Pregunta 1

Pregunta
If a project manager wants to incorporate feedback loops to provide opportunities for interaction to effective communication on the project, she should use a:
Respuesta
  • a. Presentations
  • b. Writing style
  • c. Meeting management
  • d. Sender-receiver model

Pregunta 2

Pregunta
All of the follow are dimensions of communication activities except:
Respuesta
  • a. Upward communication
  • b. Horizontal communication
  • c. Procedures
  • d. Written and oral

Pregunta 3

Pregunta
At the beginning of planning, you identify a important stakeholder who are not supporting the project. During a communication planning session you recommend use:
Respuesta
  • a. The support of management to change this stakeholder because he is not supporting the project team
  • b. The job description of this stakeholder to explain him the importance of his support
  • c. A communication style assessment to identify the preferred communication method, format and content for communication activities with this stakeholder
  • d. The avoiding style of conflict management.

Pregunta 4

Pregunta
Communications are often enhanced when the sender ____ the receiver.?
Respuesta
  • a. Speaks up to
  • b. Uses gestures when speaking to
  • c. Speaks slowly to
  • d. Shows concern for the perspective of

Pregunta 5

Pregunta
The Charter on a project would be viewed as what type of communication?
Respuesta
  • a. Formal
  • b. Formal Written
  • c. Contract
  • d. Verbal

Pregunta 6

Pregunta
communicating to the receiver which of the following will they focus on delivering and ensuring that it can be decoded correctly?
Respuesta
  • a. Medium
  • b. Feedback
  • c. Message
  • d. Noise

Pregunta 7

Pregunta
All of the following could be considered mediums for communication by a project team member except.?
Respuesta
  • a. Staff meetings
  • b. E-mail
  • c. Message
  • d. Video conference

Pregunta 8

Pregunta
The project manager wants to inform to main stakeholders about the project status sending a monthly report by e-mail. He will use:
Respuesta
  • a. Pull communication
  • b. Push communication
  • c. Intranet site
  • d. Instant message system

Pregunta 9

Pregunta
Formal written correspondence with the customer is required when:
Respuesta
  • a. Defects are detected
  • b. The customer requests additional work not covered under contract
  • c. The project has a schedule slippage that includes changes to the critical path
  • d. The project has cost overruns

Pregunta 10

Pregunta
In the communication model, who validates that the receiver has received and understood the message from the sender correctly? PMBOK p371
Respuesta
  • a. Both the sender and receiver
  • b. Project Manager
  • c. Receiver
  • d. Sender
Mostrar resumen completo Ocultar resumen completo

Similar

Los reyes católicos: La integración de las coronas
maya velasquez
Consejos para Estudiar y Citas
maya velasquez
Animales y sus Características
Diego Santos
Paisajes de España
Joaquín Ruiz Abellán
El descubrimiento de América
elenamne18
LA PRIMERA GUERRA MUNDIALO LA GRAN GUERRA
Erika Urban
Capas de la Tierra
Diego Santos
EXAMEN HISTORIA DE LA MUSICA
pipengue
Mapa Mental Estructura gramatical presente simple inglés
JOWANI BELLO MELO
APUNTES DE LATÍN
Cintia González Manzanares