Questão 1

Questão
A document called ______________ is created by decomposing the project scope into smaller, more manageable elements.
Responda
  • Scope Statement
  • Network Logic Diagram
  • Work Breakdown Structure
  • Requested Change

Questão 2

Questão
You are working on a project to build a bridge. You have reached the planned halfway mark. The total planned cost at this stage is $500. The actual physical work that has been completed at this stage is worth $400. You have already spent one thousand dollars on the project. What is the CPI?
Responda
  • 0.8
  • 1.2
  • 0.5
  • 0.4

Questão 3

Questão
Preliminary cost estimates are developed during the __________ phase of the project.
Responda
  • Conceptual
  • Detailed Design
  • Implementation
  • Execution

Questão 4

Questão
Cost baseline is usually represented using which curve or line.
Responda
  • slanted line
  • S-curve
  • Z-curve
  • PQ curve

Questão 5

Questão
By completing a forward pass a project scheduler can...
Responda
  • calculate the free float for each activity
  • calculate the total float for each activity
  • score a touchdown
  • find the critical path

Questão 6

Questão
A contractor with an Experience Modification Rate (EMR) of 0.9 regarding accident claims will most likely pay more than the industry average for worker's compensation insurance.
Responda
  • True
  • False

Questão 7

Questão
You are planning to use PERT for planning of your project. A task has pessimistic estimate of 24 days, most likely estimate of 15 days, and optimistic estimate of 12 days. What is the mean using the PERT technique?
Responda
  • 18 days
  • 25.5 days
  • 15 days
  • 16 days
  • 17 days

Questão 8

Questão
The critical path is the set of events that cannot be delayed without causing an extension of the project
Responda
  • True
  • False

Questão 9

Questão
____________ is the number of days that an activity can be delayed without extending the project minimum duration.
Responda
  • Contingency
  • Free Float
  • Total Float
  • Critical Path

Questão 10

Questão
_________________ is the amount of money added to the base estimate to account for risk and uncertainty
Responda
  • Contingency
  • Total Float
  • Free Float
  • Critical Path

Questão 11

Questão
IN 1970, the federal government began a process of providing a comprehensive set of safety rules and regulations, inspection procedures, and safety record-keeping requirements. OSHA was established at this time. OSHA stands for:
Responda
  • Occupation Standards and Health Agency
  • Observe Safe Highways Always
  • Outside Safety and Health Administration
  • Occupational Safety and Health Administration

Questão 12

Questão
The typical construction worker's (craftwork) productive versus nonproductive time can be broken down by percent of time to the following
Responda
  • 50/50
  • 30/70
  • 40/60
  • 75/25

Questão 13

Questão
If BCWS=1000, BCWP=1200, and ACWP=1300, the project is...
Responda
  • Ahead of schedule and under budget
  • Ahead of schedule and over budget
  • Behind schedule and over budget
  • Behind schedule and under budget

Questão 14

Questão
Which activity-to-activity relationship model is assumed when creating a critical path method network diagram?
Responda
  • Start to start
  • Start to finish
  • Finish to start
  • Finish to Finish

Questão 15

Questão
A rough order of magnitude estimate is made during which phase of a project?
Responda
  • project design
  • project closing
  • project executing
  • project initiating

Questão 16

Questão
A construction project has a schedule performance index (SPI) of 1.19 and a cost performance index (CPI) of 0.88. Which of the following is the best explanation for why this occurred?
Responda
  • Unfavorable work conditions
  • Labor rates too high and critical path changed
  • Overstaffing of work
  • Non-critical path activities took less time and cost 12% less

Questão 17

Questão
Project expenses paid by the owner to pay for payroll services provided by the contractors home office is what type of cost?
Responda
  • Direct field cost
  • Indirect project cost
  • Profit
  • Contingency
  • None of the Above

Questão 18

Questão
If BAC (budgeted at completion) for a work package is $10,000 and BCWP=$4,000, the the work package is...
Responda
  • 40 percent complete
  • 80 percent complete
  • 100 percent complete
  • 120 percent complete

Questão 19

Questão
When a project is completed, which of the following must be true?
Responda
  • BAC = ACWP
  • ACWP=BCWP
  • SV=0
  • BAC=ETC (estimated cost to complete)

Questão 20

Questão
If BAC=$24,000, BCWP=$12,000, ACWP=$10,000 and CPI=(BCWP/ACWP)=1.2, then the cost that remains to finish the project is...
Responda
  • 10,000
  • 12,000
  • 14,000
  • Cannot be determined

Questão 21

Questão
To control the schedule, a project manager is reanalyzing the project to predict project duration She does this by analyzing the sequence of activitie with the least amount of scheduling flexibility. What technique is she using?
Responda
  • Critical path method
  • Flowchart analysis
  • Precedence diagramming
  • Work breakdown structure

Questão 22

Questão
You are the project manager of a construction project. The original scope baseline of the project was budgeted at $100,000. Since work on the project start, there have been seventeen authorized and approved changed to the project. The changes have a value of $17,000. There is also an additional change order for $2,500 that has been paid but not yet approved by the owner. What should you report as the current budget for the project?
Responda
  • 100,000
  • 114,500
  • 117,000
  • 119,500

Questão 23

Questão
During the project life cycle, in which part of the life cycle will risk be the lowest?
Responda
  • Initiation
  • Planning
  • Execution
  • Closeout

Questão 24

Questão
In critical path scheduling, total float is calculated as the sum of an activity's early start and the late start (TF = LS + ES)
Responda
  • True
  • False

Questão 25

Questão
Cost Performance Indicator is an index showing the efficiency of the utilization of the resources on the project. Cost Performance Indicator can be calculated using the following formula: CPI = Actual Cost (AC)/Earned Value (EV)
Responda
  • True
  • False

Questão 26

Questão
According to the Association for the Advancement of Cost Engineering (AACE), Class 2 cost estimates are developed during the ___________ phase of the project.
Responda
  • Conceptual
  • Feasibility
  • Budget Authorization
  • Bid

Questão 27

Questão
What are the best uses of PERT?
Responda
  • Used in the planning phase to do "what if" scenarios for the project.
  • Assist in the controlling of changes to the project.
  • Is used in the process of preparing a WSB for the project.
  • To measure future consequences of activities.
  • A & D

Questão 28

Questão
Activities with little total float are called "near-critical" activities, because they can quickly become critical if their small amount of total float is used up in a delay.
Responda
  • True
  • False

Questão 29

Questão
A proper Work Breakdown Structure includes:
Responda
  • Physical components of the final constructed product.
  • Activities required to construct the final product that do not directly build a physical component.
  • Both physical components of the final constructed product and activities required to construct the final product that do not directly build a physical component.
  • The responsibilities of specific project organizations or people for specific wok packages.
  • None of the above

Questão 30

Questão
The Spearin doctrine is a legal principle that holds that when a contractor follows the plans and specifications furnished by the owner, and those plans and specifications turn out to be defective or insufficient, the contractor is not liable to the owner for any loss or damage resulting from the defective plans and specifications.
Responda
  • True
  • False

Questão 31

Questão
According to CVEN 349 lecture and the text, forecasts of future costs can be uncertain due to
Responda
  • Technology changes
  • Forecast errors due to economic conditions
  • Analysis Errors
  • A & B
  • All of the Above

Questão 32

Questão
For most construction activities there may be no direct relationship between elapsed time, actual work, and incurred costs?
Responda
  • True
  • False

Questão 33

Questão
A cost performance index (CPI) of 0.89 means
Responda
  • At this time, we expect the total project to cost 89 percent more than planned
  • When the project is completed, we will have spent 89 percent more than planned
  • The project is only progressing at 89 percent of that planned
  • The project is only getting 89 cents out of every dollar invested

Questão 34

Questão
An Organizational Breakdown Structure (OBS) can include
Responda
  • Activities required to construct the final product that do not directly build a physical component
  • Both physical components of the final constructed product and activities required to construct the final product that do not directly build a physical component
  • The responsibilities of specific project organizations or people for specific work packages
  • None of the above

Semelhante

Expertise in Project Management
tonesha_g
PMP® Pre-Test by Coursefountain.com
Team Coursefountain
Ch1 - The nature of IT Projects
mauricio5509
Introduction notes on SCRUM Project management framework.
Wesley Thomson
Project Management: Week 1
Sharon Ott
Summary of Definitions/Key Terms for the PMP Exam
Andrea Leyden
PMP Prep quiz
Andrea Leyden
06 PROJECT TIME MANAGEMENT
miguelabascal
Project Scope Management Process
neeshar
Project Management Integration
craigmag
PMP Executing, Monitoring and Controlling Processes
myrdenafrancis