Frage 1
Frage
An architect's preliminary estimate of construction cost would consider all of the following EXCEPT:
I. labor and materials supplied by the owner.
II. cooling towers.
III. land acquisition costs.
IV. the architect's fee.
V. metal curtain wall systems
Frage 2
Frage
An architect who prepares a preliminary estimate of construction cost according to the subsystems method
Antworten
-
A. considers one set of subsystems for concrete buildings and a different set for steel buildings.
-
B. can easily analyse the cost of alternative exterior wall systems.
-
C. would most likely use this method during the schematic design phase.
-
D. would be performing an additional service under the AIA Agreement between Owner and Architect.