders, subject matter experts, and team members when developing the project charter.
Frage 13
Frage
Data gathering techniques such as [blank_start]brainstorming[blank_end], [blank_start]checklists[blank_end], [blank_start]focus groups[blank_end], and [blank_start]interviews[blank_end] are all often part of the Develop Project Management Plan.
Antworten
-
brainstorming
-
basis of estimates
-
earned value management
-
benchmarking
-
checklists
-
benchmarking
-
analytical techniques
-
facilitation
-
focus groups
-
check sheets
-
benchmarking
-
inspections
-
interviews
-
interpersonal skills
-
earned value management
-
benchmarking
Frage 14
Frage
Brainstorming is frequently used when developing the project management plan to gather ideas and solutions about the project approach. Attendees include project members as well as subject matter experts (SMEs) or stakeholders may attend.
Frage 15
Frage
Brainstorming is not often used as a technique to generate and collect multiple ideas related to project and product requirements.
Frage 16
Frage
Brainstorming is not effective and rarely used to gather data from group members and subject matter experts when developing a quality management plan that fits an upcoming project.
Frage 17
Frage
Data analysis techniques such as [blank_start]brainstorming[blank_end], [blank_start]checklists[blank_end], and [blank_start]interviews[blank_end] are often tools and techniques of the Identify Risks process.
Antworten
-
brainstorming
-
benchmarking
-
statistical sampling
-
focus groups
-
checklists
-
benchmarking
-
statistical sampling
-
check sheets
-
interviews
-
expert judgement
-
benchmarking
-
check sheets
Frage 18
Frage
The goal of [blank_start]brainstorming[blank_end] during the Identify Risks process is to obtain a comprehensive list of individual project risks and sources of overall project risk. The project team usually performs [blank_start]brainstorming[blank_end], often with multidisciplinary set of experts who are not part the team.
Antworten
-
brainstorming
-
benchmarking
-
focus groups
-
interviews
-
brainstorming
-
benchmarking
-
interviews
-
focus groups
Frage 19
Frage
Categories of risk, such as in a risk breakdown structure, can be used as a framework for brainstorming.
Frage 20
Frage
In the Identify Risk process, while conducting brainstorming it is not necessary to pay particular attention to ensuring that risks identified through brainstorming are clearly described as they can always be fully formed later in the process.
Frage 21
Frage
During the Identify Risks process the specialized meetings known as risk workshops include some form of what kind of data gathering technique?
Antworten
-
Benchmarking
-
Focus Groups
-
Check Sheets
-
Brainstorming
Frage 22
Frage
The techniques related to data gathering found in the Identify Stakeholders process include but are not limited to what?
Frage 23
Frage
What is a refinement of brainstorming that allows individual participants time to consider the questions individually before the group creativity session is held, then allows participants to gather face-to-face in groups or through virtual environments supported by technology?
Antworten
-
Individual Brainstorming
-
Brain Writing
-
Mind Mapping
-
Brain Dump
Frage 24
Frage
Organizational process assets often used in the Plan Quality Management process often include quality templates such as [blank_start]check sheets[blank_end], tractability matrix, and others.
Antworten
-
check sheets
-
checklists
-
quality metrics
-
interviews
Frage 25
Frage
Control Quality is the process of monitoring and recording results of executing the quality management activities in order to assess performance and ensure the project outputs are complete, correct and meet customer expectations.
In order to carry out this process effectively what data gathering techniques are often used?
Frage 26
Frage
The figure shown is an example of what kind of data gathering tool and technique used in the Control Quality process group?
Antworten
-
Check / tally sheet
-
Checklist
-
Defect Tracker
-
Tally list
Frage 27
Frage
Check sheets are especially useful for gathering attributes data while performing inspections to identify defects as well as data about frequencies or consequences of defects collected.
Frage 28
Frage
Quality [blank_start]Checklists[blank_end] are structured tools used to verify that a set of required steps has been performed.
Antworten
-
Checklists
-
Check sheets
-
Metrics
-
Audits
Frage 29
Frage
Many organizations have standardized [blank_start]checklist[blank_end] available based in their own experience or use standard versions from their industry. These may guide the project manager to develop the plan or may help to verify that all the required information is included in the project management plan.
Antworten
-
checklist
-
focus groups
-
interview processes
-
check sheets
Frage 30
Frage
Select all the data gathering techniques used in the Manage Quality process.
Antworten
-
Flow charts
-
Check sheets
-
Checklists
-
Root cause analysis
-
Interviews
Frage 31
Frage
Quality checklists used in the Manage Quality process should incorporate the acceptance criteria included in the scope baseline.
Frage 32
Frage
Test and Evaluation Documents can be created based on industry needs and the organization's templates. They are inputs to the Control Quality process and are used to evaluate the achievement of quality objectives. These documents may include dedicated [blank_start]checklists[blank_end] and detailed requirements tractability matrices as part of the document.
Antworten
-
checklists
-
quality metrics
-
root cause analyses
-
check sheets
Frage 33
Frage
Checklist are not helpful in managing the control quality activities in the a structured manner and therefore only seldom applied while carrying out the Control Quality process.
Frage 34
Frage
Enterprise Environmental Factors that often play a role in the Identify Risks process group include which of the following data gathering techniques?
Antworten
-
Statistical Sampling
-
Checklists
-
Check sheets
-
Interviews
Frage 35
Frage
Risk [blank_start]checklists[blank_end] are developed based on historical information and knowledge that has been accumulated from similar projects and from other sources of information.
Antworten
-
checklists
-
analyses
-
metrics
-
responses
Frage 36
Frage
Risk checklists list specific individual project risks that have occurred previously and that are relevant to the project. They also provide an effective way to capture lessons learned.
Frage 37
Frage
While identifying risks and applying the checklist data gathering technique it is not important to look for risks not identified in the checklist due to the comprehensive nature of checklists. A team therefore has no need to update new information or remove obsolete information from the checklists. This is why use of checklists is so highly recommended.
Frage 38
Frage
[blank_start]Focus groups[blank_end] are an elicitation technique that brings together prequalified stakeholders and subject matter experts to learn about their expectations and attitudes about a proposed product, service or result.
Antworten
-
Focus groups
-
Interviews
-
Brainstorming sessions
-
Planning meetings
Frage 39
Frage
[blank_start]Focus groups[blank_end] are a data gathering technique used in the Develop Project Charter process to bring together stakeholders and subject matter experts to learn about perceived project risk, success criteria, and other topics.
Antworten
-
Focus groups
-
Interviews
-
Stakeholder meetings
-
Brainstorming sessions
Frage 40
Frage
Focus groups are often used as a data gathering technique in the Develop Project Management Plan process to discuss project management approach and the integration of the different components of the project management plan.
Frage 41
Frage
Knowledge management tools and techniques connect people so they can work together to create new knowledge, share tacit knowledge, and integrate the knowledge of diverse team members. These tools and techniques can sometimes include what data gathering method?
Antworten
-
Market Research
-
Interviews
-
Focus groups
-
Brainstorming
Frage 42
Frage
Focus groups usually are conducted under the guidance of a trained moderator who guides the group through the interactive discussion with the intent of making it more conversational than a one-on-one interview.
Frage 43
Frage
Individual and team assessment tools give the project manager and the project team insight into areas of strengths and weaknesses. Various tools are available that can help the project manager asses team member preferences, aspirations and how they process and organize information.
Which of the below data gathering techniques is an effective tool often used to help conduct these assessments?
Antworten
-
Checklists
-
Check Sheets
-
Market Research
-
Focus Groups
Frage 44
Frage
Communication Requirements Analysis is an analytical technique to determine the information needs of the project stakeholders through [blank_start]interviews[blank_end], workshops, study of lessons learned from previous projects, etc.
Frage 45
Frage
[blank_start]Interviews[blank_end] are a formal or informal approach to elicit information from stakeholders by taking to them directly.
Antworten
-
Interviews
-
Focus groups
-
Conversations
-
Individual assessments
Frage 46
Frage
During the Develop Project Charter process a common method for obtaining information on high-level requirements, assumptions or constraints, approval criteria and other information from stakeholders is through what data gathering technique?
Antworten
-
Checklists
-
Facilitation
-
Group discussions
-
Interviews
Frage 47
Frage
Interviews are a common tool and technique used in the Develop Project Management Plan process to obtain specific information from stakeholders.
Frage 48
Frage
During the Collect Requirements process [blank_start]interviews[blank_end] are typically performed by asking prepared and spontaneous questions and recording the responses.
Frage 49
Frage
Interviews often not very useful when trying to obtain confidential information.
Frage 50
Frage
Projects and product quality needs and expectations, implicit and explicit, formal and informal can be verified by using the data gather technique of [blank_start]interviewing[blank_end].
Antworten
-
interviewing
-
focus groups
-
data sheets
-
checklists
Frage 51
Frage
Perform Qualitative Risk Analysis is the process of prioritizing individual project risks for further analysis or action by assessing the probability of occurrence and impact as well other characteristics.
What are the data gathering tools and techniques used in this process?
Antworten
-
Focus groups
-
Interviews
-
Checklists
-
Check sheets
Frage 52
Frage
During the Perform Qualitative Risk Analysis process group expert judgment is often obtained through facilitated risk workshops or [blank_start]interviews[blank_end].
Frage 53
Frage
While in the Perform Qualitative Risk Analysis the possibility of expert views being biased should be taken into account during interviews and risk workshops.
Frage 54
Frage
When conducting risk probability and impact assessments, risk can be assessed in [blank_start]interviews[blank_end] or meetings with participants selected for their familiarity with the types of risk recorded in the risk register.
Antworten
-
interviews
-
focus groups
-
risk workshops
-
questionnaires
Frage 55
Frage
Perform Quantitative Risk Analysis is the process of numerically analyzing the combined effect of identified individual project risk and other sources of uncertainty on overall project objectives.
While conducting this process what data gathering technique(s) are used?
Frage 56
Frage
[blank_start]Interviews[blank_end] may be used to generate inputs for the quantitative risk analysis, drawing on inputs that include individual project risks and other sources of uncertainty.
Antworten
-
Interviews
-
Brainstorming
-
Focus groups
-
Surveys
Frage 57
Frage
During the Plan Risk Response Strategy and while gathering data using interviews it is important to promote an environment of trust and confidentiality in order to encourage honest unbiased decisions.
Frage 58
Frage
Plan Procurement Management is the process of documenting project procurement decisions, specifying the approach and identifying potential sellers.
What data gathering tool(s) and technique(s)are used throughout this process?
Frage 59
Frage
While in the Plan Procurement Management process [blank_start]market research[blank_end] includes examination of industry and specific seller capabilities.
Antworten
-
market research
-
statistical sampling
-
check sheets
-
brainstorming
Frage 60
Frage
Conducting market research while in the Plan Procurement Management process can include some or all of the following sources of information?
Antworten
-
Industry conferences
-
Online reviews
-
Encyclopedias
-
Government agencies
Frage 61
Frage
[blank_start]Questionnaires and surveys[blank_end] are written sets of questions designed to quickly accumulate information from a large number of respondents.
Frage 62
Frage
While conducting the Collect Requirements process when are questionnaires and surveys most appropriate?
Select all that apply.
Antworten
-
When gathering information from varied audiences
-
When analyzing large amount of data
-
When a quick turnaround is needed
-
When respondents are geographically dispersed
-
When trying to acquire detailed data from stakeholders
-
Where statistical analysis could be appropriate
Frage 63
Frage
[blank_start]Surveys[blank_end] may be used to gather data about customer satisfaction after deployment of a product or service.
Antworten
-
Surveys
-
Focus groups
-
Checklists
-
Brainstorming
Frage 64
Frage
The cost regarding defects identified in surveys may be considered external failure costs in the COQ model and can have extensive cost implications for the organization.
Frage 65
Frage
[blank_start]Statistical sampling[blank_end] is choosing part of a population of interest for inspection.
Antworten
-
Statistical sampling
-
Focus groups
-
Benchmarking
-
Interviews
Frage 66
Frage
While conducting the Control Quality process selecting 10 engineering drawings at random from a list of 75 is an example of what type of data gathering technique.?
Frage 67
Frage
While conducting the Control Quality process and gathering data using statistical sampling technique, the sample frequency and sizes should be determined in the Plan Quality Management process.