Zusammenfassung der Ressource
Frage 1
Frage
In which process is the initiation of the project authorised?
Frage 2
Frage
When does the process of Directing a Projectformally begin?
Antworten
-
Before Starting up a Project
-
After Starting up a Project
-
After Initiating a Project
-
After Managing a Stage Boundary
Frage 3
Frage
Which of the following products is NOT reviewed by the Project Board when authorising project closure?
Frage 4
Frage
Which role recommends the project closure?
Antworten
-
The Executive
-
The Senior User
-
The Senior Supplier
-
The Project Manager
Frage 5
Frage
Which management product is provided to the Project Board with a request to authorise initiation?
Frage 6
Frage
What is the purpose of an Exception Report?
Antworten
-
Where there is a forecast to exceed tolerance, it is prepared to inform the Project board of the situation.
-
It provides the Project Board with a summary of stage staus at intervals defined by them.
-
It contains the description, impact assessment and recommendations for a request for change or off-specification.
-
When there is a forecast to exceed tolerance, it replaces the plan which is no longer valid.
Frage 7
Frage
How often is the Managing Stage Boundary process invoked?
Antworten
-
At the end of the Starting Up a Project process.
-
At the end of each project.
-
At the end of each stage, except the final one.
-
At the end of each Work Package.
Frage 8
Frage
Who needs the information gathered in Managing a Stage Boundary to assess the continuing viability of a project?
Frage 9
Frage
Which of the following plans listed below is NOT produced or updated in the Managing a Stage Boundary process?
Antworten
-
Exception Plan
-
Next Stage Plan
-
Team Plan
-
Project Plan
Frage 10
Frage
The Project Board may request that the current stage is replanned, and the output from replanning is... which is submitted for Project Board approval?
Antworten
-
a Stage Plan
-
a Project Plan
-
a Team Plan
-
an Exception Plan
Frage 11
Frage
What is a purpose of the Closing a Project process?
Antworten
-
Enable the Project Manager to review whether the project has anything further to contribute.
-
Enable the Project Board to make the decision about whether or not to close the project.
-
Enable the Project Manager to manage the final delivery report.
-
Enable the delivery team to create the specialist products of the final stage.
Frage 12
Frage
How might the Project Manager use the Project Plan during the Closing a Project process?
Antworten
-
To update with actuals from the final stage.
-
To update with forecasts for the final stage.
-
To plan the work to review the post-project benefits.
-
To control and monitor the work of the final stage.
Frage 13
Frage
Which of the following statements represents how the Closing a Project process helps to implement the Risk theme?
Antworten
-
Describes the activity where the procedure for managing threats for the project is defined.
-
Describes the activity where ongoing opportunities for the project's products are passed on to the operational and maintenance teams.
-
Describes the activity where the delivery team report risks to the Project Manager
-
Describes the activity where risks are captured in the Risk Register.