SAB8#130 Risk vs Workarounds
  1. Workaround
    1. A workaround is not a planned response because the problems being addressed were not anticipated ahead of time. Per the name, a “workaround” let’s you “work around” the problem. As soon as it is determined that there is an unanticipated problem, it needs to be addressed, researched and incorporated into the documentation of the project plan
    2. Risk
      1. Contingency plans are developed around those possible issues and they are completed before the threat takes place. These contingency plans should address the objective of the plan, the criteria for activating the contingency plan, the people and responsibilities involved, and the additional details required for implementation.
      Show full summary Hide full summary

      Similar

      Reducing the Impact of Earthquakes
      siobhan.quirk
      Spanish Verbs
      Niat Habtemariam
      Key Paintings
      Julia Lee
      GCSE English Language Overview
      philip.ellis
      Exchange surfaces and breathing
      megan.radcliffe16
      Structure of the League of Nations
      saskiamitchell.19
      Biology B2.2
      Jade Allatt
      An Inspector Calls- Quotes
      ae14bh12
      “In gaining knowledge, each area of knowledge uses a network of ways of knowing.” Discuss this statement with reference to two areas of knowledge
      Julianapabab
      The Lymphatic System
      james liew
      1PR101 2.test - Část 16.
      Nikola Truong