MWI PMI 2017

Descrição

Quiz sobre MWI PMI 2017, criado por Markus Hansalik em 27-10-2017.
Markus Hansalik
Quiz por Markus Hansalik, atualizado more than 1 year ago
Markus Hansalik
Criado por Markus Hansalik aproximadamente 7 anos atrás
32
1

Resumo de Recurso

Questão 1

Questão
Herzberg's Theory focuses on ...
Responda
  • hygiene factors and motivators
  • hygiene factors and esteem factors
  • motivators and safety factors
  • hygiene factors and social factors

Questão 2

Questão
Which of the following BEST describes a project management plan?
Responda
  • Baselines, improvement and other management plans
  • A printout from project management software
  • The project scope
  • A bar chart

Questão 3

Questão
Which one of the following is NOT a conflict resoltion technique?
Responda
  • Withdrawing
  • Smoothing
  • Compromising
  • Advertising

Questão 4

Questão
The pareto principle states that ___________ percent of the problems are due to 20 percent of the root causes
Responda
  • 20
  • 10
  • 80
  • 50

Questão 5

Questão
Which of the following is NOT a task of the process 'Close Project or Phase'?
Responda
  • Final definition of project boundaries
  • Disposition of resources
  • Marketing of the project results
  • Administration of claims

Questão 6

Questão
A conflict in a project team is ...
Responda
  • a problem, which reduces the ability to work
  • nothing important and will not reduce the ability to work
  • a situation that occurs at least once a day
  • a crisis, that could stop the work on the project

Questão 7

Questão
If earned value (EV) = 550, actual cost (AC) = 400, planned value (PV) = 350, what is the cost variance (CV)?
Responda
  • 400
  • -50
  • 200
  • 150

Questão 8

Questão
Which one of the following processes is NOT part of the Monitoring & Controlling Process Group?
Responda
  • Control Schedule
  • Control Procurements
  • Close Procurements
  • Control Costs

Questão 9

Questão
The project charter is created in which project management process group?
Responda
  • Planning
  • Executing
  • Closing
  • Initiating

Questão 10

Questão
What is the duration of a milestone?
Responda
  • Same length as the activity it represents
  • Shorter than the activity it represents
  • Shorter than the duration of the longest activity
  • There is no duration

Questão 11

Questão
Conflict resolution techniques that may be used on a project include confronting, smoothing, forcing and:
Responda
  • Directing
  • Organizing
  • Controlling
  • Withdrawing

Questão 12

Questão
When would a milestone chart be used instead of a bar chart?
Responda
  • Reporting to management
  • Reporting to team members
  • Project planning
  • Risk analysis

Questão 13

Questão
If you make a prototype for a risky piece of equipment what type of risk response is this?
Responda
  • Accept
  • Mitigate
  • Avoid
  • Transfer

Questão 14

Questão
Which project management process group generally takes the MOST project time and resources?
Responda
  • Executing
  • Planning
  • Integration
  • Design

Questão 15

Questão
During which process group does the team measure and analyze the work being done on the project?
Responda
  • Closing
  • Executing
  • Initiating
  • Monitoring and controlling

Questão 16

Questão
A project has three critical paths. Which of the following BEST describes how this affects the project?
Responda
  • It increases the project risk.
  • It makes it easier to manage.
  • It makes it more expensive.
  • It requires more people.

Questão 17

Questão
The difference between the cost baseline and the cost budget can be BEST described as:
Responda
  • The project cost estimate.
  • The management reserve.
  • The cost account.
  • The contingency reserve.

Questão 18

Questão
Which of the following explains why quality is planned in and not inspected in?
Responda
  • It reduces quality and is less expensive.
  • It improves quality and is less expensive.
  • It reduces quality and is more expensive.
  • It improves quality and is more expensive.

Questão 19

Questão
Which of the following statements regarding the decision tree is correct?
Responda
  • You should not upgrade to the new software version because the EMV is higher than the other option.
  • You should not upgrade to the new software version because these are additional costs for the project
  • You should upgrade to the new version of the software because the EMV is 15.000,- and this is less than the EMV of 25.000 (if you do not upgrade)
  • As the impact is the same, you can choose any of the options

Questão 20

Questão
Which one of the following is NOT a response strategy for negative risks or threats?
Responda
  • Avoid
  • Mitigate
  • Exploit
  • Transfer

Questão 21

Questão
With which type of contract is the seller MOST concerned about project scope?
Responda
  • Purchase order
  • Fixed price contract
  • Cost reimbursable contract
  • Time and material

Questão 22

Questão
Which team development stages are included in the Tuckman Model?
Responda
  • Forming, Storming, Norming, Performing and Solving
  • Forming, Warming, Storming, Performing and Adjourning
  • Forming, Storming, Norming, Performing and Adjourning
  • Forming, Storming, Norming, Adjourning and Resolving

Questão 23

Questão
Which of the following is a chief characteristic of the Delphi technique?
Responda
  • Bottom-up approach
  • Extrapolation from historical records from previous projects
  • Analytical hierarchy process
  • Expert opinion

Questão 24

Questão
You have just identified the risks. What is the next process?
Responda
  • Plan Risk Management
  • Perform Quantitative Risk Analysis
  • Plan Risk Responses
  • Perform Qualitative Risk Analysis

Questão 25

Questão
A schedule performance index (SPI) of 0.76 means:
Responda
  • You are only progressing at 76 percent of the rate originally planned.
  • You are only progressing at 24 percent of the rate originally planned.
  • You are ahead of schedule.
  • You are over budget.

Questão 26

Questão
Cause-and-effect diagrams are also called?
Responda
  • Control Charts
  • Pareto Charts
  • Fishbone diagram
  • Flow Charts

Questão 27

Questão
What conflict resolution technique is a project manager using when he says, "I cannot deal with this issue now!"
Responda
  • Forcing
  • Problem solving
  • Withdrawing
  • Compromising

Questão 28

Questão
Budget at Completion (BAC) ...
Responda
  • may be calculated based on performance to date or estimated by the project team based on other factors.
  • is equal to the actual cost (AC) plus the estimate to complete (ETC) for all of the remaining work.
  • is the sum of all the budgets established for the work to be performed on a project or a work breakdown structure component or an activity.
  • is the value of work performed expressed in terms of the approved budget assigned to that work for an activity or work breakdown structure component.

Questão 29

Questão
How long is the critical path is this example?
Responda
  • 10
  • 15
  • 8
  • 9

Questão 30

Questão
The process 'Sequence Activities' belongs to which Knowledge Area?
Responda
  • Project Risk Management
  • Project Time Management
  • Project Scope Management
  • Project Integration Management

Questão 31

Questão
If you have to shorten the project duration without reducing the scope you can do the following:
Responda
  • Fast tracking
  • Analogous estimating
  • Nothing. Because duration can not be shortened
  • Create a Resource Break Down Structure

Questão 32

Questão
Secondary risks are
Responda
  • The risks that remain after planned responses have been implementes
  • A direct outcome of risk responses
  • Risks with a low priority and therefore will not be considered in further plannings
  • Risks that are deliberately accepted

Questão 33

Questão
You are estimating activity durations and have got the following values: Pessimistic: 12 Most likely: 5 Optimistic: 4 What is the expected duration when you are using Beta Distribution?
Responda
  • 12
  • 4
  • 5
  • 6

Questão 34

Questão
Which of the following is not a valid organizational structure?
Responda
  • Weak Matrix Organization
  • Functional Organization
  • Projectized Organisation
  • Hierarchical Organization

Questão 35

Questão
Which of the following is included in a project charter?
Responda
  • Detailed resource estimates
  • A risk management strategy
  • Work package estimates
  • The business need for the project

Questão 36

Questão
An organization is restructuring the way it does projects. In a shift from a strong matrix organization to a weak matrix organization, the power is shifted from the:
Responda
  • Project manager to the functional manager.
  • Functional manager to the project manager.
  • Functional manager to the sponsor.
  • Expediter to the coordinator.

Questão 37

Questão
When a product or service completely meets a customer‘s requirements:
Responda
  • The cost of quality is low.
  • Quality is achieved
  • The customer pays the minimum price.
  • The cost of quality is high.

Questão 38

Questão
The work breakdown structure is basis for all of the following EXCEPT:
Responda
  • Network Diagram
  • Risk Management
  • Estimating
  • Project charter

Questão 39

Questão
Which of the following leadership traits is MOST important for a project manager?
Responda
  • Project control
  • Communication
  • Technical expertise
  • Team building

Questão 40

Questão
The MOST important output of the process Plan Stakeholder Management is the ...
Responda
  • Project updates
  • Organizational process assets
  • Stakeholder Register
  • Stakeholder Management Plan

Questão 41

Questão
Which of the following regarding WBS is NOT correct?
Responda
  • What is not in the WBS is not part of the project
  • WBS means - Work Best to meet Schedule
  • Is often structured by phases
  • Is best presented as a graph

Questão 42

Questão
Which of the following is not a contract type category?
Responda
  • Lump sum contract
  • Request for Proposal
  • Cost reimbursable contract
  • Purchase Order

Questão 43

Questão
The highest point of Maslow's hierarchy of needs is called:
Responda
  • Need for association
  • Attainment of survival
  • Physiological satisfaction
  • Esteem

Questão 44

Questão
Which of the following risks is the biggest threat to the project?
Responda
  • 2
  • 1
  • 4
  • 3

Questão 45

Questão
Which of the following is CORRECT?
Responda
  • Critical path and near-critical path are the same
  • There can be only 1 critical path
  • Activities on the critical path have no buffer
  • A project can never have negative float

Semelhante

Mecânica
Alessandra S.
NA CONSTITUIÇÃO - Princípios Gerais
daniel_cal
Alemão Básico
Alessandra S.
Noções Gerais de Direito Administrativo
Alynne Saraiva
Aplicações do Mapa Mental
Alessandra S.
Mapas Mentais - 1
pcbsytem
Fonética, ortografia e acentuação gráfica
GoConqr suporte .
21 erros de comunicação que atrapalham sua carreira
Liliane Tubino
Palavras novas pro TOEFL
Jéssica Westphal
Liderança Militar - Exercício 2
Ibsen Rodrigues Maciel