null
US
Iniciar Sesión
Regístrate Gratis
Registro
Hemos detectado que no tienes habilitado Javascript en tu navegador. La naturaleza dinámica de nuestro sitio requiere que Javascript esté habilitado para un funcionamiento adecuado. Por favor lee nuestros
términos y condiciones
para más información.
Siguiente
Copiar y Editar
¡Debes iniciar sesión para completar esta acción!
Regístrate gratis
51672
Changes to the Construction Act
Descripción
T017 & T016 Mapa Mental sobre Changes to the Construction Act, creado por alison_patey0437 el 20/04/2013.
Sin etiquetas
t017 & t016
t017 & t016
Mapa Mental por
alison_patey0437
, actualizado hace más de 1 año
Más
Menos
Creado por
alison_patey0437
hace más de 11 años
114
0
0
Resumen del Recurso
Changes to the Construction Act
Local Democracy, Economic Development and Construction Act 2009 comes into force on 1 October 2011
Act amends the existing Housing Grants, Construction and Regeneration Act 1996 known as the Construction Act
improve payment practices within the UK construction industry
Scheme for Construction Contracts (England and Wales) Regulations 1998 is the secondary legislation which supplements the construction Act
Scheme has also been amended
All contracts entered into after 1 October will be governed by the amended Act
3 main changes
Unwritten contracts
provisions of the Construction Act have in the past applied only to construction contracts entered into “in writing”
1 October 2011 this restriction will no longer apply.
any construction contract made orally or part-orally, as well as in writing, will be covered by the Construction Act.
Adjudication procedures
result of the changes, disputes arising from oral or part-oral contracts may be referred to adjudication
Parties should also take care to ensure that pre-contract negotiations are marked as being “subject to contract”
Adjudication agreement must be “in writing”
if there is a written contract
must satisfy each of the nine requirements for adjudication
timetable to secure adjudicator and refer the dispute within 7 days of such notice;
adjudicator to reach a decision within 28 days of referral (or such longer period as is agreed by the parties)
adjudicator to extend the period of 28 days by up to 14 days with the consent of the referring party
Impose a duty on the adjudicator to act impartially;
adjudicator to take the initiative in ascertaining the facts and the law
decision of the adjudicator is binding until the dispute is finally determined by legal proceedings or arbitration or by agreement
adjudicator is not liable for anything done or omitted in his role as adjudicator unless the act or omission is in bad faith
adjudicator to correct his decision so as to remove a clerical or typographical error caused by accident or omission
Under the revised Scheme, the adjudicator must correct the decision within 5 days of delivery of the decision to the parties.
if each and every one of these requirements are not agreed in writing
all of Part 1 of the Construction Scheme will apply by default.
Enable a party to give notice at any time of its intention to refer a dispute to adjudication;
Timetable
Scheme now clarifies
28 day period for adjudication runs from the date the adjudicator receives the referral notice and not the date of dispatch by the referring part
Costs
clause allocating parties’ liability for the costs of adjudication will be ineffective subject to two exceptions
Parties may give the adjudicator power to determine who pays his fees and expenses
Parties may agree the allocation of adjudication costs but only after the notice of intention to refer has been issued
clause for payee or referring party to pay all of the payer’s or responding party’s legal costs + adjudicator’s fees and expenses = outlaw
Payment terms
payment provisions within the Construction Act have been rewritten
Adequate Payment mechanism
Act requires every construction contract to contain an adequate mechanism for determining when payments become due under the contract
from 1/10/11 any contract which determines date for payment by reference to a notice given to the payee by the payer is not an “adequate mechanism'
Pay-when-certified and pay-when-paid clauses
prohibit “pay when certified” clauses pursuant to which payment is due only upon certification of payment under another contract
only exception is where the clause is contained in a contract providing for construction work by others as is the case with Man Contracting
A “pay when paid” is clause is permitted were a payer is not paid due to another payer’s insolvency (known as “upstream insolvency”)
Payment Notices
new system of payment notices has been introduced
payer must send notice to the payee of the sum considered due at the payment due date and the basis on which that sum is calculated
notice must be given even if the sum due is zero
if the payer does not send notice within 5 days of the due date
payee to send its own payment notice or default payment notice
if the payee has submitted an application for payment before the date on which the payer’s notice was required
no requirement for a second notice.
application for interim payment will act as the payee’s notice
Mostrar resumen completo
Ocultar resumen completo
¿Quieres crear tus propios
Mapas Mentales
gratis
con GoConqr?
Más información
.
Similar
T017 Insurance
alison_patey0437
Contract Practice - Interim Valuations & Payment Privisions
alison_patey0437
Loss and Expense
alison_patey0437
Contract Practice JCT OVERVIEW
alison_patey0437
T017 Roles & Responsibilities of parties
alison_patey0437
T017 Termination & remedies for breaches outside the Contract
alison_patey0437
Contract Practice - Performance security
alison_patey0437
T017 Letters of Intent
alison_patey0437
Conflict Avoidance
alison_patey0437
T017 L&AD
alison_patey0437
T017 EOT
alison_patey0437
Explorar la Librería