used if there is a risk that a party suffering loss
of revenue/ profit of any nature if completion of a
project is delayed by fire or other insurable peril
Contractors all risk
physical damage all risk policy on the
materials used in the construction works
effective during contract up to PC - can b
ext through an agreed maintenance period
Financial cover for losses that fall directly on the insured party
LIABILITY
Employers Liability
covers the legal liability of the employer for any
illness, injury or death suffered by their employees
Annual basis - not for specific projects -
but most EL insurance issued on 'cautation'
basis.
'causation' basis = the policy is in force at the time any
event giving rise to a claim is caused that will have to
meet the claim
e.g. illness may take years to surface
if MC doesnt prove that he has taken out
insurance - emp can take it out and charge
MC
compulsory since COMPULSORY INSURANCE ACT 1969
Public Liability
covers indemnity for damages/
compensation arising from accidental
injury to 3rd parties (not employees) or
accidental damage 2 property arising in
connection with a project
insurance from beginning to PC + maintenance period
'Occurrance' basis = the policy in force from the time
of the injury/ damage will respond
Professional Imdenity
used for award of
damages/costs/settlement for negligene
IF NOTHING IS INSERTED = 'THE AGGREGATE
AMOUNT
FOR ANY ONE PERIOD OF INSURANCE'
if NO is inserted then none is required
financial cover for the legal liabilities that
the insured party owes the others
SUBROGATION
Legal technique where the insurer steps into the shoes of the
insured in order to take the benefit of any legal right or remedies
that may have against 3rd party responsible for the loss
use in loss insurances
JOINT NAMES
where the employer & contractor are insured under the same policy
it stops the insurer having the right of subrogation
against the other party if they caused loss
JCT Insurances
Schedule 6 and 3
requires insurances to cover claims
INSURANCES ARE STATED IN THE CONTRACT PARTICULARS
DANGERS OF ADVISING ON INSURANCES
The case of Pozzolanic Lytag Ltd v Bryan Hobson Associates served to highlight the
dangers of a construction practitioner taking on responsibility for insurance matters, even
inadvertently
To protect against these risks
include a specific exclusion with regard to advising on insurance in their terms of appointment
never advise on insurance without qualifying that advice to the extent that it should be
verified by an appropriately qualified and regulated specialist
THREE OPTIONS FOR INSURING THE WORKS IN JCT
OPTION A
insurance of new works by contractor
for new works
the contractor takes out the insurance
it is in joint names
it maintained until PC
the MC will only receive the value paid out by the insurers for
reinstatement, if the cost is greater than that they bear the loss
'ALL RISKS'
OPTION B
insurance of new work by employer
for new works
emp takes out policy
it may be used by freq developers who may
have a lower premium
any reinstatement works r treated as a variation &
the emp has 2 pay the actual value if that is more than
the insurance policy they bear the cost
'ALL RISKS'
any physical loss/ damage 2 work executed and site materials and
against reasonable cost of the removal and disposal of debris
OPTION C
Insurance of works to an existing building by the employer
for works 2 extg structures
joint names
'SPECIFIED PERILS'
new works have 2 b insured for all risk and specified perils
Specified perils are defined in clause 6.8 in JCT and inc fire/ lighting/
explosion/ flood/ storm/ earthquake/ riot & civil commotion
the ext structure only has to be insured for specified perils
PROCEDURE IF LOSS/DAMAGE OCCURS
contractor notify CA sating nature/location & extent of damage
valuations of wrks take NO ACCOUNT of damage - as if nothing has happened
once insurers have made inspection the contractor should
repair/restore/replace anything damaged b4 proceeding with works
MC paid for reinstatement works through interim certificates
under option A the contractor must enable the insurers to pay out
under options B & C they received the value of carrying out the works valued as a variation
TERRORISM COVER
insurance provided in joint names 4 physical loss/ damage to work
executed, site materials, ext structures & contents caused by
terrrorism
JCT clause 6.8
PROCEDURE IF COVER IS NOT AVAILABLE
immediately inform the other party that cover has ceased
b4 expiry - emp has to notify the MC in writing that they either
want the works 2 b carried out or terminate the MC contract.
if the contract is not terminate and works suffer loss/damage from terroism
the MC shall repair/restore/replace damaged work and proceed with the works
reinstatement to be treated as a variation
£ not 2 b reduced due to any act of negligence on the part of MC
in the case of ext buildings, the work must b reinstated but any damage
to ext structures is not obliged 2 b reinstated
applicable for options A B C
JOINT FIRE CODE
set out standards & procedures 2 b followed 2 min the occurences of accidental/ malicious fires
reduce the incidences of fire in construction related work. by designing out
taking simple precautions & adopting safe working practices it argues that the
majority of fire c b prevented
JCT clauses 6.13 to 6.16
insurance company requires it and it can make a policy cheaper
Applies to Contract values over £2.5m bit insurance companies also want it 4 smaller projects
LARGE PROJECT = over £20m or a smaller proj if req by insurers - they always decide
if prj if LARGE its stated in contract particulars
the MC has to provide bells/whistles/portable fire ext etc if code applies
if the proj is really large - MC provides fire marshalls
the emp is responsible to getting their people to complie and vise versa for MC people
PROCCES FOR NON-COMPLIANCE WITH CODE
MC must carry out req remedial measures of the
insurerer by the req date
if a variation is req. 4 remedial
measures it should be issued
if MC doesn't begin remedial wrks in 7days the emp can
employ others and charge the MC for the expense
A FIRE INSURANCE valuation should be the
value of reinstatement works
inc. cost of demos/ cleaning away/
rebuilding the ext design in modern
materials using modern methods 2 a
stndard equal 2 the existing property & in
accordance with current building regs