Any time you need to make a change to your
plan, you need to start with a change request.
This is a document that either you or the person
making the change needs to create. Any change
to your project needs to be DOCUMENTED so
you can figure out what needs to be done. Once
you have a change request, that then kicks off
your project´s set of change control PROCEDURES.
The KEY here is PROCEDURE change
control is about how your company
handles changes
CCB : Change Control Board
Nota:
This Group of people decides the changes when this change affect the scope.
For the exam,
assume that all
projects have CCB
PMIS
Precess: Perform Integrated Change Control
Process Group: Monitoring & Controlling
Knowledge Area: Integration Management
PM ROL: RESPONSABLE
Every change in ejecution needs a change request.
How will the change affect all the other project constraints?