Pregunta 1
Pregunta
Identify the example that would not usually be considered a project.
Respuesta
-
building a house
-
developing a computer software application program
-
hosting a wedding reception
-
assembly line manufacturing of automobiles
Pregunta 2
Pregunta
According to the authors, the prime objectives of project management are
Respuesta
-
scope, cost, time
-
quality, scope, schedule
-
customer satisfaction, budget, schedule
-
cost, quality, customer satisfaction
Pregunta 3
Pregunta
In a conventional project lifecycle, as work progresses, uncertainty about the expected outcome should
Respuesta
-
become a constant
-
decrease
-
increase
-
be fully removed
Pregunta 4
Pregunta
The attributes that characterize a project are
Respuesta
-
purpose, repetition, inter-dependencies, consistency, uncertainty, conflict, and one¬time occurrence
-
life cycle, schedule, cost, uncertainty, independence, uniqueness, and purpose
-
resources, uniqueness, conflict, inter-dependencies, one-time occurrence, and finite duration,
-
purpose, life cycle, conflict, certainty, independence, performance, and finite duration
Pregunta 5
Pregunta
The "stretched-5" pattern observed during the project lifecycle, for the most part, is a result of the
Respuesta
-
changing levels of resources used during successive stages of the project lifecycle
-
changing attitudes of the people who work in the project
-
difficulty in performing the individual activities of a project
-
principle that work expands to fill the allotted time
Pregunta 6
Pregunta
The desired outcomes or results of a project are called
Respuesta
-
subgroups
-
work packages
-
subprojects
-
deliverables
Pregunta 7
Pregunta
Earned value is based on the concept that the percentage of project completion is closely correlated with
Respuesta
-
the number of levels in the project
-
relevance of the project
-
cost or the use of resources
-
final assembly of the output
Pregunta 8
Pregunta
Which of the following is not one of the four dimensions of project success?
Respuesta
-
opening new opportunities for the future
-
number of people working on the project
-
impact on the customer
-
business impact on the organization
Pregunta 9
Pregunta
The project to construct a highway is unique because
Respuesta
-
the characteristics of terrain will be different for different segments
-
consistency of the concrete will vary for different segments
-
different types of laborers will be used to build various segments of the highway
-
different people manage different sections of the highway
Pregunta 10
Pregunta
Projects often interact with other projects being carried out simultaneously within the organization and these interactions take the form of competition for scarce resources between project. This is an example of project
Respuesta
-
bottleneck
-
breakdown
-
interdependencies
-
malfunctioning
Pregunta 11
Pregunta
When done properly, project management begins with
Pregunta 12
Pregunta
The chance that project processes or outcomes will not turn out as planned is called
Respuesta
-
risk
-
projecting
-
effort
-
negative outcome
Pregunta 13
Pregunta
Having only partial or no information about the situation or outcomes is called
Respuesta
-
uncertainty
-
risk
-
effort
-
cluelessness
Pregunta 14
Pregunta
Relations between organizational functions, where one function or task is dependent on others, are known as
Respuesta
-
interdependencies
-
links
-
projects
-
tasks
Pregunta 15
Pregunta
The of the project team is a crucial but unstated element of ancillary trade-
offs that the project manager must consider.
Pregunta 16
Pregunta
The project is generally credited with beginning the era of modern project
management
Respuesta
-
Manhattan
-
Chicago
-
Great Wall of China
-
Egyptian pyramids
Pregunta 17
Pregunta
is a subset of a project consisting of work packages
Respuesta
-
task
-
program
-
project
-
process
Pregunta 18
Pregunta
Projects are bound by the three objectives of scope, time, and cost. These are collectively referred to as the
Respuesta
-
Triple Constraint
-
Triple Factors
-
Three Constraints
-
Triple Play
Pregunta 19
Pregunta
Individuals or groups with a special interest in a project are called
Respuesta
-
stakeholders
-
project managers
-
leaders
-
directors
Pregunta 20
Pregunta
The production of weekly employment reports or the delivery of mail could be considered a
Respuesta
-
project
-
non-project
-
quasi-projects
-
triple projects
Pregunta 21
Pregunta
Which of the following demonstrates the quality of flexibility required of a project selection model?
Respuesta
-
It does not require special interpretation, data that are difficult to acquire, or excessive personnel.
-
It gives valid results within the range of conditions that the firm might experience.
-
It reflects the multiple objectives of both the firm and its managers.
-
It deals with situations both internal and external to the project.
Pregunta 22
Pregunta
The two basic types of project selection models identified in the text are
Respuesta
-
biased and unbiased
-
numeric and nonnumeric
-
active and passive
-
numeric and qualitative
Pregunta 23
Pregunta
If a system is being updated due to operating necessity, the project was selected because
Respuesta
-
the system is worth saving at any cost
-
the system is worth saving at the estimated cost of the project
-
the dimension of cost is not relevant to execution of the project
-
the cost overruns can be hidden in someone else's budget
Pregunta 24
Pregunta
The drawback of the ___________ model is that it fails to consider cash flows obtained once the initial investment has been recovered.
Respuesta
-
payback period
-
average rate of return
-
discounted cash flow
-
profitability index
Pregunta 25
Pregunta
If the NPV for a project is < 0, it indicates that the project will
Pregunta 26
Pregunta
Scoring models are most often used to overcome this disadvantage of profitability models.
Respuesta
-
The inability to account for the time value of money
-
The inability to account for project results beyond the payback period
-
The inability to account for multiple decision criteria
-
The inability to account for cash flow
Pregunta 27
Pregunta
Firms usually have two or more projects and this collection of projects is referred to as
Respuesta
-
a portfolio
-
an initiation
-
a program
-
a stochastic model
Pregunta 28
Pregunta
A technique useful for developing numeric values that are equivalent to subjective, verbal measures of relative value is the
Respuesta
-
Delphi system
-
expert system
-
portfolio
-
simulation
Pregunta 29
Pregunta
Which of the following is a type of numeric model?
Pregunta 30
Pregunta
The _________ is the value of an opportunity foregone
Respuesta
-
real option
-
profit
-
opportunity cost
-
revenue
Pregunta 31
Pregunta
The _________ is the interest rate set by an organization as the minimum acceptable rate of return for a project
Respuesta
-
hurdle rate
-
acceptable rate
-
internal rate of return
-
net present value
Pregunta 32
Pregunta
In a project portfolio, _______________ projects have objectives or deliverables that are only
incrementally different in both product and process from existing offerings.
Respuesta
-
breakthrough
-
R&D
-
platform
-
derivative
Pregunta 33
Pregunta
In a project portfolio, a project that involves a new technology or even a disruptive technology that is known to the industry would serve as an example of a project
Respuesta
-
breakthrough
-
R&D
-
platform
-
derivitive
Pregunta 34
Pregunta
The set of documents submitted when evaluating a project is referred to as the
Respuesta
-
project proposal
-
evaluation set
-
evaluation criteria
-
project manual
Pregunta 35
Pregunta
When the decision maker's information is not complete, he/she will have to make a decision under conditions of
Respuesta
-
proof
-
uncertainty
-
management
-
risk mitigation
Pregunta 36
Pregunta
The discounted cash flow method determines the net present value of all cash flows by discounting them by the
Respuesta
-
hurdle rate
-
acceptable rate
-
internal rate of return
-
net present value
Pregunta 37
Pregunta
Financial forecasts are reported as __________ financial statements.
Respuesta
-
final
-
initial
-
pro forma
-
hypothetical
Pregunta 38
Pregunta
A project selection criteria that focuses on how well new products would fit the firm's existing product line would be
Pregunta 39
Pregunta
According to research by Sanchez and Robert (2010), which of the following is not a reason why strategic benefits may be difficult to appraise?
Pregunta 40
Pregunta
________ is a modeling technique for emulating a process, usually conducted a
considerable number of times to understand the process better and measure its outcomes under different policies.
Respuesta
-
Simulation
-
Project management
-
Projectizing
-
Modeling
Pregunta 41
Pregunta
According to the authors, the analytic method, when applied to systems, focuses on
Respuesta
-
assembling the components of a system into an integrated package
-
building an array of individually designed and manufactured components
-
calculating the cost and schedule requirements
-
dividing the components of a system into smaller and smaller elements
Pregunta 42
Pregunta
The ideal project manager should be
Respuesta
-
a direct, technical supervisor knowledgeable in the technology of the process being used
-
both generalist/facilitator and have a high level of technical competence in the science of the project
-
a facilitator and specialist with technical credibility
-
a technical specialist competent in principles of robust design
Pregunta 43
Pregunta
The project manager must make trade-offs between project progress and process. Conceptually, this involves trade-offs between the _______ functions.
Respuesta
-
technical and managerial
-
schedule and cost
-
performance and schedule
-
cost and performance
Pregunta 44
Pregunta
According to the authors the project manager should be more skilled at
Respuesta
-
general management
-
technology
-
synthesis
-
analysis
Pregunta 45
Pregunta
The project manager needs _______ credibility.
Pregunta 46
Pregunta
Projects are conducted in four important environments. They are
Respuesta
-
economic, political, legal, and sociotechnical
-
internal, external, transitional, and multicultural
-
routine, unique, fast-paced, and complex
-
profit, not for profit, government, and industry
Pregunta 47
Pregunta
According to the authors, the key to coping with uncertainty at the end of a project (a common obstacle for project managers) is
Respuesta
-
discipline
-
communication
-
planning
-
supervision
Pregunta 48
Pregunta
During the buildup phase, the project goals, in order of importance, are
Respuesta
-
schedule, scope, cost
-
cost, schedule, scope
-
schedule, cost, scope
-
cost, scope, schedule
Pregunta 49
Pregunta
Resources initially budgeted for a project are frequently _________ for the task, partly because of natural optimism by the proposer about how many resources are needed.
Respuesta
-
sufficient
-
delayed
-
insufficient
-
hindrances
Pregunta 50
Pregunta
Most of the time spent by a project manager is spent
Pregunta 51
Pregunta
11. The functional manager uses the ________ approach and the PM uses the ________ approach
Respuesta
-
systems; analytic
-
numerical; nonnumeric
-
analytic; systems
-
nonnumeric; numerical
Pregunta 52
Pregunta
The project manager's responsibility to the project and to the client is met by ensuring that the _______ of the project is preserved in spite of conflicting demands made by stakeholders.
Respuesta
-
management
-
integrity
-
analysis
-
synthesis
Pregunta 53
Pregunta
During the final or phaseout stage of the project lifecycle, ___________ is the dominant goal of many project managers.
Respuesta
-
schedule
-
cost
-
scope
-
quality
Pregunta 54
Pregunta
The structure of a society is determined by its
Respuesta
-
institutions
-
wages
-
jobs
-
enemies
Pregunta 55
Pregunta
Which of the following is not a phase in the Tuckman ladder?
Respuesta
-
forming
-
defining
-
norming
-
mourning
Pregunta 56
Pregunta
The _________ is a person who spearheads an idea or action and sells it throughout the organization.
Respuesta
-
stakeholder
-
champion
-
interviewer
-
coach
Pregunta 57
Pregunta
The ______________ is an alternative action if the expected result fails to materialize.
Respuesta
-
trade-off
-
system plan
-
feedback
-
contingency plan
Pregunta 58
Pregunta
The __________ represents everything outside the system that delivers inputs or
receives outputs from the system.
Respuesta
-
environment
-
feedback
-
culture
-
system
Pregunta 59
Pregunta
The __________ is the "corporate culture" within the organization, or even within the
project
Respuesta
-
cultural anomaly
-
microculture
-
multiculture
-
interfirm culture
Pregunta 60
Pregunta
The project manager makes a ___________ by allowing one aspect of the project to get
worse in return for allowing another aspect of the project to get better.
Respuesta
-
decision
-
turnaround
-
trade-off
-
chart
Pregunta 61
Pregunta
A party to a conflict will usually be satisfied when the level of frustration has been
Respuesta
-
increased by the domination of the other party
-
lowered to the point where no action against the other party is contemplated
-
lowered because the party realizes the hopelessness of continuing the conflict
-
eliminated because the party has surrendered to the other party
Pregunta 62
Pregunta
Most of the conflicts that involve the organization and outsiders have to do with
Respuesta
-
interpersonal differences
-
cultural differences and status differences
-
technical differences
-
property rights and contractual obligations
Pregunta 63
Pregunta
During project formation, the organizational structure selected will have a major impact on the ways in which conflicts are handled. Lack of clarity about the relative power/influence/authority of the PM and the functional managers is a major component of all conflicts involving
Pregunta 64
Pregunta
If a resource conflict arises between two high-priority projects, precedence is typically given to the project with the
Respuesta
-
earliest due date
-
fastest completion time
-
biggest revenue stream
-
lowest cost to complete
Pregunta 65
Pregunta
During project build-up, the project should move from a general concept to
Pregunta 66
Pregunta
During project build-up, if the project is independent and standalone, the project manager seeks a commitment of __________ from the functional departments.
Respuesta
-
work
-
materials
-
people
-
budgets
Pregunta 67
Pregunta
During project build-up, if the project is functionally tied down, the project manager seeks a commitment of _________ from the functional departments.
Respuesta
-
work
-
materials
-
people
-
budgets
Pregunta 68
Pregunta
Personality conflicts during project phase-out are often caused by
Respuesta
-
the absence of deadlines
-
the influx of newer technology
-
pressure to complete the project and anxiety about leaving the project
-
distribution of expenses charged to the project
Pregunta 69
Pregunta
According to the authors, the nature of negotiation as it applies to project management is the realization that few of the conflicts arising in projects have to do with
Respuesta
-
whether or not the task will be done
-
the precise design of the deliverable
-
how the design will be achieved
-
who will do the work, when, and at what cost
Pregunta 70
Pregunta
When dealing with conflict between parties, it is recommended that one _______ in order to avoid the conflict becoming interpersonal.
Pregunta 71
Pregunta
Partnering is an attempt to _________ the risk associated with sub-contracting.
Respuesta
-
mitigate
-
Increase
-
absorb
-
allow
Pregunta 72
Pregunta
_________ is the process which begins when one party perceives that the other has frustrated, or is about to frustrate, some concern of his.
Respuesta
-
conflict
-
happiness
-
contentment
-
utility
Pregunta 73
Pregunta
According to the authors, the favored technique for resolving conflict is
Respuesta
-
negotiation
-
mitigation
-
avoidance
-
collaboration
Pregunta 74
Pregunta
The process through which two or more parties seek an acceptable rate of exchange for items they own or control is called
Respuesta
-
negotiation
-
mitigation
-
compromising
-
collaboration
Pregunta 75
Pregunta
During the early program phases of the project lifecycle, Thamhain et al say that conflict intensity is the greatest with respect to
Respuesta
-
cost
-
schedules
-
scope
-
quality
Pregunta 76
Pregunta
During the main program phases of the project lifecycle, Thamhain et al say that conflict intensity is the greatest with respect to
Respuesta
-
cost
-
schedules
-
scope
-
quality
Pregunta 77
Pregunta
Toward the end of the project lifecycle, Thamhain et at say that conflict intensity is the greatest with respect to
Respuesta
-
cost
-
schedules
-
scope
-
quality
Pregunta 78
Pregunta
Negotiating to a(n) __________ solution is the key to conflict resolution in project management.
Respuesta
-
win-lose
-
win-win
-
avoidance
-
confrontation
Pregunta 79
Pregunta
The total level of conflict in the project lifecycle is highest during the _________ stage
Respuesta
-
closing
-
main program
-
project build-up
-
project formation
Pregunta 80
Pregunta
The ___________ approach to negotiation aims to achieve a win-win result.
Respuesta
-
principled
-
posititional
-
stakeholder
-
paretto
Pregunta 81
Pregunta
If the project manager controls when and what people do while the functional managers control who will be assigned to the project and what technology will be used, the ______organizational form is probably being used.
Respuesta
-
projectized
-
pure project
-
matrix
-
weak project
Pregunta 82
Pregunta
In the systems approach to design, one organization would have to take responsibility for
Respuesta
-
manufacturing everything in the system
-
the integrity of the project design
-
the integrity of the subcontractors
-
product warranties
Pregunta 83
Pregunta
The process of dealing with uncertainties in projects that may affect the project for better or for worse has come to be known as
Respuesta
-
scope management
-
risk management
-
quality management
-
procurement management
Pregunta 84
Pregunta
A common objective of an organization's PM is often created by organizations to
Respuesta
-
establish consistent project management standards and methods
-
deal with technological obsolescence
-
train process managers
-
administer application software
Pregunta 85
Pregunta
A major purpose of the project management office should be to serve as
Respuesta
-
the central location for all clerical support
-
the critical disaster recovery support
-
a link between strategic management and project management
-
maintenance for the project management library
Pregunta 86
Pregunta
This member of the project team is in charge of product design and development and is responsible for functional analysis, specifications, drawings, cost estimates, quality/reliability, engineering changes, and documentation
Respuesta
-
systems architect
-
manufacturing engineer
-
project controller
-
support services manager
Pregunta 87
Pregunta
This member of the project team is responsible for the efficient production of the product of the process, including the manufacturing engineering, design and production of tooling, production scheduling, and other production tasks
Respuesta
-
project engineer
-
development engineer
-
contract administrator
-
support services manager
Pregunta 88
Pregunta
This person is responsible for the installation, testing, and support of the product (process) once its engineering is complete.
Respuesta
-
development engineer
-
systems architect
-
test engineer
-
project controller
Pregunta 89
Pregunta
One of the main technical problems faced by the project manager is meeting ________ without compromising performance.
Respuesta
-
supplier's targets
-
schedule and cost goals
-
technical specifications
-
cost and conflict goals
Pregunta 90
Pregunta
A major advantage of using a _________ placement for a project is that individual
experts can be utilized by many different projects.
Respuesta
-
standard
-
virtual
-
projectized
-
functional
Pregunta 91
Pregunta
Virtual teams, when composed, should consist of "boundary spanners" who number about one in every _________ team members
Pregunta 92
Pregunta
When a firm engages in a large number of similar projects, the ___________ organizational form is apt to be preferred.
Respuesta
-
pure project
-
partial matrix
-
functional
-
mixed matrix
Pregunta 93
Pregunta
When the standard departments of the organization represent individual disciplines such as engineering, marketing, purchasing, and so on, the organization follows
Respuesta
-
projectized management
-
matrixed management
-
functional management
-
mixed management
Pregunta 94
Pregunta
The firm or organization within which the project is being conducted is known as the
Respuesta
-
parent organization
-
consulting firm
-
project team
-
stakeholder company
Pregunta 95
Pregunta
______________ engineering refers to the use of a design team that includes design and manufacturing engineers as well as staff from other relevant areas of the business.
Respuesta
-
Concurrent
-
Alignment
-
Matrix
-
Social
Pregunta 96
Pregunta
The _________ is a basic project document that describes all the work that must be done to complete the project and forms the basis for costing, scheduling, and work
Respuesta
-
WBS
-
OBS
-
PMO
-
project charter
Pregunta 97
Pregunta
The approach to organizing that includes both functions (disciplines) and projects in its hierarchy is known as the
Respuesta
-
mixed organization
-
functional organization
-
projectized organization
-
matrix organization
Pregunta 98
Pregunta
This person's task is the efficient production of the product or process the project engineer has designed, including responsibility for manufacturing engineering, design and production of code, unit testing, production scheduling, and other production tasks.
Respuesta
-
test engineer
-
contract administrator
-
development engineer
-
systems architect
Pregunta 99
Pregunta
TQM and Six Sigma are good examples of ____________ programs
Respuesta
-
participative
-
exclusive
-
frequency
-
inclusive
Pregunta 100
Pregunta
If both functional and projectized divisions coexist in a firm, this would result in the __________ organizational structure.
Respuesta
-
composite
-
objective
-
encompassing
-
free-form
Pregunta 101
Pregunta
The _________ is a specialized view of the action plan that focuses on who has what
responsibility for each project task.
Pregunta 102
Pregunta
The success of the project launch meeting is dependent on the existence of
Respuesta
-
a project charter
-
the project's scope statement
-
a well-defined set of objectives for the project
-
project planning templates
Pregunta 103
Pregunta
This project plan element describes both the managerial and the technical approaches to the work. The technical discussion describes the relationship of the project to available technologies.
Respuesta
-
overview
-
objectives
-
general approach
-
contractual aspects
Pregunta 104
Pregunta
This project plan element should include profit and competitive goals as well as technical goals.
Respuesta
-
overview
-
objectives
-
general approach
-
contractual aspects
Pregunta 105
Pregunta
The _______ of a project includes the objectives of the project as well as the time and cost required to complete the project to the customer's satisfaction.
Respuesta
-
scope
-
change order
-
outcome
-
purpose
Pregunta 106
Respuesta
-
responsive, accountable, consult, inform
-
responsible, accountable, consult, inform
-
responsive, accountable, consult, integrate
-
responsible, admissible, consult, integrate
Pregunta 107
Pregunta
The set of physical elements required to build a project is called the
Respuesta
-
bill of materials
-
deliverable
-
milestone list
-
work statement
Pregunta 108
Pregunta
___________ is an approach that breaks the planning task down into the activities that must be done in each managerial level of the organization. Typically, the upper level sets the objectives for the next lower level.
Respuesta
-
Strategic planning
-
Organizational planning
-
Hierarchical planning
-
Agile planning
Pregunta 109
Pregunta
The major tool that a project manager uses during the planning phase is called the
Respuesta
-
WBS
-
change request
-
scope statement
-
project plan
Pregunta 110
Pregunta
___________is the tendency for the project objectives to be changed with little or no discussion with other parties actively engaged in the project
Respuesta
-
Scope reference
-
Scope creep
-
Effectiveness
-
Hierarchical planning
Pregunta 111
Pregunta
_______________ is a visual approach that closely mirrors how the human brain records and stores information that can help tap the creative potential of the entire project team
Respuesta
-
WBS generation
-
Project planning
-
Risk response planning
-
Mind mapping
Pregunta 112
Pregunta
When using a WBS, all of the work should roll up to the next level such that no extra work is required. This is referred to as the
Respuesta
-
Development rule
-
All-inclusive rule
-
100% rule
-
WBS rule
Pregunta 113
Pregunta
For projects that are constantly changing, the __________ methodology is recommended
Respuesta
-
waterfall
-
agile
-
adaptable
-
organic
Pregunta 114
Pregunta
Having key stakeholders involved early in the project tends to
Pregunta 115
Pregunta
When using the mind mapping process, you should designate one team member as the ___________ to ensure that all team members are involved and contributing, and to ensure that team members are focusing on the work that must be done.
Respuesta
-
planner
-
facilitator
-
contractor
-
manager
Pregunta 116
Pregunta
A useful tool for facilitating the management of changes to a project's scope is the
Pregunta 117
Pregunta
A project manager must ___________ as a type of risk response planning in order to soften the danger of a threat by reducing the likelihood that it will occur or by reducing its impact if it does occur.
Respuesta
-
avoid
-
transfer
-
accept
-
mitigate
Pregunta 118
Pregunta
The ____________ is a list of the project activities with major activities broken down into subactivities.
Pregunta 119
Pregunta
The process of coordinating the work and timing of the different groups working on multidisciplinary teams is called
Respuesta
-
procurement management
-
integration management
-
vertical management
-
matrix management
Pregunta 120
Pregunta
This element of the project plan contains a brief description of the procedure to be followed in monitoring, collecting, storing, and evaluating the history of the project
Respuesta
-
schedule
-
resources
-
personnel
-
evaluation methods
Pregunta 121
Pregunta
If a project budget is under funded, it will often
Respuesta
-
stimulate increased performance
-
improve utilization of resources
-
frustrate committed stakeholders
-
reduce costs
Pregunta 122
Pregunta
The project's budget should
Respuesta
-
associate resource use with the achievement of organizational goals
-
allow funds to be spent without linkage to achievement
-
not reflect the timing of expenses associated with the use of resources
-
never be changed during project execution
Pregunta 123
Pregunta
In order to develop a budget, the PM must forecast
Pregunta 124
Pregunta
A work element whose cost is fully developed would
Respuesta
-
exclude the cost of labor and resources
-
include only the profit and direct costs
-
exclude the cost of special machinery and overheads
-
include direct costs plus overhead and G&A charges
Pregunta 125
Pregunta
The traditional organizational budget is
Pregunta 126
Pregunta
__________ budgeting allows income and expenditures to be aggregated across projects.
Respuesta
-
Category-oriented
-
Activity-oriented
-
Project-oriented
-
Expense-oriented
Pregunta 127
Pregunta
The authors identify ____________ estimation errors as the two types of generic estimation errors.
Respuesta
-
small and large
-
random and planned
-
certain and uncertain
-
random and biased
Pregunta 128
Pregunta
The pattern of deviations in cost and usage used for exception reporting to management is called
Respuesta
-
simulations
-
assumptions
-
variances
-
summaries
Pregunta 129
Pregunta
___________ costs vary with output.
Pregunta 130
Pregunta
Unless the project manager is familiar with the firm's ______________ it will be very difficult to exercise budget control.
Respuesta
-
accounting system
-
budget plans
-
marketing procedure
-
cost accounting
Pregunta 131
Pregunta
The __________ form of budgeting has the advantage of using individuals closer to the work to provide estimates of resource requirements.
Respuesta
-
top-down budgeting
-
work element costing
-
bottom-up budgeting
-
iterative budgeting
Pregunta 132
Pregunta
The ___________ charge is composed of the costs of senior management, the various data functions, and any other expenses not included in overhead. Often, these charges are a fixed percentage of either the direct costs or the total of all direct and indirect costs.
Respuesta
-
salary
-
project management
-
ethical
-
G&A
Pregunta 133
Pregunta
Each time the output doubles, the worker hours per unit decrease to a fixed percentage of their previous value. That percentage is called the ___________ rate.
Respuesta
-
inflation
-
hurdle
-
interest
-
learning
Pregunta 134
Pregunta
Suppose that a person requires 60 minutes to complete a work element on the first attempt. On the second attempt, the work element is completed in 48 minutes. The learning rate for this person is _________% for this work element
Pregunta 135
Pregunta
_____________ relies on well-known statistical correlations between various factors such as the total cost of a house relative to the square feet of living area.
Respuesta
-
Parametric estimating
-
Statistical equivalence
-
Bottom-up estimating
-
Top-down estimating
Pregunta 136
Pregunta
A budget strategy that is based on collecting the judgments and experiences of top and middle managers is referred to as the ___________ approach or method.
Respuesta
-
parametric estimating
-
statistical equivalence
-
bottom-up estimating
-
top-down estimating
Pregunta 137
Pregunta
________________ are where the defined responses to the risks are detailed, but their amounts are not
yet precisely known.
Respuesta
-
Known-unknowns
-
Unknown-knowns
-
Known-knowns
-
Unknown-unknowns
Pregunta 138
Pregunta
Unknown-unknowns are not part of the baseline budget and are referred to as
Respuesta
-
management reserves
-
contingency reserves
-
PMBOK reserves
-
Buffered reserves
Pregunta 139
Pregunta
The advantage of the ____________ process is that it is generally associated with participative management
Respuesta
-
bottom-up
-
top-down
-
Murphy's
-
Efficient
Pregunta 140
Pregunta
______________ issues are present when bidders "low-ball" a bid or when some bidders get a "last look."
Respuesta
-
Ethical
-
Strategic
-
Efficient
-
Effective
Pregunta 141
Pregunta
The authors recommend preparing a schedule for each
Pregunta 142
Pregunta
In the AOA network, circles depict
Respuesta
-
networks
-
events
-
logical dependencies
-
dummy activities
Pregunta 143
Pregunta
The shortest time in which the entire network can be completed is referred to as the
Respuesta
-
critical time of the network
-
real duration of the network
-
elapsed time of the network
-
slack time of the network
Pregunta 144
Pregunta
A precedence relationship where the completion of a successor activity depends on the completion of a predecessor activity is called a
Respuesta
-
start to finish dependency
-
finish to start dependency
-
finish to finish dependency
-
start to start dependency
Pregunta 145
Pregunta
A precedent relationship where the completion of a predecessor activity depends on the initiation of a successor activity is called a
Respuesta
-
start to finish dependency
-
finish to start dependency
-
finish to finish dependency
-
start to start dependency
Pregunta 146
Pregunta
The difference between the late start and early start for an activity is called its
Respuesta
-
critical path
-
task
-
progress
-
float
Pregunta 147
Pregunta
A(n) __________ is the conversion of the project work breakdown structure into an operating timetable.
Respuesta
-
chart
-
application
-
crash
-
schedule
Pregunta 148
Pregunta
A(n) _________ is a specific task or set of tasks that are required by the project, use up resources, and take time to complete
Respuesta
-
milestone
-
activity
-
node
-
path
Pregunta 149
Pregunta
The arrangement of all activities (and, in some cases, events) in a project arrayed in their logical sequence and represented by arcs and nodes is called a
Respuesta
-
network
-
critical path
-
path
-
crashed path
Pregunta 150
Pregunta
In a network, if the delay of an activity will delay completion of the project, the activity is called a(n)
Respuesta
-
valuable
-
efficient
-
critical
-
noteworthy
Pregunta 151
Pregunta
In AOA networks, an activity of zero duration is called a(n)
Respuesta
-
dummy activity
-
critical
-
important
-
critical activity
Pregunta 152
Pregunta
The _____________ chart shows planned and actual progress for a number of tasks displayed against a horizontal timescale.
Respuesta
-
PERT
-
timeline
-
critical
-
Gantt
Pregunta 153
Pregunta
A clearly identifiable point in a project or set of activities that commonly denotes a reporting requirement or completion of a large or important set of activities is called a(n)
Respuesta
-
milestone
-
anniversary
-
node
-
dummy activity
Pregunta 154
Pregunta
In AON diagrams, a(n) ________________ is a point where one or more lines (arrows) begin or terminate, commonly used for depicting an event or activity.
Pregunta 155
Pregunta
______________ is the amount of one factor that must be sacrificed in order to achieve more or less of another factor.
Respuesta
-
trade-off
-
synergy
-
barter limit
-
limiting quantity
Pregunta 156
Pregunta
A _____________ is a combination of interrelated activities and events depicted with arcs and nodes.
Respuesta
-
linked plan
-
chain of events
-
critical chain
-
network
Pregunta 157
Pregunta
____________ law suggests that work expands to fill the allotted time.
Respuesta
-
Parkinson's
-
Murphy's
-
Brooks'
-
Federal
Pregunta 158
Pregunta
In application, PERT has primarily been used for
Pregunta 159
Pregunta
The authors define _________ as the time an activity can be delayed without affecting the start time of any successor activity
Respuesta
-
free slack
-
total slack
-
project slack
-
overhead slack
Pregunta 160
Pregunta
__________ is one possible way to check the nature and impacts of interactions between probabilistic paths in a network.
Pregunta 161
Pregunta
If deterministic time estimates are used, and if project deadlines are firm, there is a high likelihood that it will
Respuesta
-
not be necessary to crash any activities in projects
-
be necessary to crash the last few activities of most projects
-
be completed on time and within budget
-
be completed as per schedule
Pregunta 162
Pregunta
Assume two activities, printing and binding. Printing is a predecessor of binding. If printing is _______, then binding will start late by whatever amount of lateness is bequeathed to it by printing.
Respuesta
-
necessary
-
early
-
late
-
time-neutral
Pregunta 163
Pregunta
________ aims to minimize the period-by-period variations in resource loading by shifting tasks within their slack allowances. The purpose is to create a smoother distribution of resource usage.
Respuesta
-
Resource loading
-
Resource leveling
-
Scope loading
-
Resource succeeding
Pregunta 164
Pregunta
A project task is said to be __________ if it requires a fixed amount of time and known quantities of resources
Respuesta
-
scope constrained
-
time constrained
-
resource constrained
-
system constrained
Pregunta 165
Pregunta
One of the problems that Goldratt observed was that if an activity has slack time, the task might become delayed until the slack is removed. This is referred to as
Respuesta
-
Goldratt's Law
-
Murphy's Law
-
the delay game
-
the student syndrome
Pregunta 166
Pregunta
The points between the extreme points of the relationship between time use and resource use represent
Respuesta
-
time constrained projects
-
resource constrained projects
-
alternative trade-offs between time and resources
-
a non-feasible solution space of trade-off alternatives related to time and resource use
Pregunta 167
Pregunta
The _________ technique overlaps the design and build phases of a project to expedite its completion.
Respuesta
-
crashing
-
fast-tracking
-
leading
-
blitzing
Pregunta 168
Pregunta
Most heuristic solution methods start with the _____________ and analyze resource usage period by period, resource by resource.
Respuesta
-
GERT schedule
-
Gantt chart
-
PERT/CPM schedule
-
Master schedule
Pregunta 169
Pregunta
The use of ______________ activity time estimates may reduce the chance that crashing the
project will be needed.
Respuesta
-
one probabilistic
-
two probabilistic
-
three probabilistic
-
four probabilistic
Pregunta 170
Pregunta
The standard practice with AOA and AON is to estimate activity times under the assumption of resource loadings that are
Respuesta
-
probabillistic
-
crashed
-
normal
-
dynamic
Pregunta 171
Pregunta
With respect to project scheduling, __________ is the amount of work waiting to be processed because there is a shortage of some resource.
Respuesta
-
in-process inventory
-
schedule slippage
-
resource utilization
-
management delay
Pregunta 172
Pregunta
If the appropriate scheduling equation for task A of a project were W = D * U, and it was initialized so that W = 40d, D = 10d, and U = 4 resources, and task A is an effort-driven activity, correctly balance this equation if the value for U is changed from 4 to 5. To balance the equation, the altered variable and its new value are
Respuesta
-
D = 6w
-
W = 6d
-
D = 8d
-
W = 8d
Pregunta 173
Pregunta
The principal reason why a project manager is surprised by resource constraints on a project is the failure to include _________ in risk identification activities.
Respuesta
-
resource availability
-
resource cost
-
resource mobility
-
resource skill
Pregunta 174
Pregunta
Which of the following describes a situation where priorities are assigned to activities according to some rule not associated with task length, slack, or resource requirements?
Respuesta
-
student's syndrome
-
arbitrary
-
most successors
-
most resources
Pregunta 175
Pregunta
The two fundamental approaches to constrained allocation problems are
Respuesta
-
heuristic approaches and rules of thumb
-
linear programming approaches and optimization models
-
heuristic approaches and optimization models
-
goal programming and trial and error
Pregunta 176
Pregunta
When crashing a project, our first task is to develop
Respuesta
-
a table or graph of the cost of a project as a function of the project's possible completion dates
-
a schedule that shows the risks associated with each activity in the project
-
a list that shows the activities and the events of a project without referring to the costs
-
a table showing the noncritical activities and the cost associated with each of those activities
Pregunta 177
Pregunta
In some situations, two activities are scheduled to be carried out in parallel and using the same scarce resource. If the supply of the scarce resource is not sufficient to allow both activities to be carried out simultaneously, then whichever of the two is given priority immediately lengthens the other activity's path but not its actual
Respuesta
-
duration
-
slack
-
float
-
buffer
Pregunta 178
Pregunta
The two principles to follow when crashing a project focuses on the
Respuesta
-
critical path and selects the least expensive alternative
-
critical path and selects the most expensive alternative
-
shortest path and selects the least expensive alternative
-
shortest path and selects the most expensive alternative
Pregunta 179
Pregunta
Using Goldratt's meaning of the word "dependent," the activities of a project can be ordered into paths based on their resource dependencies as well as on their technological precedence requirements. The longest of these paths of sequentially time-dependent activities is known as the
Respuesta
-
priority chain
-
critical chain
-
dependency path
-
heuristic path
Pregunta 180
Pregunta
The ___________ heuristic provides a general solution for critical path and time and is usually the default rule for a schedule.
Respuesta
-
as soon as possible
-
as late as possible
-
minimum slack first
-
shortest task first
Pregunta 181
Pregunta
Monitoring, as an activity, should be kept distinct from __________, which uses data supplied by monitoring to bring actual performance into approximate congruence with planned performance.
Respuesta
-
recording
-
controlling
-
collecting
-
reporting
Pregunta 182
Pregunta
An appropriate and common secondary user for monitoring includes
Respuesta
-
auditing, learning from mistakes, and reporting progress and status
-
exercising effective control over the project
-
evaluating current status of the project
-
fixing the blame when things go wrong
Pregunta 183
Pregunta
According to the authors, the key items to be planned, monitored, and controlled are
Respuesta
-
schedule, budget, and financial stability
-
schedule, quality, performance, and customer satisfaction
-
schedule, budget, and feasibility
-
schedule, budget, and performance
Pregunta 184
Pregunta
According to the authors, in the planning - monitoring - controlling cycle, the directions of the flows indicate that
Respuesta
-
information flows from the top to bottom and authority flows from the bottom to the top
-
information flows from the bottom to the top and authority flows from the top to the bottom
-
authority flows from the bottom to the top
-
information flows from the top to the bottom
Pregunta 185
Pregunta
The first step in setting up a monitoring system is to
Respuesta
-
collect existing data to see what data is relevant and available
-
collect every available piece of information so it can be analyzed
-
use whatever information is available
-
identify the key factors to be controlled
Pregunta 186
Pregunta
In earned value analysis, the 50-50 rule assumes that
Respuesta
-
50 percent is earned when the task is half done and 50 percent is earned at completion
-
50 percent is earned when the task begins and 50 percent is earned at completion
-
50 percent is earned when the task begins and 50 percent is earned at the halfway stage
-
50 percent is earned when the project is planned and 50 percent is earned when the project is over
Pregunta 187
Pregunta
In earned value analysis, if the cost variance is (-$10,000),
Respuesta
-
the cost variance is favorable
-
the cost variance is unfavorable
-
the scheduled variance is favorable
-
the scheduled cost avoidance is unfavorable
Pregunta 188
Pregunta
One of the most common errors when collecting data is
Respuesta
-
collecting rapidly changing data frequently
-
collecting data infrequently because data collection is so time consuming
-
collecting data that rarely changes
-
reporting to management after collecting data
Pregunta 189
Pregunta
Reports for ______________ have a need for detailed information about individual tasks and the factors affecting such tasks.
Respuesta
-
top executives
-
lower-level personnel
-
all the stakeholders
-
project managers
Pregunta 190
Pregunta
The project control process should be viewed as a(n) ________________, with revised plans
and schedules (if warranted) following corrective actions. The project control process should run continuously until the project is completed.
Respuesta
-
closed loop system
-
open loop system
-
open environment
-
earned value plan
Pregunta 191
Pregunta
Ordinal rankings of performance are examples of a _________ type of measure.
Pregunta 192
Pregunta
____________ are used when some aspect of system performance cannot be measured
directly
Respuesta
-
Indicators
-
Frequency counts
-
Raw numbers
-
Verbal measures
Pregunta 193
Pregunta
____________ can often give the project manager early warning signals of potential problems in a project and help understand the relationships of individual tasks to one another and to the overall project.
Pregunta 194
Pregunta
The earned value rule that divides the actual task time-to-date by the scheduled time for the task to calculate percent complete is called the _________ rule.
Respuesta
-
50-50
-
0-100 percent
-
critical input use
-
proportionality
Pregunta 195
Pregunta
In earned value analysis, EAC refers to the
Pregunta 196
Pregunta
In earned value analysis, BAC refers to the
Respuesta
-
budgeted annual cost
-
budget at completion
-
budget at close-out
-
big annual cost
Pregunta 197
Pregunta
If EV= $500, AC = $475, PV = $450; SV =
Pregunta 198
Pregunta
If CSI is less than 1, it is indicative of a(n)
Respuesta
-
problem
-
good project
-
efficient project
-
budget error
Pregunta 199
Pregunta
Conceptually, EAC represents the amount spent to date
Respuesta
-
plus the delay costs
-
BAC
-
CV
-
ETC
Pregunta 200
Pregunta
In earned value analysis, the 0 - 100 percent rule allows
Respuesta
-
100 percent credit before starting work and 0 percent credit after the completion
-
0 percent credit when work begins and 100 percent credit when the project is complete
-
0 percent credit when work begins and 100 percent credit at completion of the activity
-
0 percent credit at completion of the activity and 100 percent credit at formal acceptance during scope verification