Questão 1
Questão
The retail chain is using a vendor to provide engineers for a security camera network design and implementation. Presently, the seller is having issues getting paid from the retailer and chooses to inform the buyer that they are in default of the contract. The seller then decides to remove the engineers from the job site, effectively stopping all project work since they haven’t been paid by the buyer yet. What most accurately describes this situation?
Responda
-
a. The buyer is wrong in stopping payment until the issues resolved.
-
b. The buyer is right in stopping payment until the issue is resolved.
-
c. The seller is wrong and needs to correct the situation.
-
d. Both sides appear to be in default of the contract.
Questão 2
Questão
The procurement process at your company is normally extremely complicated and time consuming. A new initiative is put in place to use a qualified sellers list to help make the process more efficient. All of the following are advantages of using a qualified sellers list except....
Responda
-
a. Provides a list of pre-qualified vendors
-
b. Provides the ability to work with vendors that are compatible with your company’s processes
-
c. Provides contracts without negotiations
-
d. Provides a list of vendors that meet your industry standards
Questão 3
Questão
The agreement could be:
Questão 4
Questão
All the followings statements about change control are incorrect EXCEPT:
Responda
-
a. A fixed-price contract will minimize the need for change control.
-
b. Changes seldom provide real benefits to the Project.
-
c. Contracts should include procedures to accommodate changes.
-
d. More detailed specifications eliminate the cause of changes.
Questão 5
Questão
A seller is working on a cost-reimbursable (CR) contract when the buyer decides he would like to expand the scope of services and change to a fixed-priced (FP) contract. All of the following are the seller’s options EXCEPT:
Responda
-
a. Completing the original work on a cost-reimbursable basis and then negotiating a fixed priced for the additional work.
-
b. Completing the original work and rejecting the additional work.
-
c. Negotiating a fixed-priced contract that includes the work.
-
d. Starting over with a new contract.
Questão 6
Questão
The retail chain is using a vendor to provide engineers for a security camera network design and implementation. The buyer of the solution is providing requirements that the solution needs to be able to accomplish when the solution is complete. What type of Scope of Work is being utilized on this project?
Responda
-
a. Functionality
-
b. Design
-
c. Analogous
-
d. Cost Plus
Questão 7
Questão
The contract is expected to cost $280K US. Actual costs are $240K US. There is a 50/50% share for any cost savings. What is the total cost of the contract for the buyer?
Responda
-
a. $240K US
-
b. $260K US
-
c. $300K US
-
d. $280K US
Questão 8
Questão
The project team is involved in a make-or-buy analysis. The members have decided it is best to buy the products needed instead of creating the products internally. They are evaluating the contract format to use to minimize their risk. This will likely mean shifting the risk to the seller. What type of contract will provide the seller with the most risk when entering into a contract?
Questão 9
Questão
The retail chain is using a vendor to provide engineers for a security camera network design and implementation. Presently, the team is negotiating a contract with potential vendors. What is the main goal of negotiations?
Responda
-
a. To attain the best price possible for the seller
-
b. To attain the best price possible for the buyer
-
c. To attain a fair price for the buyer and seller
-
d. To attain a fair price for the seller to get more work from the buyer
Questão 10
Questão
The primary objective of contract negotiation is to:
Responda
-
a. Get the most from the other side.
-
b. Protect the relationship.
-
c. Get the highest monetary return.
-
d. Define objective and stick to them.
Questão 11
Questão
The retail chain is using a vendor to provide engineers for a security camera network design and implementation. Presently, the team is meeting with potential vendors, showing them the details of the work of the project they would be involved in, as well as answering any questions they have about the work before their proposals are submitted. What is this called?
Questão 12
Questão
A routine audit of a cost-reimbursable (CR) contract determines that overcharges are being made. If the contract does not specify corrective action, the buyer should:
Responda
-
a. Continue to make project payments.
-
b. Halt payments until the problem is corrected.
-
c. Void the contract and start legal action to recover overpayments.
-
d. Change the contract to require more frequent audits.
Questão 13
Questão
In a fixed-priced (FP) contract, the fee or profit is:
Responda
-
a. Unknown.
-
b. Part of the negotiation involved in paying every invoice.
-
c. Applied as a line item to every invoice.
-
d. Determined with the other party at the end of the project.
Questão 14
Questão
If a project manager was performing Control Procurements, which of the following duties might he be performing?
Responda
-
a. Approving seller invoices.
-
b. Negotiating the contract.
-
c. Bidder conferences
-
d. Weighing seller responses.
Questão 15
Questão
The retail chain is using a vendor to provide engineers for a security camera network design and implementation The team has been completing the work they agreed upon. Both parties are communicating via status reports. The seller has submitted the first payment request. In what process is the team involved?
Questão 16
Questão
The construction project is beginning the initial stages of procurement. The Project Manager is evaluating the best type of contract for the work. He decides not to use the cost plus fixed fee of cost as the buyer has said they dont want that type of contract. Why is a cost plus fixed fee contract bad for the buyer?
Responda
-
a. It provides no reason for the buyer to control the costs.
-
b. It requires use of a more detailed Request for Proposal (RFP).
-
c. It requires the seller to audit all costs incurred.
-
d. It provides no reason for the seller to control costs.
Questão 17
Questão
An airport is buying services from a construction company to put in a new runway for $40M US over four years. At the start of each year, the amount fluctuates relative to the national cost of living. This is an example of what type of contract?
Questão 18
Questão
All of the following statements concerning procurement documents are incorrect EXCEPT:
Responda
-
a. Well-designed procurement documents can simplify comparison of responses.
-
b. Procurement documents must be rigorous with no flexibility to allow consideration of seller suggestions.
-
c. In general, procurement documents should not include selection criteria.
-
d. Well-designed procurement documents do not include a procurement statement of work.
Questão 19
Questão
The sponsor is worried about the seller deriving extra profit on the cost plus fixed fee (CPFF) contract. Each month he requires the Project manager to submit CPI calculations and an analysis of the cost to complete. The Project manager explains to the sponsor that extra profits should NOT be a worry on this project because:
Responda
-
a. The team is making sure the seller does not cut scope.
-
b. All cost invoiced are being audited.
-
c. There can only be a maximum 10% increase if there is an unexpected cost overrun.
-
d. The seller only receives the fee when the Project is completed.
Questão 20
Questão
Once signed, a contract is legally binding unless:
Responda
-
a. One party is unable to perform.
-
b. One party is unable to finance its part of the work.
-
c. It is in violation of applicable law
-
d. It is declared null and void by either party’s legal counsel.