Questão 1

Questão
You have recently taken over a troubled automobile project which has gone out of control. The project team missed many deadlines and stakeholders were not happy with the project progress. As an experienced project manager, your first priority is to bring the schedule into alignment with the project plan. You would like to use what-if scenario analysis to see how various factors affected the project schedule so that you can develop a plan to reduce the impact of adverse conditions on the project schedule in future. What would be your next course of action once you determine the factors that created schedule overrun?
Responda
  • Prepare a resource breakdown structure to identify resources used
  • Update activity lists to incorporate new activities into the schedule
  • Generate change requests for a corrective action
  • Develop project schedule network diagrams to determine the total slack

Questão 2

Questão
You are the project manager of a project and are about to conduct a risk identification exercise in a few days’ time. You would like to proactively remind the participants in the exercise of the various sources from which risk may arise in the project. What could you use to help you do this?
Responda
  • A Risk Breakdown Structure (RBS)
  • A Risk Simulation Structure (RSS)
  • A Risk Register
  • An Impact Matrix

Questão 3

Questão
A buyer and seller are looking at getting into a long-term relationship spanning over 10 years. Both parties would like to be protected from the unstable financial conditions of the country that are beyond their control. What type of contract is appropriate for such a relationship?
Responda
  • Fixed Price Incentive Fee (FPIF)
  • Firm Fixed Price (FPP)
  • Time & Material (T&M)
  • Fixed Price with Economic Price Adjustment Contract (FP-EPA)

Questão 4

Questão
What term defines the work needed to complete a product, service, or result?
Responda
  • Product scope
  • Scope creep
  • Scope verification
  • Project scope

Questão 5

Questão
Emily is managing the construction of a new office facility for her company. The project is half way through the execution. The project sponsor has asked Emily to ensure that all they key project stakeholders are still committed to the project. How can Emily assess the stakeholders’ current engagement levels?
Responda
  • By analyzing the most recent issue register
  • By reviewing the Stakeholders Engagement Assessment Matrix last updated during the planning phase of the project
  • By requesting the key stakeholders to submit a signed declaration of commitment
  • By communicating and interacting with the key stakeholders

Questão 6

Questão
A team of engineers is reviewing the architecture diagram for a new ERP system being deployed at a large accounting firm. The engineers are discussing the impact of the failure of each node in the diagram on overall availability of the final product. The intent of the discussion is to minimize the likelihood of failure and the effects of any failure. What is this called?
Responda
  • SWOT Analysis
  • Quantitative Analysis
  • Failure Mode and Effect Analysis
  • Deming Cycle

Questão 7

Questão
You are a certified PMP, and have been contact by PMI as part of an investigation they are conducting into allegations of improper conduct by your manager, also a PMP. A complaint has been filed stating that your manager has received bribes related to a large procurement contract on another project. PMI has asked if you would be able to provide information regarding this situation. What should you do?
Responda
  • Confront your manager.
  • Send PMI project documentation and emails related to the allegations to assist with their investigation.
  • Notify the appropriate management immediately.
  • Do nothing, citing a conflict of interest.

Questão 8

Questão
You are the project manager managing a project to design a print head for dot matrix printers. In order to determine ideal settings for print quality, the quality manager of the company suggests trying out various scenarios for printing by varying certain parameters on the print head. Identifying such variables which influence the product or process under development is called:
Responda
  • Benchmarking
  • Design of Experiments
  • Statistical Sampling
  • Brainstorming

Questão 9

Questão
Midway through a project, a project manager determined that the project was running way behind schedule. If the project manager needs to shorten the project schedule, without changing the project scope, which of the following schedule compression techniques could be applied?
Responda
  • Crashing
  • Reserve Analysis
  • Forecasting
  • Last Tracking

Questão 10

Questão
As a project manager, you are performing various project performance measurements to assess the magnitude of variation. You then attempt to determine the cause and decide whether corrective action is required. This would be known as:
Responda
  • Scope Analysis
  • Variance Analysis
  • Performance Reporting
  • Configuration Management

Questão 11

Questão
A project manager is looking at a make-or-buy analysis as part of the Plan Procurement Management process. What type of costs should the project manager consider for this analysis?
Responda
  • Direct costs
  • Indirect costs
  • Out-of-pocket costs
  • Both direct as well as indirect costs

Questão 12

Questão
Jane is the project manager for a healthcare facility construction project. She is currently holding a board briefing and updating the project’s current status to the board members. When Jane was presenting her project risks, the chairman suggested some preventive actions. What should Jane do first?
Responda
  • Jane should politely deny the request
  • Jane should write a change request
  • Jane should directly update the project management plan as the request has come from the Chairman
  • Jane should escalate the issue to the project sponsor

Questão 13

Questão
During the course of the project, the project management team developed a forecast for the estimate at completion (EAC) based on the project performance. Which of the following statements about EAC is correct?
Responda
  • The EAC forecast based on the Bottom-up estimate to complete (ETC) requires a new estimate.
  • The EAC forecast is best estimated using the estimate to complete (ETC) work performed considering both SPI and CPI factors.
  • The EAC forecast is best estimated using the estimate to complete (ETC) work performed at the present CPI.
  • The EAC forecast is best estimated using the estimate to complete (ETC) work performed at the budgeted rate

Questão 14

Questão
You are managing a medium sized construction project, and are reviewing some invoices from the electrical contractor. You see that materials not required for your project have been included on the invoice. After making a few phone calls it becomes clear that one of your project resources asked one of the vendor’s staff to add a few extra circuits to one part of the building. This change was never approved through the change management process. What do you do?
Responda
  • Notify the manager of your project resource that he failed to follow proper processes.
  • Refuse to pay the charges.
  • Call a team meeting to determine how this will impact the project, then inform stakeholders of the impacts.
  • Immediately inform the project stakeholders of the unauthorized scope change. Then call a team meeting to determine the impact to the project.

Questão 15

Questão
The total planned value (PV) for a project was $ 150,000. During the course of the project, the actual cost incurred turned out to be $ 275,000. What is the limit that the project manager usually imposes on the actual cost (AC)?
Responda
  • The AC is usually limited to twice the planned value.
  • The AC will not have an upper limit.
  • The AC is usually limited to thrice the planned value.
  • The AC is usually limited to 1.5 times the planned value

Questão 16

Questão
The selection of life cycle for the project, the processes to be applied to each phase, and the results of the tailoring by the project management team are usually found in the:
Responda
  • Project scope statement
  • Project management plan
  • Project schedule
  • Project charter

Questão 17

Questão
A project consists of multiple phases. Which of the following is a valid statement and applies to each phase of the project?
Responda
  • Each phase is generally concluded with a review of the work accomplished but is only closed if the next phase has already been started.
  • Each phase of the project is considered complete when the project sponsor signs off on that phase of the project.
  • Each phase of the project is generally concluded with a review of the work accomplished and deliverables to determine acceptance and whether the phase should be considered closed.
  • Each phase is generally concluded with a review of the work accomplished. A phase is never considered complete until the end of the project when the entire project can be deemed complete.

Questão 18

Questão
You are a project manager who is in charge of an important project for your company. The project is 40% complete after 3 months and has cost $350,000. The budget for the project is $950,000 and is scheduled to last 8 months. How is the project performing?
Responda
  • The project is behind schedule and over budget.
  • The project is ahead of schedule and under budget
  • The project is behind schedule and under budget.
  • The project is ahead of schedule and over budget

Questão 19

Questão
The manager of a project, that your company is running in another country, is at the corporate headquarters for a company-wide project management meeting. During a break, you overhear the project manager discussing payments made to local municipal governments for construction permits for his project. Your company has a strict policy about paying or taking bribes. What should you do?
Responda
  • Report him to PMI.
  • Report him to his manager.
  • Notify his project stakeholders.
  • Do nothing.

Questão 20

Questão
Many project managers have seen a graph which shows “Influence of Stakeholders” starting out high and declining as the project progresses. Conversely, it shows the “Cost of Changes” starting out low and increasing as the project progresses. What is the key message a project manager should obtain from this graph?
Responda
  • Stakeholder influence is not important at the end of the project.
  • Changes should be made as early in the project as possible.
  • Money should be set aside for expected changes at the end of the project.
  • The project should be placed on hold until all changes are made

Semelhante

Termos téc. Enfermagem
Letícia Silva
Gerenciamento de Projetos
Luiz Fernando
Phrasal Verbs - Inglês #11
Eduardo .
GEOGRAFIA - GEOPOLITICA
neusamiotto
A U T A R Q U I A
Jean Pierre Silva
Tipos textuais
brunolorenzatto
Acentuação gráfica
Lúcia Amaral
Teaching with GoConqr Tools
miminoma
Direito Constitucional e Administrativo
Maria José
RECORDANDO A HISTÓRIA DO BRASIL
Lucas Villar
1_1_Simulado SAEP - Técnico em Edificações
Carlos Santos