Frage 1

Frage
An architect's preliminary estimate of construction cost would consider all of the following EXCEPT: I. labor and materials supplied by the owner. II. cooling towers. III. land acquisition costs. IV. the architect's fee. V. metal curtain wall systems
Antworten
  • A. I only
  • B. I and IV
  • C. None, everything would be considred
  • D. III and IV

Frage 2

Frage
An architect who prepares a preliminary estimate of construction cost according to the subsystems method
Antworten
  • A. considers one set of subsystems for concrete buildings and a different set for steel buildings.
  • B. can easily analyse the cost of alternative exterior wall systems.
  • C. would most likely use this method during the schematic design phase.
  • D. would be performing an additional service under the AIA Agreement between Owner and Architect.
Zusammenfassung anzeigen Zusammenfassung ausblenden

ähnlicher Inhalt

10 Mind Mapping Strategien für Lehrer
AntonS
Stoffwechsel/Energieumsatz
Anja Buster
UML - Diagramme
futurebase
Vererbung
Greta Warnke
Sturm und Drang & Empfindsamkeit
Julia Schaffhirt
Euro-FH // Zusammenfassung SOPS1
Robert Paul
Abitur Lernplan 2017
Justin Nolte
Vetie - Tierzucht & Genetik - T IV
Fioras Hu
Tierseuchenbekämpfung 2017
Birte Schulz
Vetie Pharma Übungsfragen 2019/2020
Maite J
Vetie Innere Medizin 2020
Ferdinand Kähn