SAB4#63_Network Diagram Analysis
  1. Critical path metod

    Anotações:

    • Involves determining the longest path through the network diagram, the earliest and latest activity can star, and the earliest and latest it can be completed.
    1. Critical path

      Anotações:

      • Is the longest duration path through a network diagram an determines the shortest time it could take to complete the project.
      • The aesiest way to find the critical path is to identify all paths through the network and add the activity durations along each path.  The path with the longest duration is the critical path.
      1. Near critical path

        Anotações:

        • This path is close in duration to the critical path.  Something could happen that shortnes the critical path or lengthens the near-critial path to the point where the near-critical path becomes critical.
        • The closer in length the near-critical an critical paths are, the more risk the project has.
      2. Float (slack)
        1. Total float

          Anotações:

          • Is the amount of time an activity can be delayed without delaying the project end date or an intermediary milestone.
          1. Free float

            Anotações:

            • This is the amount of time an activity can be delayed without delating the early start date of its succesor 
            1. Project float

              Anotações:

              • Is the amount of time a project can be delayed without delaying the externally imposed project completion date required by the customer or management.
              1. Start formula

                Anotações:

                • Float=LS-ES
                1. Finish formula

                  Anotações:

                  • LF-EF
              2. Schedule compresion

                Anotações:

                • During project planning, schedule compresion can help a project manager determine if the desired completion date can be met and, if not, what can de changed to meet the requested date.
                1. Fast tracking

                  Anotações:

                  • Involves taking critical path activities that were originally planned in a series and doing them instead in parallel for some or all of their duration.
                  1. Crashing

                    Anotações:

                    • Involves adding or adjunting resources in order to compress the schedule while mantaining the original project scope.
                    • Crashing, by definition, always results in increased costs and may increase risk.
                  2. Modeling

                    Anotações:

                    • In creating a finalized, realistic schedule, it is helpful to ask "what if a particular factor changed on the project?  Would thah produce a shorter schedule?
                    • The assumptions for each activity can change and, therefore, the activity durations can also change.
                    1. Monte Carlo Analysis

                      Anotações:

                      • This technique uses computer software to simulate the outcome of a project, based on the three-point estimates (optimistic, pessimistic, and most likely) for each activity and the network diagram.
                      • The simulation can tell you: 1.- The probability of completing the project on any specific day. 2.- The probabilty of completing the project for any specific cost. 3.- The probability of any activity actually being on the critical path. 4.- The overall project riks.
                    2. Resource optimiaztion

                      Anotações:

                      • Refers to finding ways to adjust the use of resources.
                      1. Resource leveling

                        Anotações:

                        • Is used to produce a resource-limited schedule.
                        1. Resource Smoothing

                          Anotações:

                          • Is a modified form of resource leveling, where resources are leveled only within the limits of the float of ther activities.
                        2. Critical chain method

                          Anotações:

                          • Uses a network diagram and critical path to develop a schedule by assigning each activity to occur as late as posible to still meet the end date.
                          • You add resource dependencies to the schedule and then calculate the critical chain. Starting at the end date, you buid buffers for ersource limitations and risks into the chain at critical milestones (risk response planning).
                          • These reserves, spread throughout the project, provide cushions for delays in the scheduled activities.  You manage these buffers so thah you meet each individual milestone date and thus the project milestone completion date as well.

                          Semelhante

                          Direito Constitucional - Brutal - Tribunais
                          Rômulo Campos
                          English - prepositions (at, in, on)
                          jdbenthien
                          Phrasal Verbs - Inglês #5
                          Eduardo .
                          História do Brasil - Período Colonial
                          alessandra
                          Processo Civil
                          Marcela Martins
                          Palácio das Memórias (técnica em 05 etapas) - SEJA O MESTRE DO SEU PALÁCIO
                          angrafederal
                          TÉCNICAS DE ESTUDO
                          Rafael Fernando
                          Guia de Estudos ENEM 2016
                          GoConqr suporte .
                          Totalitarismo: Fascismo e Nazismo
                          jacson luft
                          Hipertensão Arterial Sistêmica - HAS
                          Katye dos Passos Rodrigues
                          Plano de estudos ENEM 2017 - Matérias que mais caem
                          Nathalia - GoConqr