Pregunta 1
Pregunta
Q. 201: The inputs for developing a test plan are taken from
Respuesta
-
A. Project plan
-
B. Business plan
-
C. Support plan
-
D. None of the above
Pregunta 2
Pregunta
Q. 202: To test a function, the programmer has to write a ______, which calls the
function and passes it the test data.
Respuesta
-
A. Stub
-
B. Driver
-
C. Proxy
-
D. None of the above
Pregunta 3
Pregunta
Q. 203: Which of the following is not a static testing technique
Respuesta
-
A. Error guessing
-
B. Walkthrough
-
C. Data flow analysis
-
D. Inspections
Pregunta 4
Pregunta
Q. 204: Which of the following statements about component testing is not true?
Respuesta
-
A. Component testing should be performed by development
-
B. Component testing is also know as isolation or module testing
-
C. Component testing should have completion criteria planned
-
D. Component testing does not involve regression testing
Pregunta 5
Pregunta
Q. 205: Inspections can find all the following except
Respuesta
-
A. Variables not defined in the code
-
B. Spelling and grammar faults in the documents
-
C. Requirements that have been omitted from the design documents
-
D. How much of the code has been covered
Pregunta 6
Pregunta
Q. 206: Which of the following is not a characteristic for Testability?
Respuesta
-
A. Operability
-
B. Observability
-
C. Simplicity
-
D. Robustness
Pregunta 7
Pregunta
Q. 207: Software testing accounts to what percent of software development costs?
Respuesta
-
A. 10-20
-
B. 40-50
-
C. 70-80
-
D. 5-10
Pregunta 8
Pregunta
Q. 208: Equivalence partitioning is:
Respuesta
-
A. A black box testing technique used only by developers
-
B. A black box testing technique than can only be used during system testing
-
C. A black box testing technique appropriate to all levels of testing
-
D. A white box testing technique appropriate for component testing
Pregunta 9
Pregunta
Q. 209: If an expected result is not specified then:
Respuesta
-
A. We cannot run the test
-
B. It may be difficult to repeat the test
-
C. It may be difficult to determine if the test has passed or failed
-
D. We cannot automate the user inputs
Pregunta 10
Pregunta
Q. 210: How much testing is enough
Respuesta
-
A. This question is impossible to answer
-
B. The answer depends on the risks for your industry, contract and special requirements
-
C. The answer depends on the maturity of your developers
-
D. The answer should be standardized for the software development industry
Pregunta 11
Pregunta
Q. 211: The purpose of requirement phase is
Respuesta
-
A. To freeze requirements
-
B. To understand user needs
-
C. To define the scope of testing
-
D. All of the above
Pregunta 12
Pregunta
Q. 212: Which of these can be successfully tested using Loop Testing methodology?
Respuesta
-
A. Simple Loops
-
B. Nested Loops
-
C. Concatenated Loops
-
D. All of the above
Pregunta 13
Pregunta
Q. 213: Cyclomatic Complexity method comes under which testing method.
Respuesta
-
A. White box
-
B. Black box
-
C. Green box
-
D. Yellow box
Pregunta 14
Pregunta
Q. 214: A reliable system will be one that:
Respuesta
-
A. Is unlikely to be completed on schedule
-
B. Is unlikely to cause a failure
-
C. Is likely to be fault-free
-
D. Is likely to be liked by the users
Pregunta 15
Pregunta
Q. 215: Which, in general, is the least required skill of a good tester?
Pregunta 16
Pregunta
Q. 216: A regression test:
Respuesta
-
A. Will always be automated
-
B. Will help ensure unchanged areas of the software have not been affected
-
C. Will help ensure changed areas of the software have not been affected
-
D. Can only be run during user acceptance testing
Pregunta 17
Pregunta
Q. 217: Function/Test matrix is a type of
Respuesta
-
A. Interim Test report
-
B. Final test report
-
C. Project status report
-
D. Management report
Pregunta 18
Pregunta
Q. 218: The process starting with the terminal modules is called:
Respuesta
-
A. Top-down integration
-
B. Bottom-up integration
-
C. None of the above
-
D. Module integration
Pregunta 19
Pregunta
Q. 219: Verification is:
Respuesta
-
A. Checking that we are building the right system
-
B. Checking that we are building the system right
-
C. Performed by an independent test team
-
D. Making sure that it is what the user really wants
Pregunta 20
Pregunta
Q. 220: The difference between re-testing and regression testing is
Respuesta
-
A. Re-testing is running a test again; regression testing looks for unexpected side effects
-
B. Re-testing looks for unexpected side effects; regression testing is repeating those tests
-
C. Re-testing is done after faults are fixed; regression testing is done earlier
-
D. Re-testing uses different environments, regression testing uses the same environment
-
E. Re-testing is done by developers, regression testing is done by independent testers
Pregunta 21
Pregunta
Q. 221: Testing should be stopped when:
Respuesta
-
A. All the planned tests have been run
-
B. Time has run out
-
C. All faults have been fixed correctly
-
D. Both A. and C.
-
E. I depends on the risks for the system being tested
Pregunta 22
Pregunta
Q. 222: Which of the following is the main purpose of the integration strategy for
integration testing in the small?
Respuesta
-
A. To ensure that all of the small modules are tested adequately
-
B. To ensure that the system interfaces to other systems and networks
-
C. To specify which modules to combine when and how many at once
-
D. To ensure that the integration testing can be performed by a small team
-
E. To specify how the software should be divided into modules
Pregunta 23
Pregunta
Q. 223: Which of the following is NOT part of configuration management:
Respuesta
-
A. Status accounting of configuration items
-
B. Auditing conformance to ISO9001
-
C. Identification of test versions
-
D. Record of changes to documentation over time
-
E. controlled library access
Pregunta 24
Pregunta
Q. 224:Regression testing should be performed:
v) Every week
w) After the software has changed
x) As often as possible
y) When the environment has changed
z) Wwhen the project manager says
Respuesta
-
A. v & w are true, x – z are false
-
B. w, x & y are true, v & z are false
-
C. w & y are true, v, x & z are false
-
D. w is true, v, x y and z are false
-
E. All of the above are true
Pregunta 25
Pregunta
Q. 225: A tool that supports traceability, recording of incidents or scheduling of tests is
called:
Respuesta
-
A. A dynamic analysis tool
-
B. A test execution tool
-
C. A debugging tool
-
D. A test management tool
-
E. A configuration management tool
Pregunta 26
Pregunta
Q. 226: The cost of fixing a fault:
Respuesta
-
A. Is not important
-
B. Increases as we move the product towards live use
-
C. Decreases as we move the product towards live use
-
D. Is more expensive if found in requirements than functional design
-
E. Can never be determined
Pregunta 27
Pregunta
Q. 227: Order numbers on a stock control system can range between 10000 and 99999
inclusive. Which of the following inputs might be a result of designing tests for only
valid equivalence classes and valid boundaries:
Respuesta
-
A. 1000, 5000, 99999
-
B. 9999, 50000, 100000
-
C. 10000, 50000, 99999
-
D. 10000, 99999
-
E. 9999, 10000, 50000, 99999, 10000
Pregunta 28
Pregunta
Q. 228: When what is visible to end-users is a deviation from the specific or expected
behavior, this is called:
Respuesta
-
A. An error
-
B. A fault
-
C. A failure
-
D. A defect
-
E. A mistake
Pregunta 29
Pregunta
Q. 229: Which expression best matches the following characteristics or review
processes:
1. Led by author
2. Undocumented
3. No management participation
4. Led by a trained moderator or leader
5. Uses entry exit criteria
s) Inspection
t) Peer review
u) Informal review
v) Walkthrough
Respuesta
-
A. s = 4, t = 3, u = 2 and 5, v = 1
-
B. s = 4 and 5, t = 3, u = 2, v = 1
-
C. s = 1 and 5, t = 3, u = 2, v = 4
-
D. s = 5, t = 4, u = 3, v = 1 and 2
-
E. s = 4 and 5, t = 1, u = 2, v = 3
Pregunta 30
Pregunta
Q. 230: Given the following:
Switch PC on
Start "outlook"
IF outlook appears THEN
Send an email
Close outlook
Respuesta
-
A. 1 test for statement coverage, 1 for branch coverage
-
B. 1 test for statement coverage, 2 for branch coverage
-
C. 1 test for statement coverage. 3 for branch coverage
-
D. 2 tests for statement coverage, 2 for branch coverage
-
E. 2 tests for statement coverage, 3 for branch coverage
Pregunta 31
Pregunta
Q. 231: Test managers should not:
Respuesta
-
A. Report on deviations from the project plan
-
B. Sign the system off for release
-
C. Re-allocate resource to meet original plans
-
D. Rise incidents on faults that they have found
-
E. Provide information for risk analysis and quality improvement
Pregunta 32
Pregunta
Q. 232: Which of the following is NOT part of system testing:
Respuesta
-
A. Business process-based testing
-
B. Performance, load and stress testing
-
C. Requirements-based testing
-
D. Usability testing
-
E. Top-down integration testing
Pregunta 33
Pregunta
Q. 233: When a new testing tool is purchased, it should be used first by:
Respuesta
-
A. A small team to establish the best way to use the tool
-
B. Everyone who may eventually have some use for the tool
-
C. The independent testing team
-
D. The managers to see what projects it should be used in
-
E. The vendor contractor to write the initial scripts
Pregunta 34
Pregunta
Q. 234: Which of the following is not part of performance testing:
Respuesta
-
A. Measuring response time
-
B. Measuring transaction rates
-
C. Recovery testing
-
D. Simulating many users
-
E. Generating many transactions
Pregunta 35
Pregunta
Q. 235: What is the purpose of test completion criteria in a test plan:
Respuesta
-
A. To know when a specific test has finished its execution
-
B. To ensure that the test case specification is complete
-
C. To set the criteria used in generating test inputs
-
D. To know when test planning is complete
-
E. To plan when to stop testing
Pregunta 36
Pregunta
Q. 236: Given the following code, which is true:
IF A > B THEN
C = A – B
ELSE
C = A + B
ENDIF
Read D
IF C = D Then
Print "Error"
ENDIF
Respuesta
-
A. 1 test for statement coverage, 3 for branch coverage
-
B. 2 tests for statement coverage, 2 for branch coverage
-
C. 2 tests for statement coverage. 3 for branch coverage
-
D. 3 tests for statement coverage, 3 for branch coverage
-
E. 3 tests for statement coverage, 2 for branch coverage
Pregunta 37
Pregunta
Q. 237: Unreachable code would best be found using:
Pregunta 38
Pregunta
Q. 238: What information need not be included in a test incident report:
Respuesta
-
A. How to fix the fault
-
B. How to reproduce the fault
-
C. Test environment details
-
D. Severity, priority
-
E. The actual and expected outcomes
Pregunta 39
Pregunta
Q. 239: Which of the following is NOT included in the Test Plan document of the Test
Documentation Standard:
Respuesta
-
A. Test items (i.e. software versions)
-
B. What is not to be tested
-
C. Test environments
-
D. Quality plans
-
E. Schedules and deadlines
Pregunta 40
Pregunta
Q. 240: IEEE 829 test plan documentation standard contains all of the following except:
Respuesta
-
A. Test items
-
B. Test deliverables
-
C. Test tasks
-
D. Test environment
-
E. Test specification
Pregunta 41
Pregunta
Q. 251: Which of the following is NOT a black box technique:
Respuesta
-
A. Equivalence partitioning
-
B. State transition testing
-
C. LCSAJ
-
D. Syntax testing
-
E. Boundary value analysis
Pregunta 42
Pregunta
Q. 252: Expected results are:
Respuesta
-
A. Only important in system testing
-
B. Only used in component testing
-
C. Never specified in advance
-
D. Most useful when specified in advance
-
E. Derived from the code
Pregunta 43
Pregunta
Q. 253: Beta testing is:
Respuesta
-
A. Performed by customers at their own site
-
B. Performed by customers at their software developer’s site
-
C. Performed by an independent test team
-
D. Useful to test bespoke software
Pregunta 44
Pregunta
Q. 254: Consider the following:
Pick up and read the newspaper
Look at what is on television
If there is a program that you are interested in watching then switch the the television on
and watch the program
Otherwise
Continue reading the newspaper
If there is a crossword in the newspaper then try and complete the crossword
Respuesta
-
A. SC = 1 and DC = 1
-
B. SC = 1 and DC = 2
-
C. SC = 1 and DC = 3
-
D. SC = 2 and DC = 2
-
E. SC = 2 and DC = 3
Pregunta 45
Pregunta
Q. 255: A typical commercial test execution tool would be able to perform all of the
following EXCEPT:
Respuesta
-
A. Generating expected outputs
-
B. Replaying inputs according to a programmed script
-
C. Comparison of expected outcomes with actual outcomes
-
D. Recording test inputs
-
E. Reading test values from a data file
Pregunta 46
Pregunta
Q. 256: Consider the following statements about early test design:
i. Early test design can prevent fault multiplication
ii. Faults found during early test design are more expensive to fix
iii. Early test design can find faults
iv. Early test design can cause changes to the requirements
v. Early test design takes more effort
Respuesta
-
A. i, iii & iv are true. Ii & v are false
-
B. iii is true, I, ii, iv & v are false
-
C. iii & iv are true. i, ii & v are false
-
D. i, iii, iv & v are true, ii us false
-
E. i & iii are true, ii, iv & v are false
Pregunta 47
Pregunta
Q. 257: Given the following code, which is true about the minimum number of test
cases required for full statement and branch coverage:
Read P
Read Q
IF P+Q > 100 THEN
Print "Large"
ENDIF
If P > 50 THEN
Print "P Large"
ENDIF
Respuesta
-
A. 1 test for statement coverage, 3 for branch coverage
-
B. 1 test for statement coverage, 2 for branch coverage
-
C. 1 test for statement coverage, 1 for branch coverage
-
D. 2 tests for statement coverage, 3 for branch coverage
-
E. 2 tests for statement coverage, 2 for branch coverage
Pregunta 48
Pregunta
Q. 258: The place to start if you want a (new) test tool is:
Respuesta
-
A. Attend a tool exhibition
-
B. Invite a vendor to give a demo
-
C. Analyse your needs and requirements
-
D. Find out what your budget would be for the tool
-
E. Search the internet
Pregunta 49
Pregunta
Q. 259: Error guessing is best used
Respuesta
-
A. As the first approach to deriving test cases
-
B. After more formal techniques have been applied
-
C. By inexperienced testers
-
D. After the system has gone live
-
E. Only by end users
Pregunta 50
Pregunta
Q. 260: Exit Criteria may consist of:
i. Thoroughness measures, such as coverage of code, functionality or risk
ii. Estimates of Defect density or reliability measures.
iii. Residual risk such as defects not fixed or lack of test coverage in certain areas
iv. Verifying the Test Environment.
Respuesta
-
A. iv is correct and i,ii,iii are incorrect.
-
B. i,ii,iii is correct and iv is incorrect
-
C. ii is correct and i,ii,iii are incorrect
-
D. iii and iv are correct and i,ii are incorrect
Pregunta 51
Pregunta
Q. 261: One of the fields on a form contains a text box, which accepts alphabets in
lower or upper case. Identify the invalid Equivalance class value.
Respuesta
-
A. CLASS
-
B. cLASS
-
C. CLass
-
D. CLa01ss
Pregunta 52
Pregunta
Q. 262: The Kick Off phase of a formal review includes the following:
Respuesta
-
A. Explaining the objective
-
B. Fixing defects found typically done by author
-
C. Follow up
-
D. Individual Meeting preparations
Pregunta 53
Pregunta
Q. 263: Peer Reviews are also called as :
Respuesta
-
A. Inspection
-
B. Walkthrough
-
C. Technical Review
-
D. Formal Review
Pregunta 54
Pregunta
Q. 264: Validation involves which of the following
i. Helps to check the Quality of the Built Product
ii. Helps to check that we have built the right product.
iii. Helps in developing the product
iv. Monitoring tool wastage and obsoleteness.
Respuesta
-
A. Options i,ii,iii,iv are true.
-
B. ii is true and i,iii,iv are false
-
C. i,ii,iii are true and iv is false
-
D. iii is true and i,ii,iv are false.
Pregunta 55
Pregunta
Q. 265: Success Factors for a review include:
i. Each Review does not have a predefined objective
ii. Defects found are welcomed and expressed objectively
iii. Management supports a good review process.
iv. There is an emphasis on learning and process improvement.
Respuesta
-
A. ii,iii,iv are correct and i is incorrect
-
B. iii , i , iv is correct and ii is incorrect
-
C. i , iii , iv , ii is in correct
-
D. ii is correct
Pregunta 56
Pregunta
Q. 266: Which of the following helps in monitoring the Test Progress:
i. Percentage of Test Case Execution
ii. Percentage of work done in test environment preparation.
iii. Defect Information e.g. defect density, defects found and fixed
iv. The size of the testing Team and skills of the engineers
Respuesta
-
A. iv is correct and i,ii,iii are incorrect
-
B. i,ii,iii are correct and iv is incorrect
-
C. i,ii are correct and iii,iv are incorrect
-
D. i,iv are correct and ii , iii are incorrect
Pregunta 57
Pregunta
Q. 267: Defects discovered by static analysis tools include:
i. Variables that are never used.
ii. Security vulnerabilities.
iii. Programming Standard Violations
iv. Uncalled functions and procedures
Respuesta
-
A. i , ii,iii,iv is correct
-
B. iii ,is correct I,ii,iv are incorrect.
-
C. i ,ii, iii and iv are incorrect
-
D. iv, ii is correct
Pregunta 58
Pregunta
Q. 268: Which of the following is true about White and Black Box Testing Technique:-
Respuesta
-
A. Equivalence partitioning, Decision Table and Control flow are White box Testing
Techniques.
-
B. Equivalence partitioning, Boundary Value Analysis , Data Flow are Black Box Testing
Techniques.
-
C. Equivalence partitioning , State Transition , Use Case Testing are black box Testing
Techniques.
-
D. Equivalence Partitioning, State Transition, Use Case Testing and Decision Table are
White Box Testing Techniques.
Pregunta 59
Pregunta
Q. 269: Which of the following techniques is NOT a black box technique?
Respuesta
-
A. State transition testing
-
B. LCSAJ (Linear Code Sequence and Jump)
-
C. Syntax testing
-
D. Boundary value analysis
Pregunta 60
Pregunta
Q. 270: Features of White Box Testing Technique:
i. We use explicit knowledge of the internal workings of the item being tested to select the
test data.
ii. Uses specific knowledge of programming code to examine outputs and assumes that the
tester knows the path of logic in a unit or a program.
iii. Checking for the performance of the application
iv. Also checks for functionality.
Respuesta
-
A. i, ii are true and iii and iv are false
-
B. iii is true and i,ii, iv are false
-
C. ii ,iii is true and i,iv is false
-
D. iii and iv are true and i,ii are false
Pregunta 61
Pregunta
Q. 271. The Provision and Management of a controlled library containing all the
configurations items is called as
Pregunta 62
Pregunta
Q. 272: The selection of a test approach should consider the context:
i. Risk of Failure of the Project, hazards to the product and risks of product failure to
humans
ii. Skills and experience of the people in the proposed technique, tools and methods
iii. The objective of the testing endeavor and the mission of the testing team.
iv. The size of the testing Team
Respuesta
-
A. i,ii,iii,iv are true
-
B. i,ii,iii are true and iv is false.
-
C. ii,iii,iv are true and i is false.
-
D. i,iv are true and ii, iii are false.
Pregunta 63
Pregunta
Q. 273: Benefits of Independent Testing
Respuesta
-
A. Independent testers are much more qualified than Developers
-
B. Independent testers see other and different defects and are unbiased.
-
C. Independent Testers cannot identify defects.
-
D. Independent Testers can test better than developers
Pregunta 64
Pregunta
Q. 274: Minimum Test Required for Statement Coverage:
Disc = 0
Order-qty = 0
Read Order-qty
If Order-qty >=20 then
Disc = 0.05
If Order-qty >=100 then
Disc =0.1
End if
End if
Respuesta
-
A. Statement coverage is 4
-
B. Statement coverage is 1
-
C. Statement coverage is 3
-
D. Statement Coverage is 2
Pregunta 65
Pregunta
Q. 275: Test Conditions are derived from:
Respuesta
-
A. Specifications
-
B. Test Cases
-
C. Test Data
-
D. Test Design
Pregunta 66
Pregunta
Q. 276: Which of the following is the task of a Test Lead / Leader.
i. Interaction with the Test Tool Vendor to identify best ways to leverage test tool on the
project.
ii. Write Test Summary Reports based on the information gathered during testing
iii. Decide what should be automated , to what degree and how.
iv. Create the Test Specifications
Respuesta
-
A. i, ii, iii is true and iv is false
-
B. ii,iii,iv is true and i is false
-
C. i is true and ii,iii,iv are false
-
D. iii and iv is correct and i and ii are incorrect
Pregunta 67
Pregunta
Q. 277: Impact Analysis helps to decide:
Respuesta
-
A. How much regression testing should be done.
-
B. Exit Criteria
-
C. How many more test cases need to written.
-
D. Different Tools to perform Regression Testing
Pregunta 68
Pregunta
Q. 278: Drivers are also known as:
i. Spade
ii. Test harness
iii. Scaffolding
Respuesta
-
A. i , ii are true and iii is false
-
B. i , iii are true and ii is false
-
C. ii , iii are true and i is false
-
D. All of the above are true
Pregunta 69
Pregunta
Q. 279: Which of the following is not a type of incremental testing approach?
Pregunta 70
Pregunta
Q. 280: In a system designed to work out the tax to be paid:
An employee has £4000 of salary tax free. The next £1500 is taxed at 10% The next £28000
is taxed at 22% Any further amount is taxed at 40% Which of these groups of numbers would
fall into the same equivalence class?
Pregunta 71
Pregunta
Q. 281: In case of Large Systems :
Respuesta
-
A. Only few tests should be run
-
B. Testing should be on the basis of Risk
-
C. Only Good Test Cases should be executed.
-
D. Test Cases written by good test engineers should be executed.
Pregunta 72
Pregunta
Q. 282: What is the expected result for each of the following test cases?
A. Citibank card member, holding a Silver room
B. Non Citibank-member, holding a Platinum room
Respuesta
-
A. A – Don’t offer any upgrade, B – Don’t offer any upgrade.
-
B. A – Don’t offer any upgrade, B – Offer upgrade to Gold.
-
C. A – Offer upgrade to Silver, B – Offer upgrade to Silver.
-
D. A – Offer upgrade to Gold, B – Don’t offer any upgrade.
Pregunta 73
Pregunta
Q. 283: Which of the following is not phase of the Fundamental Test Process?
Respuesta
-
A. Test Planning and Control
-
B. Test implementation and Execution
-
C. Requirement Analysis
-
D. Evaluating Exit criteria and reporting
Pregunta 74
Pregunta
Q. 284: The structure of an incident report is covered in the Standard for Software Test
Documentation IEEE 829 and is called as:
Respuesta
-
A. Anomaly Report
-
B. Defect Report
-
C. Test Defect Report
-
D. Test Incident Report
Pregunta 75
Pregunta
Q. 285: Repeated Testing of an already tested program, after modification, to discover
any defects introduced or uncovered as a result of the changes in the software being
tested or in another related or unrelated software component:
Respuesta
-
A. Re Testing
-
B. Confirmation Testing
-
C. Regression Testing
-
D. Negative Testing
Pregunta 76
Pregunta
Q. 286: Consider the following state transition diagram of a switch. Which of the
following represents an invalid state transition?
Respuesta
-
A. OFF to ON
-
B. ON to OFF
-
C. FAULT to ON
Pregunta 77
Pregunta
Q. 287: We use the output of the requirement analysis, the requirement specification
as the input for writing:
Respuesta
-
A. User Acceptance Test Cases
-
B. Integration Level Test Cases
-
C. Unit Level Test Cases
-
D. Program specifications
Pregunta 78
Pregunta
Q. 288: Regression testing should be performed:
i. Every week
ii. After the software has changed
iii. As often as possible
iv. When the environment has changed
v. When the project manager says
Respuesta
-
A. i & ii are true, iii, iv & v are false
-
B. ii, iii & iv are true, i & v are false
-
C. ii & iv are true, i, iii & v are false
-
D. ii is true, i, iii, iv & v are false
Pregunta 79
Pregunta
Q. 289: Evaluating testability of the requirements and system are a part of which
phase:-
Respuesta
-
A. Test Analysis and Design
-
B. Test Planning and control
-
C. Test Implementation and execution
-
D. Evaluating exit criteria and reporting
Pregunta 80
Pregunta
Q. 290: Which of the following has highest level of independence in which test cases
are:
Respuesta
-
A. Designed by persons who write the software under test
-
B. Designed by a person from a different section
-
C. Designed by a person from a different organization
-
D. Designed by another person
Pregunta 81
Pregunta
Q. 291: Test planning has which of the following major tasks?
i. Determining the scope and risks, and identifying the objectives of testing.
ii. Determining the test approach (techniques,test items, coverage, identifying and
interfacing the teams involved in testing , testware)
iii. Reviewing the Test Basis (such as requirements,architecture,design,interface)
iv. Determining the exit criteria.
Respuesta
-
A. i,ii,iv are true and iii is false
-
B. i,,iv are true and ii is false
-
C. i,ii are true and iii,iv are false
-
D. ii,iii,iv are true and i is false
Pregunta 82
Pregunta
Q. 292: Deciding How much testing is enough should take into account :-
i. Level of Risk including Technical and Business product and project risk
ii. Project constraints such as time and budget
iii. Size of Testing Team
iv. Size of the Development Team
Respuesta
-
A. i,ii,iii are true and iv is false
-
B. i,,iv are true and ii is false
-
C. i,ii are true and iii,iv are false
-
D. ii,iii,iv are true and i is false
Pregunta 83
Pregunta
Q. 293: Which of the following will be the best definition for Testing:
Respuesta
-
A. The goal / purpose of testing is to demonstrate that the program works.
-
B. The purpose of testing is to demonstrate that the program is defect free.
-
C. The purpose of testing is to demonstrate that the program does what it is supposed to
do.
-
D. Testing is executing Software for the purpose of finding defects.
Pregunta 84
Pregunta
Q. 294: Minimum Tests Required for Statement Coverage and Branch Coverage:
Read P
Read Q
If p+q > 100 then
Print "Large"
End if
If p > 50 then
Print "pLarge"
End if
Respuesta
-
A. Statement coverage is 2, Branch Coverage is 2
-
B. Statement coverage is 3 and branch coverage is 2
-
C. Statement coverage is 1 and branch coverage is 2
-
D. Statement Coverage is 4 and Branch coverage is 2
Pregunta 85
Pregunta
Q. 295: Match every stage of the software Development Life cycle with the Testing Life
cycle:
i. Hi-level design a Unit tests
ii. Code b Acceptance tests
iii. Low-level design c System tests
iv. Business requirements d Integration tests
Respuesta
-
A. i-d , ii-a , iii-c , iv-b
-
B. i-c , ii-d , iii-a , iv-b
-
C. i-b , ii-a , iii-d , iv-c
-
D. i-c , ii-a , iii-d , iv-b
Pregunta 86
Pregunta
Q. 296: Which of the following is a part of Test Closure Activities?
i. Checking which planned deliverables have been delivered
ii. Defect report analysis.
iii. Finalizing and archiving testware.
iv. Analyzing lessons.
Respuesta
-
A. i , ii , iv are true and iii is false
-
B. i , ii , iii are true and iv is false
-
C. i , iii , iv are true and ii is false
-
D. All of above are true
Pregunta 87
Pregunta
Q. 297: Which of the following is NOT part of a high level test plan?
Respuesta
-
A. Functions not to be tested.
-
B. Environmental requirements.
-
C. Analysis of Specifications.
-
D. Entry and Exit criteria.
Pregunta 88
Pregunta
Q. 298: If a candidate is given an exam of 40 questions, should get 25 marks to pass
(61%) and should get 80% for distinction, what is equivalence class.
Respuesta
-
A. 23, 24, 25
-
B. 0, 12, 25
-
C. 30, 36, 39
-
D. 32,37,40
Pregunta 89
Pregunta
Q. 299: Which of the following statements is true of static analysis:
Respuesta
-
A. Compiling code is not a form of static analysis.
-
B. Static analysis need not be performed before imperative code is executed.
-
C. Static analysis can find faults that are hard to find with dynamic testing.
-
D. Extensive statistic analysis will not be needed if white- Box testing is to be performed.
Pregunta 90
Pregunta
Q. 300: In a system designed to work out the tax to be paid: An employee has $4000 of
salary tax free. The next $1500 is taxed at 10% The next $28000 is taxed at 22% Any
further amount is taxed at 40%
Which of these groups of numbers would fall into the same equivalence class?
Pregunta 91
Pregunta
Q. 301: Cost of the reviews will not include.
Respuesta
-
A. Review process itself
-
B. Metrics analysis
-
C. Tool support.
-
D. Process improvement.
Pregunta 92
Pregunta
Q. 302: Regression testing always involves
Respuesta
-
A. Testing whether a known software fault been fixed.
-
B. Executing a large number of different tests.
-
C. Testing whether modifications have introduced adverse side effects.
-
D. Using a test automation tool.
Pregunta 93
Pregunta
Q. 303: Capture and replay facilities are least likely to be used to _______
Respuesta
-
A. Performance testing
-
B. Recovery testing
-
C. GUI testing
-
D. User requirements.
Pregunta 94
Pregunta
Q. 304: Which tool will be used to test the flag memory leaks and unassigned pointers
Respuesta
-
A. Dynamic analysis tool
-
B. Static Analysis tool.
-
C. Maintenance tool.
-
D. Configuration tool.
Pregunta 95
Pregunta
Q. 305: Cyclomatic complexity is used to calculate
Respuesta
-
A. Number of independent paths in the basis set of a program
-
B. Number of binary decisions + 1
-
C. Number bound for the number of tests that must be conducted to ensure that all statements have been executed at least once
-
D. Number of branches and decisions
Pregunta 96
Pregunta
Q. 306: Which of the following is not included in Test Plan.
Pregunta 97
Pregunta
Q. 307: Software quality is not relevant to _______
Respuesta
-
A. Correctness
-
B. Usability
-
C. Viability
-
D. Reusability.
Pregunta 98
Pregunta
Q. 308: Match the following:
1. Test estimation
2. Test control
3. Test monitoring
a. Measures of tracking process
b. Effort required to perform activities
c. Reallocation of resources
Respuesta
-
A. 1-b, 2-c, 3-a
-
B. 1-b, 2-a, 3-c
-
C. 1-c, 2-a, 3-b
-
D. 1-a, 2-b, 3-c
Pregunta 99
Pregunta
Q. 309: When do you stop testing?
Respuesta
-
A. When the specified number of faults are found.
-
B. When the test completion criteria are met.
-
C. When all high and medium priority tests are complete.
-
D. When all statements have been executed
Pregunta 100
Pregunta
Q. 310: What is the smallest number of test cases required to Provide 100% branch
coverage?
If(x>y) x=x+1;
else y=y+1;
while(x>y)
{
y=x*y; x=x+1;
}
Pregunta 101
Pregunta
Q. 311: Match the following.
1. Configuration identification
2. Configuration control
3. Status reporting
4. Configuration auditing
a. Maintains of CI’s in a library
b. Checks on the contents of the library
c. Function recording and tracking problems.
d. Requires the all CI’s and their versions in the system are known
Respuesta
-
A. 1-d, 2-c, 3-d, 4-a.
-
B. 1-d, 2-a, 3-c, 4-b.
-
C. 1-a, 2-b, 3-d, 4-c.
-
D. 1-c, 2-b, 3-a, 4-d.
Pregunta 102
Pregunta
Q. 312: Integration testing in the large involves:
Respuesta
-
A. Testing the system when combined with other systems.
-
B. Testing a sub-system using stubs and drivers.
-
C. Testing a system with a large number of users.
-
D. Combing software components and testing them in one go.
Pregunta 103
Pregunta
Q. 313: One of the following is not a part of white box testing as per BS7925-II
standards.
Respuesta
-
A. Random testing
-
B. Data Flow testing.
-
C. Statement testing.
-
D. Syntax testing.
Pregunta 104
Pregunta
Q. 314: A piece of software has been given _______what tests in the Following will you
perform?
1) Test the areas most critical to business processes
2) Test the areas where faults will be maximum
3) Test the easiest functionalities
Respuesta
-
A. 1&2 are true and 3 is false.
-
B. 1,2&3 are true.
-
C. 1 is true, 2&3 are false.
-
D. 1&2 are false, 3 is true