Pregunta 1

Pregunta
Which of the following scenarios below would be the best at reducing foot fall noise compared to the others?
Respuesta
  • Carpet on soft underlayment on 4" to 8" thick concrete structural slab.
  • Carpet on underlayment on concrete structural slab with isolation hangers (spring, neoprene) with 6" or more air space resiliently suspended to secure gypsum board ceiling underneath.
  • Carpet installed on 2" to 4" floated concrete slab with fiberboard between pads on the concrete structural slab.
  • 8" concrete slab

Pregunta 2

Pregunta
Which type of joint allows movement between the concrete slab and adjoining columns and walls of a building?
Respuesta
  • Isolation Joints
  • Control Joints
  • Slab Joints
  • Joist Joints

Pregunta 3

Pregunta
Drag and drop the given mortar types to match the given construction application options accordingly-each mortar type is to be used only once.
Respuesta
  • N
  • M
  • S
  • O

Pregunta 4

Pregunta
During the construction administration phase of a high-end downtown historic hotel renovation project, the architect receives shop drawings for aluminum roof cladding and notices that copper fasteners are specified for attachment. What is the potential problem with the detail?
Respuesta
  • Architect is only responsible for reviewing the shop drawing, not approving, therefore potential risks are not their responsibility.
  • A potential risk of galvanic corrosion exists; cladding will corrode.
  • A potential risk of galvanic corrosion exists; fasteners will corrode.
  • There is no risk of galvanic reaction, detail should be approved by architect.

Pregunta 5

Pregunta
An architect is working on the details of a new shopping mall project that will be built in an old navy yard as part of the redevelopment of the whole area. The developer wants to retain the existing character of the site by recommending the floor finishes of the main gallery area be slip-resistant exposed concrete. What type of concrete finishing method/material below is more suitable for the exposed floor finishes of the main gallery area of this new shopping mall?
Respuesta
  • A burlap drag
  • Coarse-bristled broom finishing
  • Sawing
  • Machine Troweling

Pregunta 6

Pregunta
Which of the following is the most watertight mortar joint profile?
Respuesta
  • Raked
  • Concave
  • Flush
  • Struck

Pregunta 7

Pregunta
A 34‐W, 425‐mA (milliampere), 48‐in. fluorescent tube produces 3200 lm. What is the illuminance on the floor of a 12 ft-square room in foot candles, assuming 60% overall efficiency and uniform illumination? (Round the nearest whole number)
Respuesta
  • 267
  • 160
  • 22
  • 13

Pregunta 8

Pregunta
A 2-in.-diameter round steel rod 10 ft long is subjected to a tensile force of 60 kips. How much will it elongate under the load? (Round the nearest thousandth) Δ𝐋 = 𝐏𝐋/𝐀𝐄 and Modulus of Elasticity of steel at 29,000 ksi and π = 3,14
Respuesta
  • 0.0025"
  • 0.006"
  • 0.079"
  • 0.047

Pregunta 9

Pregunta
During the construction documentation phase of a school project in Duluth, MN, the architect and the engineer are discussing the appropriate portland cement type to be specified for the project. Which type of the portland cement type below would provide the best performance considering the concrete work is scheduled in early November?
Respuesta
  • Type I
  • Type II
  • Type III
  • Type IV

Pregunta 10

Pregunta
An architect is working on a high-end restaurant project where the client wants an open kitchen, visible to restaurant customers, with white tiles, cabinets and counter surfaces. While reviewing the interior elevations, the architect notices that the grout specified by the interior designer does not meet this design intent. Which material below is not supposed to be in the grout mixture if it is desired to have white finish color?,
Respuesta
  • Iron
  • China clay
  • Limestone
  • Chalk

Pregunta 11

Pregunta
Which type of temperature reinforcement is more likely to be used to prevent cracking in the slabs due to abrupt temperature changes?𝐂𝐡𝐞𝐜𝐤 𝐭𝐡𝐞 𝐭𝐰𝐨 𝐭𝐡𝐚𝐭 𝐚𝐩𝐩𝐥𝐲.
Respuesta
  • Steel rebars
  • Synthetic fiber reinforcement
  • Welded wire fabric.
  • Light welded wire fabric.

Pregunta 12

Pregunta
An 8 feet tall, 240 feet wide brick masonry wall has been designed, and the architect is working on updating the construction cost of the wall during the CD phase. Based on the itemized costs given below, what would be the total cost of the wall? • Approximately 175 bricks will be used per 10 square yard wall (waste material included), and 10 bricks cost $3.5 • 10 Sq Yd brick wall grout cost $250 • 10 Sq Yd brick wall labor cost $850 • 1.5% inflation cost should be added to the overall cost
Respuesta
  • $24,773.00
  • $25,145.00
  • $25,890.00
  • $28,163.00

Pregunta 13

Pregunta
Which of the following documents are part of Bidding Documents? 𝐂𝐡𝐞𝐜𝐤 𝐭𝐡𝐞 𝐭𝐰𝐨 𝐭𝐡𝐚𝐭 𝐚𝐩𝐩𝐥𝐲.
Respuesta
  • Change Orders
  • Addendum
  • General Conditions
  • Contract Modifications

Pregunta 14

Pregunta
During the bidding phase of an interior office renovation project, the owner decides to revise wood wall bases WB-2 and WB-3 to resilient vinyl wall bases. According to the partial finish plan view given above, select the rooms that will be affected based on this revision. 𝐂𝐡𝐞𝐜𝐤 𝐭𝐡𝐞 𝐟𝐢𝐯𝐞 𝐭𝐡𝐚𝐭 𝐚𝐩𝐩𝐥𝐲
Respuesta
  • 201
  • 202
  • 203
  • 204
  • 205
  • 206
  • 207
  • 208
  • 209
  • 217

Pregunta 15

Pregunta
An architect is working on the revisions of the given items below during the Construction Documentation phase of a project. Drag and drop given revision items to match the given Master Specification divisions accordingly. Drag and drop the letter's across the irrelevant Division.
Respuesta
  • X
  • Temporary protective walkways
  • Plastic Toilet Compartments
  • Dampers

Pregunta 16

Pregunta
The second floor of a high school library has classrooms, conference rooms, office spaces, and two staircases on opposite ends of the floor. The school board has decided to remodel the second floor to add an automatic fire sprinkler system and an emergency communication system. They also wish to expand the space by removing partition walls between the library and the adjacent unused building. With the new addition, the office space will increase by 20%, and classroom areas will increase by 30%. Based on the current areas per use given below, what is the minimum required stair width of the new space? 𝐂𝐮𝐫𝐫𝐞𝐧𝐭 𝐀𝐫𝐞𝐚𝐬: ○ Classrooms: 1860 SF ○ Conference Rooms: 800 SF ○ Office: 1150 SF https://codes.iccsafe.org/content/IBC2021P2
Respuesta
  • 24"
  • 36"
  • 44"
  • 48"

Pregunta 17

Pregunta
Based on the information given in the plan diagram above, what is the minimum total length of an unobstructed straight ADA ramp system and entry hall required to create an accessible route between points A and B? (The thickness of the partition at the entry door is to be ignored)
Respuesta
  • 46'
  • 48'
  • 51'
  • 56'

Pregunta 18

Pregunta
Select the location of the Main Switch Board on the electrical single-line diagram given above
Respuesta
  • 1
  • 2
  • 3
  • 4

Pregunta 19

Pregunta
Drag and drop the given components of the schematic shelf detail above across to the letters accordingly.
Respuesta
  • Brick Veneer
  • Air Space
  • Flashing
  • Shelf angle
  • Weep hole
  • Mortar net
  • Backer rod & sealant
  • Plastic shim

Pregunta 20

Pregunta
Select the location of the fire stop in the fire-rated partition and metal deck section detail given below.
Respuesta
  • A
  • B
  • C
  • D
  • E
Mostrar resumen completo Ocultar resumen completo

Similar

Project Closeout
Kara Biczykowski
PDD Quiz XII
a a
PDD Quiz IX
a a
MAPA CONCEPTUAL DE POLITICAS PUBLICAS
pamm_1805
Esquema del reformismo ilustrado en España
maya velasquez
EJES BÁSICOS DE LA ATENCIÓN A LA PRIMERA INFANCIA DESDE UN ENFOQUE DIFERENCIAL
maria cely
FGM-12. MANIFESTACIONES EXTERNAS DE LA DISCIPLINA
antonio del valle
mapa mental de modelo OSI y modelo TCP/IP
alejandrovielmas
Vocabulario inglés variado con expresiones
María Luisa
ORTOGRAFÍA: B o V ...
Ulises Yo
VIOLENCIA Y DELINCUENCIA
Edgar Sarzosa