Frage 1
Frage
Which of the following statements about contract termination is FALSE?
Antworten
-
A Early terminations are handled in the Close Project or Phase process.
-
B Contract termination may result from mutual agreement to terminate the contract.
-
C Termination conditions should be documented in the contract.
-
D Contract termination may result from default of one party.
Frage 2
Frage
Which of these statements about contracts is FALSE?
Antworten
-
A A contract is a mutually binding legal agreement.
-
B A contract can include change request handling.
-
C Contracts are used only for complex procurements.
-
D A contract is a legal relationship subject to remedy in the courts.
Frage 3
Frage
Greg needs a good understanding of planned work to determine project purchases. What document will be the most helpful?
Frage 4
Frage
An independent estimate used when conducting procurements is sometimes used to:
Antworten
-
A Establish a budget estimate.
-
B Serve as a benchmark of proposed responses.
-
C Build an order of magnitude estimate.
-
D Confuse prospective sellers.
Frage 5
Frage
Which of the following is an objective of the Control Procurements process?
Antworten
-
A Set limitations of liability
-
B Assess and invoke penalties
-
C Monitor contract performance
-
D Issue individual performance reports
Frage 6
Frage
Which of the following statements about selecting a seller is TRUE?
Antworten
-
A Project teams should select the lowest cost seller.
-
B The selection process should produce one seller for each product.
-
C Selection criteria can be limited to price if the item is available from multiple sellers.
-
D The project manager selects the sellers.
Frage 7
Frage
What is a structured review of the seller's progress to deliver project scope and quality, within cost and on schedule?
Frage 8
Frage
Which of the following terms indicates that the buyer will evaluate the response based on technical factors?
Antworten
-
A Bid
-
B Quote
-
C Tender
-
D Proposal
Frage 9
Frage
Inputs to Conduct Procurements include all of the following EXCEPT:
Frage 10
Frage
The Project Procurement Management Knowledge Area includes all of the following processes EXCEPT:
Frage 11
Frage
Outputs of the Conduct Procurements process do NOT include:
Antworten
-
A Selected sellers.
-
B Qualified sellers.
-
C Agreements
-
D Resource calendar.
Frage 12
Frage
Where can Baird look to find a qualified sellers list?
Antworten
-
A Yellow pages
-
B Project management plan
-
C Procurement management plan
-
D Organizational process assets
Frage 13
Frage
Which of the following is a TRUE statement?
Antworten
-
A T&M contracts are for a fixed amount
-
B T&M contracts can be open-ended
-
C T&M contracts do not reimburse costs
-
D T&M contracts are unilateral
Frage 14
Frage
Which of the following is NOT an organizational process assets update associated with the Close Procurement process?
Antworten
-
A Procurement management plan
-
B Procurement file as a complete set of indexed contract documentation including the closed contract
-
C Deliverable acceptance
-
D Lessons learned documentation
Frage 15
Frage
Which of the following is NOT usually included in a procurement document?
Frage 16
Frage
Company policy requires you to advertise contract needs in your local paper. How does this benefit your project?
Antworten
-
A It can expand the list of potential sellers
-
B It speeds up the source selection process
-
C It makes it easier to contact vendors
-
D It is always a legal requirement
Frage 17
Frage
CPFF is the abbreviation for:
Frage 18
Frage
Which of the following is NOT a tool or technique used with the Close Procurements process?
Frage 19
Frage
Your sponsor wants to know if your contractor has finished a set of deliverables. Where will you find that information?
Frage 20
Frage
Which of the following is NOT an input to the Conduct Procurements process?