Questão 1
Questão
Herzberg's Theory focuses on ...
Responda
-
hygiene factors and motivators
-
hygiene factors and esteem factors
-
motivators and safety factors
-
hygiene factors and social factors
Questão 2
Questão
Which of the following BEST describes a project management plan?
Questão 3
Questão
Which one of the following is NOT a conflict resoltion technique?
Responda
-
Withdrawing
-
Smoothing
-
Compromising
-
Advertising
Questão 4
Questão
The pareto principle states that ___________ percent of the problems are due to 20 percent of the root causes
Questão 5
Questão
Which of the following is NOT a task of the process 'Close Project or Phase'?
Questão 6
Questão
A conflict in a project team is ...
Responda
-
a problem, which reduces the ability to work
-
nothing important and will not reduce the ability to work
-
a situation that occurs at least once a day
-
a crisis, that could stop the work on the project
Questão 7
Questão
If earned value (EV) = 550, actual cost (AC) = 400, planned value (PV) = 350, what is the cost variance (CV)?
Questão 8
Questão
Which one of the following processes is NOT part of the Monitoring & Controlling Process Group?
Responda
-
Control Schedule
-
Control Procurements
-
Close Procurements
-
Control Costs
Questão 9
Questão
The project charter is created in which project management process group?
Responda
-
Planning
-
Executing
-
Closing
-
Initiating
Questão 10
Questão
What is the duration of a milestone?
Responda
-
Same length as the activity it represents
-
Shorter than the activity it represents
-
Shorter than the duration of the longest activity
-
There is no duration
Questão 11
Questão
Conflict resolution techniques that may be used on a project include confronting, smoothing, forcing and:
Responda
-
Directing
-
Organizing
-
Controlling
-
Withdrawing
Questão 12
Questão
When would a milestone chart be used instead of a bar chart?
Questão 13
Questão
If you make a prototype for a risky piece of equipment what type of risk response is this?
Responda
-
Accept
-
Mitigate
-
Avoid
-
Transfer
Questão 14
Questão
Which project management process group generally takes the MOST project time and resources?
Responda
-
Executing
-
Planning
-
Integration
-
Design
Questão 15
Questão
During which process group does the team measure and analyze the work being done on the project?
Questão 16
Questão
A project has three critical paths. Which of the following BEST describes how this affects the project?
Responda
-
It increases the project risk.
-
It makes it easier to manage.
-
It makes it more expensive.
-
It requires more people.
Questão 17
Questão
The difference between the cost baseline and the cost budget can be BEST described as:
Questão 18
Questão
Which of the following explains why quality is planned in and not inspected in?
Responda
-
It reduces quality and is less expensive.
-
It improves quality and is less expensive.
-
It reduces quality and is more expensive.
-
It improves quality and is more expensive.
Questão 19
Questão
Which of the following statements regarding the decision tree is correct?
Responda
-
You should not upgrade to the new software version because the EMV is higher than the other option.
-
You should not upgrade to the new software version because these are additional costs for the project
-
You should upgrade to the new version of the software because the EMV is 15.000,- and this is less than the EMV of 25.000 (if you do not upgrade)
-
As the impact is the same, you can choose any of the options
Questão 20
Questão
Which one of the following is NOT a response strategy for negative risks or threats?
Responda
-
Avoid
-
Mitigate
-
Exploit
-
Transfer
Questão 21
Questão
With which type of contract is the seller MOST concerned about project scope?
Questão 22
Questão
Which team development stages are included in the Tuckman Model?
Responda
-
Forming, Storming, Norming, Performing and Solving
-
Forming, Warming, Storming, Performing and Adjourning
-
Forming, Storming, Norming, Performing and Adjourning
-
Forming, Storming, Norming, Adjourning and Resolving
Questão 23
Questão
Which of the following is a chief characteristic of the Delphi technique?
Questão 24
Questão
You have just identified the risks. What is the next process?
Questão 25
Questão
A schedule performance index (SPI) of 0.76 means:
Responda
-
You are only progressing at 76 percent of the rate originally planned.
-
You are only progressing at 24 percent of the rate originally planned.
-
You are ahead of schedule.
-
You are over budget.
Questão 26
Questão
Cause-and-effect diagrams are also called?
Responda
-
Control Charts
-
Pareto Charts
-
Fishbone diagram
-
Flow Charts
Questão 27
Questão
What conflict resolution technique is a project manager using when he says, "I cannot deal with this issue now!"
Responda
-
Forcing
-
Problem solving
-
Withdrawing
-
Compromising
Questão 28
Questão
Budget at Completion (BAC) ...
Responda
-
may be calculated based on performance to date or estimated by the project team
based on other factors.
-
is equal to the actual cost (AC) plus the estimate to complete (ETC) for all of the remaining work.
-
is the sum of all the budgets established for the work to be performed on a project or a work breakdown structure component or an activity.
-
is the value of work performed expressed in terms of the approved budget assigned to that work for an activity or work breakdown structure component.
Questão 29
Questão
How long is the critical path is this example?
Questão 30
Questão
The process 'Sequence Activities' belongs to which Knowledge Area?
Questão 31
Questão
If you have to shorten the project duration without reducing the scope you can do the following:
Questão 32
Questão
Secondary risks are
Responda
-
The risks that remain after planned responses have been implementes
-
A direct outcome of risk responses
-
Risks with a low priority and therefore will not be considered in further plannings
-
Risks that are deliberately accepted
Questão 33
Questão
You are estimating activity durations and have got the following values:
Pessimistic: 12
Most likely: 5
Optimistic: 4
What is the expected duration when you are using Beta Distribution?
Questão 34
Questão
Which of the following is not a valid organizational structure?
Questão 35
Questão
Which of the following is included in a project charter?
Responda
-
Detailed resource estimates
-
A risk management strategy
-
Work package estimates
-
The business need for the project
Questão 36
Questão
An organization is restructuring the way it does projects. In a shift from a strong matrix organization to a weak matrix organization, the power is shifted from the:
Responda
-
Project manager to the functional manager.
-
Functional manager to the project manager.
-
Functional manager to the sponsor.
-
Expediter to the coordinator.
Questão 37
Questão
When a product or service completely meets a customer‘s requirements:
Responda
-
The cost of quality is low.
-
Quality is achieved
-
The customer pays the minimum price.
-
The cost of quality is high.
Questão 38
Questão
The work breakdown structure is basis for all of the following EXCEPT:
Responda
-
Network Diagram
-
Risk Management
-
Estimating
-
Project charter
Questão 39
Questão
Which of the following leadership traits is MOST important for a project manager?
Responda
-
Project control
-
Communication
-
Technical expertise
-
Team building
Questão 40
Questão
The MOST important output of the process Plan Stakeholder Management is the ...
Questão 41
Questão
Which of the following regarding WBS is NOT correct?
Responda
-
What is not in the WBS is not part of the project
-
WBS means - Work Best to meet Schedule
-
Is often structured by phases
-
Is best presented as a graph
Questão 42
Questão
Which of the following is not a contract type category?
Questão 43
Questão
The highest point of Maslow's hierarchy of needs is called:
Questão 44
Questão
Which of the following risks is the biggest threat to the project?
Questão 45
Questão
Which of the following is CORRECT?
Responda
-
Critical path and near-critical path are the same
-
There can be only 1 critical path
-
Activities on the critical path have no buffer
-
A project can never have negative float