Pregunta 1
Pregunta
A document called ______________ is created by decomposing the project scope into smaller, more manageable elements.
Respuesta
-
Scope Statement
-
Network Logic Diagram
-
Work Breakdown Structure
-
Requested Change
Pregunta 2
Pregunta
You are working on a project to build a bridge. You have reached the planned halfway mark. The total planned cost at this stage is $500. The actual physical work that has been completed at this stage is worth $400. You have already spent one thousand dollars on the project. What is the CPI?
Pregunta 3
Pregunta
Preliminary cost estimates are developed during the __________ phase of the project.
Respuesta
-
Conceptual
-
Detailed Design
-
Implementation
-
Execution
Pregunta 4
Pregunta
Cost baseline is usually represented using which curve or line.
Respuesta
-
slanted line
-
S-curve
-
Z-curve
-
PQ curve
Pregunta 5
Pregunta
By completing a forward pass a project scheduler can...
Pregunta 6
Pregunta
A contractor with an Experience Modification Rate (EMR) of 0.9 regarding accident claims will most likely pay more than the industry average for worker's compensation insurance.
Pregunta 7
Pregunta
You are planning to use PERT for planning of your project. A task has pessimistic estimate of 24 days, most likely estimate of 15 days, and optimistic estimate of 12 days. What is the mean using the PERT technique?
Respuesta
-
18 days
-
25.5 days
-
15 days
-
16 days
-
17 days
Pregunta 8
Pregunta
The critical path is the set of events that cannot be delayed without causing an extension of the project
Pregunta 9
Pregunta
____________ is the number of days that an activity can be delayed without extending the project minimum duration.
Respuesta
-
Contingency
-
Free Float
-
Total Float
-
Critical Path
Pregunta 10
Pregunta
_________________ is the amount of money added to the base estimate to account for risk and uncertainty
Respuesta
-
Contingency
-
Total Float
-
Free Float
-
Critical Path
Pregunta 11
Pregunta
IN 1970, the federal government began a process of providing a comprehensive set of safety rules and regulations, inspection procedures, and safety record-keeping requirements. OSHA was established at this time. OSHA stands for:
Respuesta
-
Occupation Standards and Health Agency
-
Observe Safe Highways Always
-
Outside Safety and Health Administration
-
Occupational Safety and Health Administration
Pregunta 12
Pregunta
The typical construction worker's (craftwork) productive versus nonproductive time can be broken down by percent of time to the following
Pregunta 13
Pregunta
If BCWS=1000, BCWP=1200, and ACWP=1300, the project is...
Respuesta
-
Ahead of schedule and under budget
-
Ahead of schedule and over budget
-
Behind schedule and over budget
-
Behind schedule and under budget
Pregunta 14
Pregunta
Which activity-to-activity relationship model is assumed when creating a critical path method network diagram?
Respuesta
-
Start to start
-
Start to finish
-
Finish to start
-
Finish to Finish
Pregunta 15
Pregunta
A rough order of magnitude estimate is made during which phase of a project?
Respuesta
-
project design
-
project closing
-
project executing
-
project initiating
Pregunta 16
Pregunta
A construction project has a schedule performance index (SPI) of 1.19 and a cost performance index (CPI) of 0.88. Which of the following is the best explanation for why this occurred?
Respuesta
-
Unfavorable work conditions
-
Labor rates too high and critical path changed
-
Overstaffing of work
-
Non-critical path activities took less time and cost 12% less
Pregunta 17
Pregunta
Project expenses paid by the owner to pay for payroll services provided by the contractors home office is what type of cost?
Respuesta
-
Direct field cost
-
Indirect project cost
-
Profit
-
Contingency
-
None of the Above
Pregunta 18
Pregunta
If BAC (budgeted at completion) for a work package is $10,000 and BCWP=$4,000, the the work package is...
Respuesta
-
40 percent complete
-
80 percent complete
-
100 percent complete
-
120 percent complete
Pregunta 19
Pregunta
When a project is completed, which of the following must be true?
Pregunta 20
Pregunta
If BAC=$24,000, BCWP=$12,000, ACWP=$10,000 and CPI=(BCWP/ACWP)=1.2, then the cost that remains to finish the project is...
Respuesta
-
10,000
-
12,000
-
14,000
-
Cannot be determined
Pregunta 21
Pregunta
To control the schedule, a project manager is reanalyzing the project to predict project duration She does this by analyzing the sequence of activitie with the least amount of scheduling flexibility. What technique is she using?
Respuesta
-
Critical path method
-
Flowchart analysis
-
Precedence diagramming
-
Work breakdown structure
Pregunta 22
Pregunta
You are the project manager of a construction project. The original scope baseline of the project was budgeted at $100,000. Since work on the project start, there have been seventeen authorized and approved changed to the project. The changes have a value of $17,000. There is also an additional change order for $2,500 that has been paid but not yet approved by the owner. What should you report as the current budget for the project?
Respuesta
-
100,000
-
114,500
-
117,000
-
119,500
Pregunta 23
Pregunta
During the project life cycle, in which part of the life cycle will risk be the lowest?
Respuesta
-
Initiation
-
Planning
-
Execution
-
Closeout
Pregunta 24
Pregunta
In critical path scheduling, total float is calculated as the sum of an activity's early start and the late start (TF = LS + ES)
Pregunta 25
Pregunta
Cost Performance Indicator is an index showing the efficiency of the utilization of the resources on the project. Cost Performance Indicator can be calculated using the following formula: CPI = Actual Cost (AC)/Earned Value (EV)
Pregunta 26
Pregunta
According to the Association for the Advancement of Cost Engineering (AACE), Class 2 cost estimates are developed during the ___________ phase of the project.
Respuesta
-
Conceptual
-
Feasibility
-
Budget Authorization
-
Bid
Pregunta 27
Pregunta
What are the best uses of PERT?
Respuesta
-
Used in the planning phase to do "what if" scenarios for the project.
-
Assist in the controlling of changes to the project.
-
Is used in the process of preparing a WSB for the project.
-
To measure future consequences of activities.
-
A & D
Pregunta 28
Pregunta
Activities with little total float are called "near-critical" activities, because they can quickly become critical if their small amount of total float is used up in a delay.
Pregunta 29
Pregunta
A proper Work Breakdown Structure includes:
Respuesta
-
Physical components of the final constructed product.
-
Activities required to construct the final product that do not directly build a physical component.
-
Both physical components of the final constructed product and activities required to construct the final product that do not directly build a physical component.
-
The responsibilities of specific project organizations or people for specific wok packages.
-
None of the above
Pregunta 30
Pregunta
The Spearin doctrine is a legal principle that holds that when a contractor follows the plans and specifications furnished by the owner, and those plans and specifications turn out to be defective or insufficient, the contractor is not liable to the owner for any loss or damage resulting from the defective plans and specifications.
Pregunta 31
Pregunta
According to CVEN 349 lecture and the text, forecasts of future costs can be uncertain due to
Pregunta 32
Pregunta
For most construction activities there may be no direct relationship between elapsed time, actual work, and incurred costs?
Pregunta 33
Pregunta
A cost performance index (CPI) of 0.89 means
Respuesta
-
At this time, we expect the total project to cost 89 percent more than planned
-
When the project is completed, we will have spent 89 percent more than planned
-
The project is only progressing at 89 percent of that planned
-
The project is only getting 89 cents out of every dollar invested
Pregunta 34
Pregunta
An Organizational Breakdown Structure (OBS) can include
Respuesta
-
Activities required to construct the final product that do not directly build a physical component
-
Both physical components of the final constructed product and activities required to construct the final product that do not directly build a physical component
-
The responsibilities of specific project organizations or people for specific work packages
-
None of the above