Zusammenfassung der Ressource
Frage 1
Frage
The following is true about the WBS:
Antworten
-
a. The WBS is another term for the Gantt chart.
-
b. Each descending level of the WBS represents an increasingly detailed definition of the project work. Correcta
-
c. Work not in the WBS is usually defined in the scope statement of the project.
-
d. The WBS is the bill of materials needed to accomplish the project objectives and created the required deliveralbes.
Frage 2
Frage
Validate scope is closely related to:
Frage 3
Frage
In creating a Work Breakdown Structure (WBS) on the project, the team would consider all of the following applicable except…?
Antworten
-
a. The team and the Project Manager should be involved in creating it.
-
b. It will resemble an organizational chart in appearance when complete.
-
c. The Activity sequencing of the WBS can be done only in parallel. Correcta
-
d. It is a Decomposition of the work of the project.
Frage 4
Frage
Which of the following best describes product analysis?
Antworten
-
a. Working with the customer to determine the product description
-
b. Mathematically analyzing the quality desired for the project
-
c. Gaining a better understanding of the product of the project in order to create the project scope statement
-
d. Determining if the quality standard on the project can be met
Frage 5
Frage
A new call center is being built to support a new product at a satellite Internet company. The company doesn’t have any data associated with the time frames needed to complete a customer order. This data is important because it will help determine the number of employees needed in the call center. The company performs some tests to try to determine how long it will take to complete a customer order. This test data is then incorporated into the projections and planning. What has the company just created?
Antworten
-
a. Staff acquisition
-
b. Constraints
-
c. Assumptions Correcta
-
d. Team development
Frage 6
Frage
All of the following are true about the project scope statement EXCEPT:?
Antworten
-
a. It is an output of Validate Scope. Correcta
-
b. It describes, in detail, the project’s deliverables and the work required to create those deliverables.
-
c. It provides a common understanding of entire project scope among all project stakeholders
-
d. It describes the project’s major objectives.
Frage 7
Frage
An input to the Define scope Process is:?
Frage 8
Frage
The project team and their manager have been working hard to prepare the estimate for the new warehouse project. They have defined the scope of the project and are now working on the Work Breakdown Structure. The Work Breakdown Structure represents what on a project?
Antworten
-
a. The schedule
-
b. The Decomposition of the task list
-
c. The Decomposition of the work of the project
-
d. The task list of the project
Frage 9
Frage
The following is an example of a constraint:?
Antworten
-
a. A predefined budget. Correcta
-
b. The threat of a strike by a subcontractor.
-
c. Relationship with the seller.
-
d. The method used to measure project performance.
Frage 10
Frage
The preparation of the scope baseline can BEST be described as involving:?
Antworten
-
a. The functional managers
-
b. The project team Correcta
-
c. Sponsor and Project manager
-
d. The project expediter