Critical path: The path of activities which represent the [blank_start]longest[blank_end] total time required to complete the project. A delay in an activity on the critical path causes a delay in the [blank_start]entire project[blank_end].
Answer
longest
shortest
entire project
preceding activity
parallel activities
Question 3
Question
Finish to start lag: The minimum amount of time that must pass between the [blank_start]finish[blank_end] of one activity and the [blank_start]start[blank_end] of its successor(s)
Answer
finish
start
finish
start
Question 4
Question
The variance in the project completion time can be calculated by [blank_start]summing[blank_end] the variances in the completion times of the activities in the critical path
Answer
subtracting
summing
multiplying
Question 5
Question
The normal distribution assumption holds if the number of activities in the path is large enough for the [blank_start]central limit theorem[blank_end] to be applied.
Answer
central limit theorem
Question 6
Question
The following times for completion an activity have been estimated.
Optimistic time: 4 days
Most likely time: 7 days
Pessimistic time: 10 days.
The variance in the expected time is [blank_start]1[blank_end] days.
Answer
1
Question 7
Question
When preparing a Work Breakdown Structure, continue to subdivide components until the lowest level component requires between [blank_start]8[blank_end] and [blank_start]80[blank_end] hours of work.
Answer
8
80
Question 8
Question
When components of a WBS are defined in sufficient detail for management and planning purposes, they are known as [blank_start]work packages[blank_end].
Answer
work packages
Question 9
Question
High level elements in the WBS should match, word for word, nouns used to describe outcomes in the [blank_start]scope statement[blank_end].
Answer
scope statement
Question 10
Question
The current activity has an Early Start of March 1st and a duration of 3 days.
The succeeding activity has an Early Start of March 7th. Assuming everyday is a work day, then the free float is [blank_start]3[blank_end] days.