Questão 1
Questão
Most issues/problems require more than one measurement to characterize and
understand. Is this sentence True or False?
Questão 2
Questão
The number of re-work is an example of the following project metrics:
Responda
-
Quality metrics
-
Schedule metrics
-
Risk metrics
-
Resources metrics
-
Cost metrics
Questão 3
Questão
In Configuration Management Tasks what mean “Identification”
Responda
-
Ensure changes are made properly
-
Authority to approve and prioritize changes
-
Controlling changes before and after customer release
-
Tracking changes to multiple SCI versions
-
Tell others about changes made
Questão 4
Questão
In Configuration Management Tasks what mean “Change control”
Responda
-
Ensure changes are made properly
-
Authority to approve and prioritize changes
-
Controlling changes before and after customer release
-
Tracking changes to multiple SCI versions
-
Tell others about changes made
Questão 5
Questão
In Configuration Management Tasks what mean “Configuration auditing”
Responda
-
Ensure changes are made properly
-
Authority to approve and prioritize changes
-
Controlling changes before and after customer release
-
Tracking changes to multiple SCI versions
-
Tell others about changes made
Questão 6
Questão
In Configuration Management Tasks what mean “Version control”
Responda
-
Authority to approve and prioritize changes
-
Tell others about changes made
-
Controlling changes before and after customer release
-
Tracking changes to multiple SCI versions
-
Ensure changes are made properly
Questão 7
Questão
In Configuration Management Tasks what mean “Reporting”
Responda
-
Authority to approve and prioritize changes
-
Tell others about changes made
-
Controlling changes before and after customer release
-
Tracking changes to multiple SCI versions
-
Ensure changes are made properly
Questão 8
Questão
Which one of the above risk areas must be done well on a project and why?
Responda
-
All areas ?
-
Risk Mitigation - Requires the team to setup a plan for ...
-
Risk Identification - Requires the team to produce a ToS
-
Risk prioritization - Requires the team to evaluate ToS
Questão 9
Questão
Metrics should augment and replace, good management judgment. Is this sentence True or False?
Questão 10
Questão
If we have 5 key stakeholder, how many channel of communication we need to
consider?
Questão 11
Questão
Business reorganization canNOT cause changes in current projects (for the same organization).
True/False?
Questão 12
Questão
The schedule is a good way to track a project.
Questão 13
Questão
The schedule ties all parts of the project together.
Questão 14
Questão
User manual is an example of Configuration Item?
Questão 15
Questão
If you are given the rime of a co-worker to help you for the three days and the tasks have the following dependencies. Task B must follow Task A and Task E must follow Task D. How long will the project take?
Task A 2 days | Task B 3 days
Task C 5 days| Task D 2 days
Task E 5 days | Task F 1 day
(Given that you are working only 5 days in a week)
Responda
-
2 weeks 4 days
-
3 weeks
-
3 weeks 3 days
-
4 weeks
Questão 16
Questão
In SCM Processes “Configuration audit”
Responda
-
Independent review or examination to assess if a product or process is in compliance with specification, standards, contractual agreement, or other criteria
-
Used to ensure that changes to a product or system are introduced in a controlled and coordinated manner
-
Administrative tracking and reporting of Cis in CM system
-
Creation and availability of a new version of software to the public
Questão 17
Questão
In SCM Processes “Release management”
Responda
-
Independent review or examination to assess if a product or process is in compliance with specification, standards, contractual agreement, or other criteria
-
Used to ensure that changes to a product or system are introduced in a controlled and coordinated manner
-
Administrative tracking and reporting of Cis in CM system
-
Creation and availability of a new version of software to the public
Questão 18
Questão
In SCM Processes “Status Accounting”
Responda
-
Independent review or examination to assess if a product or process is in compliance with specification, standards, contractual agreement, or other criteria
-
Used to ensure that changes to a product or system are introduced in a controlled and coordinated manner
-
Administrative tracking and reporting of Cis in CM system
-
Creation and availability of a new version of software to the public
Questão 19
Questão
Which sequence is the correct to testing structure (organization)?
Responda
-
Functional Test-> Unit test-> Component test->Regression test
-
Unit test-> Component test-> Regression test ->Functional Test
-
Functional Test-> Unit test-> Regression test-> Component test
-
Unit test-> Functional Test-> Component test-> Regression test
Questão 20
Questão
While measuring the SV (Schedule Variance) we will get the Positive value, what does it mean?
Questão 21
Questão
When considering making the schedule for a project, which of the following items is critical to know?
Responda
-
All of the given
-
The estimates for the project
-
The scope for the project
-
The risks associated with the project
Questão 22
Questão
Critical path method is used in which of the following processes:
Questão 23
Questão
Provide a definition for the following terms:
Responda
-
Metrics - A use of measure to evaluate the state of a process or tasks that are being completed
-
Quality - The process of ensuring that the product or goal is met with certain expectations and abilities meeting what the customer or user wants from the product.
-
Configuration Management - The product that mechanism to ensure that as developed is under control to the point that any version of the product along its lifecycle can be produced.
-
Lifecycle - The understanding of the total existence of a project or product from its first inception to the point at which it is stopped and never acted upon. For the living creatures it is birth to death.
-
Process Model - A representation of the methods that will be used to achieve a goal.
Questão 24
Questão
Please provide a proper description of the notion below:
Responda
-
Metrics - provides measuring units to depict values, threshold, constraints, scope, duration, maximums, minimums, and average, etc
-
Measures - represents information to establish a common understanding of status, condition and position of something.
-
Software Project Metrics - Tools for anyone involved in software engineering to understand varying aspects of the code base, and the project progress.
Questão 25
Questão
Match the abbreviations with the correct definitions:
Responda
-
The amount of budget deficit or surplus at a given point in time, expressed as the difference between the earned value and the actual cost - CV(cost variance)
-
The amount by which the project is ahead or behind the planned delivery date, at a given point in time, expressed as the difference between the earned value and the planned value - SV(Schedule variance)
-
The authorized budget assigned to scheduled work - PV(Planned value)
-
The realization cost incurred for the work performed on an activity during a specific time period - AC (Actual cost)
Questão 26
Questão
If the students had the lecture 2 days ago how much information they can recall?
Questão 27
Questão
Please provide a definition of a critical path of the project schedule
Questão 28
Questão
It is best to represent risks in an IF-Then format
Questão 29
Questão
Leadership is primarily dealing with:
Responda
-
Change Management
-
Situation analysis
-
Attention getting
-
Approval provision
-
Complexity Management
Questão 30
Questão
Configuration management is all about
Responda
-
budget control
-
human resource control
-
change control
-
quality control
Questão 31
Questão
Budgetary or scheduling constraints can cause changes
Questão 32
Questão
Every software engineer has to be concerned how changes are made
Questão 33
Questão
Not an example of Stakeholder:
Responda
-
approving manager
-
external customer
-
project manager
-
3rd-party supplier
-
internal customer
Questão 34
Questão
What organizational structure is most project focused?
Responda
-
Functional
-
Strong Matrix
-
Weak Matrix
-
Balanced Matrix
-
Projectized
Questão 35
Questão
The ___ is key to the definition of a project?
Responda
-
project has a fixed amount of resources to complete it.
-
manager is needed for a project to exist.
-
project time is unchangeable.
-
number of requirements divided by the resources times the hours does not exceed three the scope development time.
-
goal is clear and singular.
Questão 36
Questão
Data used in project can be CI
Questão 37
Questão
What is risk? Choose False
Questão 38
Questão
What is risk? Choose True
Questão 39
Questão
Intangible assets are include:
Responda
-
Franchises
-
Patents
-
Copyrights
-
Inventory
-
Securities like stocks
Questão 40
Questão
New market conditions usually never trigger changes
Questão 41
Questão
Metrics cannot identify, explain or predict everything
Questão 42
Questão
List the set of tasks which if completed will get the project exactly 75% complete?
Task N 10 hours, Task O 5 hours, Task P 7 hours, Task Q 4 hours, Task R 20 hours,
Task S 12 hours, Task T 19 hours, Task U 15 hours, Task V 8 hours.
Responda
-
N,O,P,Q,R
-
N,Q,T,O,R,U,P
-
O,Q,R,T,U,S
-
S,T,U,V
Questão 43
Questão
Configuration Management Maturity
Responda
-
5 Levels
-
4 Levels
-
6 Levels
-
2 Levels
Questão 44
Questão
CPI = EV / actual cost
Questão 45
Questão
Which one of the above risk areas must be done well on a project and why
Responda
-
ALL areas
-
Risk mitigation
-
Risk identification
-
Risk Prioritization
Questão 46
Responda
-
Are drown up early on a project's life cycle – Project Charter
-
Are groups of individuals who have an interest – Stakeholder
-
Splits large project tasks into more manageable – WBS
Questão 47
Questão
What is meant by the term “project network diagram”?
Responda
-
Detailed description of work packages
-
Graphical representation of activities or nodes and the dependencies between them
-
Definition of tasks
-
Protection of the necessary resources
Questão 48
Questão
In the PEAK decision model, risk is one of the outputs of decisions made for project
Questão 49
Questão
Project manager should only at the beginning of the project identify and analyze the risk faced by their project. True or False?
Questão 50
Questão
Gannt chart is used to show project timeline
Questão 51
Questão
Who conduct the beta testing
Responda
-
Developers
-
Testers
-
Customers
Questão 52
Questão
Parkinson’s Law in Project Management Estimation
Responda
-
it is never to reach absolute
-
80% effects from 20% causes
-
work will grow to fill time allocated
-
bad defined project causes failure
Questão 53
Questão
To understand clearly what a project is requires elicitation techniques that work well. How can we best tell if the elicitation techniques we are using work well?
Responda
-
The customer agrees
-
The developers says
-
The requirements are testable
-
The project team is using effort on the project
-
The project management states that they are
Questão 54
Questão
What are the control mechanisms ? Please find TRUE statement
Responda
-
Processes contain lifecycles
-
You cannot control something if you are monitoring it
-
The control mechanism (management) process for a development project should be defined
-
Monitoring and Tracking are the same thing
-
Control and Status are the same thing
Questão 55
Questão
Why do we need teams?
Responda
-
all people are social and work better in social environment
-
a well setup team can better utilize the skills of people
-
everyone knows that a team can do more than individual
-
teams are always fun…
Questão 56
Questão
What type of Stakeholder do you know?
Questão 57
Questão
SRS acronym is stand for Software Requirements Specification
Questão 58
Questão
What types of software testing can involve Users?
Questão 59
Questão
The problem stated as “Can the project be done at the specified cost with the available resources?” is relates to
Responda
-
Project schedule
-
Project quality
-
Project cost
-
Project scope
Questão 60
Questão
How can I identify a clear scope for a project?
Responda
-
There are a clear set of wants from all the stakeholders written up for the scope
-
The customers approves of what is written up as the scope for the project
-
All statements about what needs to be done are well written
-
The development team agrees with what is written up as the scope of the project.
Questão 61
Questão
What does EV metric measure?
Responda
-
Estimated Value - The authorized budget assigned to scheduled work.
-
Elaborative Value - The expected cost to finish all the remaining project work.
-
Executive Value - The sum of all budgets established for the work to be performed.
-
Earned Value - The measure of work performed expressed in terms of the budget authorized for that work.
Questão 62
Questão
What is not an example of Stakeholder?
Responda
-
External customer
-
Third-party supplier
-
Neighbours
-
Approving manager
-
Internal customer
Questão 63
Questão
What is NOT an input for Quality Control Process?
Responda
-
Quality metrics
-
Quality checklists
-
Process flowcharts
-
Validated deliverables
Questão 64
Questão
How many steps are in 'Metrics & Measures - Roadmap' ?
Questão 65
Questão
Tangible assets are include:
Questão 66
Questão
What is an example of Requirements metrics?
Questão 67
Questão
For the basic estimation techniques,you have learned about please select a proper description
Responda
-
Bottom Up - Have an understanding of bottom pieces of the project and then builds the full picture of project estimate
-
Estimation by analogy - Requires a local,idiosyncratic,database
-
Top Down - Generate the top parts and then cost smaller and smaller pieces and add them up
-
Wideband Delphi - Using a group of people to improve an estimate
-
Algorithmic/Parametric - Using computer models to enter values and generate an estimate for a project