Questão 1

Questão
You are the Project Manager for a large construction project. While reviewing the expenditures, you realize that you are 20% over budget. What process group are you working in?
Responda
  • Closure
  • Execution
  • Planning
  • Monitor & Control

Questão 2

Questão
What is the main benefit of a balanced matrix organization over a projectized organizational structure?
Responda
  • As a Project Manager, you have a great deal of authority
  • More efficient use of resources
  • Reporting to a functional manager
  • Reporting to 2 Managers

Questão 3

Questão
As the Sponsor on a large, multi-national hydroelectric power project, during the execution phase, your primary responsibilities are to:
Responda
  • Provide the financial resources and champion the project
  • Manage a group of interrelated projects
  • Manage the Project Team
  • Provide status updates to the customer

Questão 4

Questão
Name the 5 project management process groups.
Responda
  • Initiating, Planning, Executing, Monitoring & Control, Closing
  • Planning, Executing, Monitoring, Integrated Change, Closing
  • Business Case, Planning, Executing, Monitoring & Control, Closing

Questão 5

Questão
You are hired to manage an exciting new project for a software development company making CRM tools. You are unfamiliar with the project management resources available in the company. Who should you go to for help identifying the resources and best practices?
Responda
  • Project Sponsor
  • Operations Manager
  • Other Project Managers
  • Project Management Office

Questão 6

Questão
As you progress through the project life cycle:
Responda
  • Risk increases and cost of changes increases
  • Cost of changes decreases and risk increases
  • Risk decreases and cost of changes increases
  • Cost of changes decreases and risk decreases

Questão 7

Questão
The purpose of the Closer Process Group is:
Responda
  • Complete the work as quickly as possible
  • Analyze the project risks at the end of the project
  • Inspect the outputs to ensure the quality is as planned
  • Formally complete the project

Questão 8

Questão
In the Statement Of Work, you provide:
Responda
  • Project charter
  • Market demand analysis
  • Change control tools you will use
  • Scope description

Questão 9

Questão
The output of the Develop Project Charter process is:
Responda
  • Project charter
  • Project Management Plan
  • Work performance data
  • Business case

Questão 10

Questão
According to the PMBOK all the following are types of project constraints except:
Responda
  • Scope
  • Portfolio Alignment
  • Risks
  • Schedule

Questão 11

Questão
You are the Project Manager for a project that will design and build the iPhone X, the latest in mobile phone technology. The requirements call for a new production facility in Asia. Immediately after working with Senior Management to create a business case and statement of work for the new production facility, what document will you want to produce?
Responda
  • Project document updates
  • Lessons learned
  • Project plan
  • Project charter

Questão 12

Questão
The ideal Project Team size is?
Responda
  • 10-15
  • 3-6, 6-9

Questão 13

Questão
Your project has been officially approved by your sponsor, what process group will you move from and which process group will you move to?
Responda
  • Planning to execution
  • Initiation to execution
  • Planning to initiation
  • Initiation to planning

Questão 14

Questão
All the following are examples of expert judgement except:
Responda
  • PMO
  • Tech manuals
  • PM information system
  • Professional associations

Questão 15

Questão
In Project Integration Management, as you develop the Project Management Plan, you will:
Responda
  • Direct and manage the planning of work defined in the Project Charter and implement to achieve the project’s objectives
  • Provide the project schedule which is derived from progress against the schedule baseline.
  • Validate plans and changes from Perform Integrated Change Control and ensure that the changes are appropriately executed
  • Define, prepare, and coordinate all subsidiary plans and integrate them into a comprehensive plan.

Questão 16

Questão
The process group where you will identify if any changes to the plan are needed and initiate those plans is:
Responda
  • Monitoring and control
  • Executing
  • Planning
  • Initiating

Questão 17

Questão
The organizational structure that gives project managers a very high degree of authority over their project is:
Responda
  • Functional
  • Projectized
  • Weak matrix
  • Strong matrix

Questão 18

Questão
The largest portion of the projects budget will be expended in what process group?
Responda
  • Planning
  • Execution
  • Closing
  • Monitoring and control

Questão 19

Questão
All of the following are examples of Enterprise Environmental Factors EXCEPT:
Responda
  • Established communication channels
  • Organizational culture
  • Project management information system
  • Project charter

Questão 20

Questão
The leader of the project is working on completing a database upgrade but cannot get the additional resources she needs to be able to complete the project. The rest of the project team is working on daily operations work. The leader has not been given the authority to put additional resources on the project. What is the organizational structure this team is working in?
Responda
  • Project team
  • Strong matrix
  • Projectized
  • Functional

Questão 21

Questão
Portfolio management refers to:
Responda
  • Applying resource-leveling heuristics across all the organization's projects to achieve the organization's strategic objectives.
  • Managing the levels of functional authority to facilitate project decision making.
  • Managing various contents of the project file
  • The centralized management of one or more portfolios to achieve strategic objectives.

Questão 22

Questão
A project has all of the following characteristics except:
Responda
  • Short duration
  • Unique
  • Temporary endeavor
  • Specific end

Questão 23

Questão
A program is:
Responda
  • Project over 1$ mill
  • Group of related projects, subprograms & program activities managed in a coordinated way.
  • Sequence of steps constituting a project
  • Group of related tasks lasting one year or less

Questão 24

Questão
The project manager has the lowest level of authority in this type of organization:
Responda
  • Projectized
  • Weak matrix
  • Strong matrix
  • Functional

Questão 25

Questão
Project Management Process Groups are:
Responda
  • Genearlly, discrete, one-time events
  • Overlapping activities that occur throughout the project
  • Overlapping activities that generally occur at the same level of intensity within each phase of the project.
  • Discrete, repetative events that occur generally at the same level of intensity throughout each phase of the project.

Questão 26

Questão
Decomposition is:
Responda
  • Creating subproject to ensure scope
  • Organizing and defining the complete scope
  • Subdividing project scope & deliverables into more manageable components
  • Documents planning assumptions

Questão 27

Questão
You are exactly half way through a construction project when the customer insists that you add a third entry way. What process will you need to follow to make the updates?
Responda
  • Validate scope
  • Brainstorming
  • Control scope
  • Collect requirements

Questão 28

Questão
What process group determines how the scope is defined?
Responda
  • Create WBS
  • Control scope
  • Plan scope management
  • Define scope

Questão 29

Questão
Requirements must be:
Responda
  • A component of change control
  • A validated for conformity as part of the project scope statement
  • An out put of the Validate Scope process
  • Measureable

Questão 30

Questão
All of the following are tools for collecting requirements EXCEPT:
Responda
  • Focus groups
  • Observations
  • Interviews
  • Quality assurance

Questão 31

Questão
The process that documents stakeholder needs to meet the projects objectives are:
Responda
  • Decomposition
  • WBS
  • Validate scope
  • Collect requirements

Questão 32

Questão
Acceptance Criteria is:
Responda
  • Part of the lessons learned
  • Unique & verifiable product, result or capability for a product
  • A set of conditions that is required to be met before deliverables are accepted.
  • Given by the PMO

Questão 33

Questão
The project scope statement is:
Responda
  • Determining, documenting, and managing stakeholder needs and requirements.
  • Set of conditions that is required to be met before deliverables are accepted.
  • The features and functions that characterize a project.
  • Description of the project, major deliverables, assumptions and constraints

Questão 34

Questão
The WBS is:
Responda
  • Project schedule components organized by work package
  • Work breakdown system
  • Project document updates
  • a hierarchical decomposition of the total scope of work to be carried out by the project team

Questão 35

Questão
The lowest level of WBS components are:
Responda
  • Quality requirements
  • Acceptance criteria
  • WBS dictionary
  • Work packages

Questão 36

Questão
The project scope statement includes all of the following except:
Responda
  • Scope baseline
  • Scope description
  • Deliverable
  • Acceptance criteria

Questão 37

Questão
One of the outputs for the validate scope process is:
Responda
  • Acceptance criteria
  • Resources required
  • Description of work
  • Accepted deliverables

Questão 38

Questão
Which of the following provides more detailed information?
Responda
  • Scope statement
  • Scope baseline
  • WBS
  • WBS dictionary

Questão 39

Questão
You are the leader of the Project Management Office for your company. One day, an experienced Project Manager asks why he should go to the trouble of creating a Work Breakdown Structure for his new project. The best answer would be:
Responda
  • It is optional
  • It is a legal requirement for external projects
  • It will help you organize project deliverables & work
  • It helps to verify project quality

Questão 40

Questão
What is the purpose of the validate scope process?
Responda
  • Collect requirements for the project
  • Make needed changes to the project charter
  • Acceptance of the project deliverables
  • Create WBS

Questão 41

Questão
Create WBS is in which process group?
Responda
  • Execution
  • Monitoring & control
  • Initiation
  • Planning

Questão 42

Questão
Gold plating is:
Responda
  • Decreasing risk by providing project safeguards
  • Changing requirements to improve the project
  • Giving a customer more than they want
  • Taking features away to keep costs down

Questão 43

Questão
Project scope is:
Responda
  • Making sure there is no gold plating in the project
  • The value created by completing a project under budget and on schedule
  • Determining, documenting & managing stakeholder needs and requirements
  • Work performed to deliver a product, service or results with specified features and functions

Questão 44

Questão
What is the WBS typically used for?
Responda
  • Defines the stakeholder list
  • Identifies the logical person to be the sponsor
  • Defines the level of reporting that the seller provides the buyer
  • Organizes & defines the work elements required to create the required deliverables

Questão 45

Questão
Which of the following processes is not an output of the control scope process?
Responda
  • Work performance information
  • Change requests
  • Project document updates
  • Accepted deliverables

Questão 46

Questão
You are managing a global project that involves stakeholders and several international locations. You are likely to consult the WBS dictionary to find:
Responda
  • Strengths, weaknesses, opportunities, and threats of key stakeholders and their impact upon the WBS.
  • Detail deliverable, activity, and scheduling information about each component in the WBS.
  • Accepted deliverables
  • High level task information for the schedule management plan

Questão 47

Questão
The following is an example of a constraint associated with the project scope that limits the team's options and scope definition:
Responda
  • Threat of a strike
  • Quality of analysis
  • Predefined budget or any imposed dates/schedule milestones that are issued by the customer or performing organization.
  • Existing relationships with sellers, suppliers, or others in the supply chain

Questão 48

Questão
An output of the define scope process is:
Responda
  • WBS
  • Scope & schedule delays control plan
  • Project scope statement
  • Resource breakdown structure

Questão 49

Questão
The difference between the Project Charter and the Project Scope Statement is:
Responda
  • The Project Scope Statement lists high level technical requirements and regulatory constraints.
  • The Project Scope Statement provides a high level description of scope elements.
  • The Project Charter provides a high level description of scope elements.
  • The Project Charter lists project deliverables in smaller, more manageable components.

Questão 50

Questão
Control scope:
Responda
  • Updates the WBS dictionary to ensure all tasks are accounted for
  • Ensures risks are mitigated
  • Plans how to determine scope
  • Manages changes to the scope baseline

Questão 51

Questão
Plan schedule management is:
Responda
  • Identifying and documenting logical relationships among project activities.
  • Analyzing activity sequences to create the project schedule baseline.
  • Monitoring the status of project activities to ensure they are performing to expected specifications in regards to project constraints.
  • Establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.

Questão 52

Questão
The duration of a milestone is:
Responda
  • 0 days
  • 1 days
  • 10 days

Questão 53

Questão
What is the best tool for determining the overall length of a project?
Responda
  • WBS
  • Precedence diagram
  • Expert judgement
  • Pie chart

Questão 54

Questão
The critical path is:
Responda
  • The shortest sequence duration
  • The sequence of activities that are determined to be key activities for successful project execution
  • The path with the highest number of activities
  • The shortest amount of time you can get the project done in

Questão 55

Questão
The maximum amount of slack in the critical path is:
Responda
  • +1
  • -1
  • 0

Questão 56

Questão
The Critical Path has a duration of 10. There is an independent sequence, XYZ. Activity X has a duration of 2. Activity Y has a duration of 3. Activity Z has duration of 2. The EAC is 4000. The total float of XYZ is:
Responda
  • 0
  • 3

Questão 57

Questão
To complete your project on time, you ask for additional overtime for your project team. This is an example of:
Responda
  • Fast tracking
  • Crashing
  • Critical chain
  • Schedule network analysis

Questão 58

Questão
Lag is:
Responda
  • The time an activity will start sooner than its dependency
  • Determined by the critical chain
  • The time when an activity is dependent on another activity to start at the same time
  • The time an activity will start later than its dependency

Questão 59

Questão
You ask your construction manager how long it will take to complete the new server room. He gives you a likely estimate of 6 weeks, but says it may take as long as 10 weeks. He may be able to get it done in 4 weeks if everything goes well. Calculate your PERT estimate of how long it will take to complete the server room.
Responda
  • 20 weeks
  • 6.3 weeks
  • 6 weeks
  • 4.6 weeks

Questão 60

Questão
The method where buffers are added to each activity to account for resource availability is:
Responda
  • Critical path
  • Resource leveling
  • Critical chain
  • Crashing

Questão 61

Questão
A benefit of bottom-up estimating is:
Responda
  • Determines resources need to schedule the project
  • Ability to automate your estimate
  • Allows for what-if analysis
  • A more accurate estimate

Questão 62

Questão
One of the outputs of the Develop Schedule process group that helps create the Project Management plan is:
Responda
  • Sequence activities
  • Work package acceptance criteria
  • Schedule baseline
  • Scope baseline

Questão 63

Questão
The minimum project duration is 6 months. Another path, series ABCD, will take 4 months to complete. In addition, series EFG will take 2 months. How much float is in ABCD?
Responda
  • 4 months
  • 0 months
  • 2 months
  • 12 months

Questão 64

Questão
Which of the following allows you to accomplish tasks in parallel when they normally would be done in sequence?
Responda
  • Fast tracking
  • Critical chain
  • Resource leveling
  • Crashing

Questão 65

Questão
Analogous estimating is a technique for estimating the duration or cost of an activity or project using historical data from a similar activity or project. What is the disadvantage of this technique?
Responda
  • More costly
  • Takes more time
  • Requires using PERT
  • Less accurate

Questão 66

Questão
Your project will run through the summer when your employees generally take vacation. To account for the risk of lower resource availability in your project plan, you could use:
Responda
  • Critical chain
  • Crashing
  • Resource leveling
  • Fast tracking

Questão 67

Questão
You need Activity A in your project plan to start 3 days before Activity B. Activity B would be called:
Responda
  • Lag
  • Lead
  • Critical chain

Questão 68

Questão
You are creating the Schedule Baseline for a multi-national government pipeline project that will deliver oil faster and cheaper. You need to know how long it will take to build the new capacity. Who would you consult to determine the time required?
Responda
  • Government experts
  • Project sponsor
  • Scrum master
  • The people that will be doing the work

Questão 69

Questão
An example of a finish to finish relationship is:
Responda
  • Rocket fuel tanks that must be filled prior to launch
  • A dinner cruise that sells tickets up until departure
  • Dinner when all of the food is ready at the same time
  • Drag racing

Questão 70

Questão
Parametric estimating:
Responda
  • Accounts for risk
  • Is where an algorithm is used to calculate cost or duration based on historical data
  • Focuses on planning at a daily activity level

Questão 71

Questão
In rolling wave planning:
Responda
  • Focus is maintained on long-term objectives, allowing near-term objectives to be rolled out as part of the ongoing wave of activities.
  • The work to be accomplished in the near term is planned in detail, the work in the more distant future is planned at a higher level.

Questão 72

Questão
Analogous duration estimating is:
Responda
  • Frequently used to estimate project duration when there is a limited amount of detailed information about the project
  • A bottom up estimating technique
  • Based on multiple duration estimating
  • Generally more accurate than other duration estimating methods when expert judgement is used

Questão 73

Questão
To enter logical dependencies in MS project you enter the dependency in which column:
Responda
  • Predecessor
  • Resource
  • Linkages
  • Critical chain

Questão 74

Questão
Outputs from the Estimate Activity Resources process include:
Responda
  • Activity resource requirements
  • Salary schedules for various project human resources
  • Risk register
  • Activity list

Questão 75

Questão
An example of a mandatory dependency is:
Responda
  • A dependency established based on knowledge of best practices within a particular application area
  • A dependency established based on some unusual aspect of the project where a specific sequence is desired
  • On a construction project, to erect the superstructure only after the foundation has been built.
  • On a software development project, to start design only after completion and approval of all project requirements.

Questão 76

Questão
Earned Value is:
Responda
  • Actual cost of work scheduled
  • AC / % Complete
  • Measure of work expressed in terms of budget authorized for that work

Questão 77

Questão
A SPI is 1.4 - your project is?
Responda
  • Ahead of schedule
  • Over budget
  • Under budget

Questão 78

Questão
You are 1 month into your project. You need to determine how much your project will cost when it is done. What Earned Value metric will you use to determine the cost?
Responda
  • BAC
  • EAC

Questão 79

Questão
Project XYZ has a Schedule Variance of -500. That means that:
Responda
  • The SPI is 500
  • Your project is behind schedule

Questão 80

Questão
Your EAC is 4000. The PV is 1000. The AC is 400. What is the ETC?
Responda
  • -10
  • 10
  • 2600
  • 3600

Questão 81

Questão
All of the following are processes included in Project Cost Management except:
Responda
  • Determine budget
  • Estimate activity resources
  • Estimate costs
  • Control costs

Questão 82

Questão
Planned value is:
Responda
  • Actual cost of work
  • Realized cost of work
  • Authorized budget assigned to the scheduled work
  • Difference btwn earned value and actual cost

Questão 83

Questão
If the earned value is 40,000, the planned value is 50,000, and the actual cost is 45,000, what is the cost performance index?
Responda
  • 1.13
  • .88
  • 1.27

Questão 84

Questão
In class, we discussed that in Initiation, a Rough Order of Magnitude estimate should be within what percent?
Responda
  • + - 25%
  • + - 3%
  • + - 50%

Questão 85

Questão
Your project is behind schedule and over budget. When calculating the project’s CPI, you will get:
Responda
  • number greater than 1
  • number less than 1

Questão 86

Questão
What metric will show how efficiently the project team is using time?
Responda
  • PV
  • SPI
  • CPI
  • SV

Questão 87

Questão
The output of the determine budget process is:
Responda
  • Schedule
  • Cost forecasts
  • Cost management plan
  • Cost baseline

Questão 88

Questão
During a project, earned value analysis is performed. You get the following numbers: EV = 50,000 PV = 60,000 AC = 75,000 What are the correct results?
Responda
  • CV = -25000 SV = -10000
  • CV 10000 SV= -15000

Questão 89

Questão
There are 4 activities in your project. Activity A has a planned value of 20,000. Activity B has a planned value of 30,000. Activity C has a planned value of 10,000. Activity D has a planned value of 40,000. What is the BAC?
Responda
  • 25000
  • 37000
  • 12500
  • 100000

Questão 90

Questão
Determine the variance at completion with the following information: SV = -50,000 Estimate at completion = 100,000 Budget at completion = 200,000
Responda
  • 50000
  • 10000
  • 2
  • 1.5

Questão 91

Questão
Direct costs are:
Responda
  • Directly related to the project and can be controlled
  • Included in overhead costs
  • Excluded from the project budget
  • Part of activity cost estimates

Questão 92

Questão
Which of the following processes do not belong to the Project Cost Management process group?
Responda
  • Plan cost management
  • Control cost
  • Determine budget
  • Contingency reserve

Questão 93

Questão
Cost estimation of individual work packages or activities is called:
Responda
  • Bottom-up estimating
  • Analogous estimating
  • Three point estimation
  • Expert judgement

Questão 94

Questão
The output of determine budget is:
Responda
  • Cost management plan
  • Activity cost estimate
  • Cost baseline

Questão 95

Questão
The earned value calculations for your project are: BAC = 10,000 EAC = 5,000 ETC = 4,000 What is the VAC and will you be over or under budget?
Responda
  • 6000 and over budget
  • 5000 and over budget
  • 1000 and over budget
  • 6000 and under budget

Questão 96

Questão
Parametric estimating involves:
Responda
  • Defining cost or duration parameters of the project lifecycle
  • Calculating the individual cost estimates or each work package & integrating them to obtain the total cost of the project
  • Using statistical relationship between relevant historical data and other variables to calculate a cost estimate for project work

Questão 97

Questão
The EAC is based on:
Responda
  • The actual costs incurred for work completed (AC) and the estimate to complete (ETC) the remaining work
  • The EV and the actual cost for work completed CV
  • The cost performance index (CPI) and the cost of variance (CV).

Questão 98

Questão
Earned value management (EVM) is a commonly used:
Responda
  • Analysis of the value of the equipment that has been installed in the project as of the status to date.
  • Analysis of the sum of the labor costs, which have been incurred on the project to date.
  • Method to assess performance management and progress for projects.
  • Method of measuring the amount of money that has been spent on the project to date.

Questão 99

Questão
You're earned value management analysis indicates that your project is falling behind its baseline schedule. You know this because the cumulative EV is much:
Responda
  • Higher than the AC
  • Higher than the PV
  • Lower than the PV
  • Lower than the CPI

Questão 100

Questão
Item PV AC EV 1 10,000 11,000 10,000 2 9,000 8,000 7,000 3 8,000 8,000 8,000 4 7,000 7,000 5,000
Responda
  • 1
  • 2
  • 3
  • 4

Questão 101

Questão
Plan quality management is:
Responda
  • Process of identifying quality requirements
  • Planning the cost of precision measurement
  • Identifying project grade
  • Auditing the quality requirements and results

Questão 102

Questão
What would be the least effective tool or method to reduce quality cost?
Responda
  • Statistical sampling
  • Inspection
  • Nominal group technique
  • Control charts

Questão 103

Questão
Quality is:
Responda
  • Measure of exactness
  • Assessment of correctness
  • Degree to which a set of inherent characteristics fulfill requirements

Questão 104

Questão
The 3 quality processes in project quality management are:
Responda
  • Determine quality, monitor quality, plan quality
  • Cost benefit analysis, cost of quality, cost of conformance
  • Plan quality management, control quality, perform quality assurance

Questão 105

Questão
The Ishikawa Diagram tool is used to:
Responda
  • Gather info on the frequency of poor quality
  • Help identify the actionable root cause of the problem
  • Describe the central tendency of a process
  • Show if a process is stable and predictable

Questão 106

Questão
Grade is:
Responda
  • Measure of exactness
  • Measure of correctness
  • Categorization of deliverables having the same functional use but different technical characteristics

Questão 107

Questão
The cost of quality includes all of the following EXCEPT:
Responda
  • Prevention costs
  • Returns
  • Raw materials
  • Customer service

Questão 108

Questão
The quality management plan is an output of which process:
Responda
  • Project quality management
  • Plan quality management
  • Control quality

Questão 109

Questão
Increased prevention costs should result in:
Responda
  • Increased frequency of external failures
  • High internal failure costs
  • Decreased internal and external failure costs

Questão 110

Questão
Pareto diagrams:
Responda
  • Are used to gather attributes data while performing inspections
  • Identify the vital few sources that are responsible for causing the most problems
  • Are used to monitor cost and schedule variances

Questão 111

Questão
Perform quality assurance is:
Responda
  • The processes and activities that will determine quality policies, objectives & responsibilities
  • Auditing the quality requirements and results from quality control measurements
  • Process of determining project grade

Questão 112

Questão
Scatter diagrams:
Responda
  • Show forces for and against change
  • Map operational details of procedures
  • Seek to explain changes in variable Y in relation to changes in X

Questão 113

Questão
A project manager can use a control chart to determine:
Responda
  • The central distribution of a statistical distribution
  • If the amount of prevention costs are increasing
  • If a process is stable or predictable

Questão 114

Questão
The results of performing the control quality process are:
Responda
  • Decreased costs
  • Stable processes
  • Verified deliverables

Questão 115

Questão
An example of appraisal costs is:
Responda
  • Rework
  • Warranties
  • Training
  • Inspections

Questão 116

Questão
The perform quality assurance process is in:
Responda
  • Execution
  • Planning
  • Monitor & Control

Questão 117

Questão
Checksheets are:
Responda
  • Used to organize facts in a manner that will facilitate the effective collection of useful data about a potential quality problem
  • Used to monitor cost & schedule variances
  • Used to describe the central tendency, dispersion, and the shape of the distribution

Questão 118

Questão
Degree of quality should be:
Responda
  • Inspected in
  • Planned in
  • SWOT

Questão 119

Questão
Control Quality is:
Responda
  • Comparing the cost of quality to the requirements
  • Achieving project objectives of scope, time & cost
  • Process of monitoring & recording results of quality activities to asses project performance

Questão 120

Questão
Understanding, evaluating, defining & managing requirements are essential to satisfying:
Responda
  • Customer expectations
  • The scope statement
  • Upper management
  • Functional requirements

Questão 121

Questão
The quality management plan is a component of the ________________ that describes how the organization's quality policies will be implemented.
Responda
  • WBS
  • Project scope
  • Project management plan

Questão 122

Questão
The seven basic quality tools include all of the following EXCEPT:
Responda
  • Calibration graphs
  • Pareto diagrams
  • Control charts

Questão 123

Questão
Inspection is:
Responda
  • Examination of a work product to determine if it conforms to documented standards
  • Documenting results of control quality activities
  • A validated deliverable required by the project

Questão 124

Questão
Which of the following is true regarding precision and accuracy?
Responda
  • Precision is a measure of correctness whereas accuracy is an assessment of exactness
  • Precision is a measure of exactness, whereas accuracy is an assessment of correctness.

Questão 125

Questão
Project Human Resource Management includes the following processes:
Responda
  • Acquire project team, develop project team, HR management plan, performance assessments
  • Plan HR team, manage project team, evaluate project team, identify project roles
  • Plan HR management, acquire project team, develop project team, project team

Questão 126

Questão
The human resource management plan is an output of which process:
Responda
  • Acquire project team
  • Plan HR management
  • Develop project team
  • Manage project team

Questão 127

Questão
The best illustrate for your project teams reporting relationships you would use:
Responda
  • Matrix chart
  • RACI chart
  • A hierarchical chart

Questão 128

Questão
Which of the following is NOT one of toucans 5 stages of team development?
Responda
  • Norming
  • Storming
  • Adjourning
  • Developing

Questão 129

Questão
There is a critical disagreement between two of your project team members. You need to help them resolve the issue. To help them find a solution that is a win for both sides, you would use which technique for resolving conflict?
Responda
  • Force
  • Withdraw
  • Collaborate
  • Smooth

Questão 130

Questão
RACI stands for?
Responda
  • Rational Accountable Creative Informed
  • Responsible Actionable Creative Independent
  • Responsible Accountable Consulted Informed

Questão 131

Questão
The project manager:
Responda
  • Performs the work of the project
  • The person assigned to lead the team that is responsible for achieving the project objectives
  • The person who provides the resources and support for the project

Questão 132

Questão
A member of your team has broken one of the agreed upon ground rules, who should enforce the rule?
Responda
  • PMO
  • Project Manager
  • All project team members
  • Sponsor

Questão 133

Questão
The process of developing an appropriate approach and plan for project communications based on stakeholder’s needs, requirements, and available organizational assets is:
Responda
  • Control communications
  • Plan communications management
  • Manage communications
  • Develop communications plan

Questão 134

Questão
In addition to distributing information, the Manage Communications process is also concerned with:
Responda
  • Making sure the information has been received and understood
  • Creating the project communications plan
  • Planning the correct channel to use to distribute the information

Questão 135

Questão
For your new project, you need to produce a simple status update for your Sponsor. What information would you not want to include?
Responda
  • Lessons learned
  • Current status
  • Risks

Questão 136

Questão
As a Project Manager in a matrix environment, you do not have direct authority over your project team. However, your team likes you and enjoys working for you. You are relying on what type of influence?
Responda
  • Formal
  • Referent
  • Expert
  • Reward

Questão 137

Questão
What topic would likely be covered in the kick off meeting?
Responda
  • Procurement plan
  • Lessons learned
  • Performance evaluations
  • Roles and responsibilities

Questão 138

Questão
Mid-way through a project, your sponsor comes to you and asks for a monthly project status report to be produced that will help the executive team understand the progress being made on the project. What process are you in now?
Responda
  • Plan communications management
  • Control communications
  • Communication models
  • Manage communications

Questão 139

Questão
You have a virtual team working on your project. What is a disadvantage of having a team that is not all located in the same place?
Responda
  • Cannot have kick off meetings
  • Opportunity for misunderstandings
  • Easy conflict resolution

Questão 140

Questão
The PMO:
Responda
  • Is a person/group that provides resources/support
  • Standardizes the project related governance
  • Is a collection of logically related project activities that culminates in the completion of one or more deliverables

Questão 141

Questão
Your project team is beginning to work together and adjust their habits to support the team. They are beginning to trust each other more. What development stage is your team in?
Responda
  • Forming
  • Withdraw
  • Forcing
  • Norming

Questão 142

Questão
You are creating a weekly status update, what process are you in?
Responda
  • Develop project team
  • Control communications
  • Manage communications
  • Plan communications management

Questão 143

Questão
Your project team is well organized, interdependent and handles issues effectively. What stage are they in?
Responda
  • Developing
  • Norming
  • Performing

Questão 144

Questão
The HRMP should generally include all of the following EXCEPT:
Responda
  • Staffing management plan
  • Project interfaces
  • Roles & responsibilities
  • Project organization charts

Questão 145

Questão
Techniques and considerations for effective communications management generally includes all of the following EXCEPT:
Responda
  • Employing organizational process assets to reduce risk
  • Facilitation techniques for building consensus
  • Listening techniques

Questão 146

Questão
The acquisitions strategy for acquiring a project team consists of:
Responda
  • Hiring consultants from the outside
  • Obtaining resources through ranking criteria
  • Acquiring members of the team from other teams within the organization

Questão 147

Questão
The Acquire Project Team is the process of confirming human resource availability and obtaining the team necessary to complete project activities. The enterprise environmental factors that can influence this process generally include all of the following EXCEPT:
Responda
  • Organizational structure
  • Multi-criteria decision analysis
  • Competency levels, prior experience & cost rate.

Questão 148

Questão
Generally acknowledged techniques for resolving conflict include:
Responda
  • Accept, compromise, attack & separate
  • Smooth compromise collaborate co-locate
  • Accommodate compromise force & collaborate

Questão 149

Questão
Project risk is:
Responda
  • A condition that causes negative impact to the project
  • A threat to the success of the project
  • An uncertain event that if it occurs has a positive or negative effect

Questão 150

Questão
The strategy to address opportunities and seek to ensure the opportunity happens is:
Responda
  • Avoid
  • Enhance
  • Exploit

Questão 151

Questão
The risk register is an output of which project risk management process?
Responda
  • Performing qualitative risk analysis
  • Perform quantitative risk analysis
  • Plan risk management
  • Identify risks

Questão 152

Questão
The following process is in monitoring & control:
Responda
  • Plan risk management
  • Control risks
  • Perform quant risk analysis

Questão 153

Questão
Relies on anonymous feedback from experts through questionnaires and drives toward consensus
Responda
  • Root cause analysis
  • Probability impact matrix
  • Delphi technique
  • Risk register

Questão 154

Questão
The risk register should include:
Responda
  • Identified risks & WBS number
  • Identified risks & potential responses
  • Risk categorization & identified risks
  • Identified risk & risk analysis

Questão 155

Questão
Is used to determine the risk rating to help prioritize risks:
Responda
  • Risk categorization
  • Risk register
  • Expected monetary value analysis
  • Probability & impact matrix

Questão 156

Questão
Helps compare the relative importance & impact of variables that have a high degree of uncertainty to those that are more stable:
Responda
  • Expected monetary analysis
  • Tornado diagram
  • Decision tree
  • Monte carlo technique

Questão 157

Questão
Uses a computer to produce many simulations using random sampling to obtain probable results distribution:
Responda
  • Expected monetary analysis
  • Monte Carlo technique
  • Decision tree diagram
  • Sensitivity analysis

Questão 158

Questão
You are building a skyscraper in New York City. If the project falls behind schedule, you will lose millions of dollars in fees to the city. You want to shift the financial burden of the threat of fees to a third party. What strategy should you use?
Responda
  • Mitigate
  • Avoid
  • Exploit
  • Transfer

Questão 159

Questão
Your software project is given very good press in The Wall Street Journal. You want to make sure the chances for success are increased so you add more resources to the project. What strategy are you using?
Responda
  • Share
  • Accept
  • Transfer
  • Enhance

Questão 160

Questão
Qualitative risk analysis deals with:
Responda
  • Developing options for risk responses
  • Numerically analyzing the effect of risks
  • Prioritizing risks
  • Monitoring residual risks

Questão 161

Questão
Using Expected Monetary Value Analysis, calculate the average outcome for a project that has either a $300,000 profit and 30% chance of achieving it, or a $100,000 loss and 70% chance of having that happen.
Responda
  • 160,000
  • 20,000
  • 400,000
  • 90,000

Questão 162

Questão
Process of determining options to reduce threats and enhance opportunities:
Responda
  • Identify risks
  • Control risks
  • Plan risk response
  • Perform qualitative risk analysis

Questão 163

Questão
Your Risk Register calls out several risks, including not having enough resources available to complete the software in time to ship it. You check in weekly with the developers to make sure the software will be completed in time. What process are you in?
Responda
  • Plan risk management
  • Control risks
  • Plan risk response
  • Identify risks

Questão 164

Questão
When using the Delphi technique, you should:
Responda
  • Have a unanimous decision
  • Encourage brainstorming
  • Not share the responses through the entire process
  • Make sure the participants are experts

Questão 165

Questão
In the plan risk responses process, an accept strategy for a negative risk or threat indicates that the project team has decided:
Responda
  • To agree with the PM
  • To eliminate a specific threat or risk
  • Not to change the project management plan to deal with a risk, or is unable to identify any other suitable response strategy

Questão 166

Questão
As an update of the control risks process, an updated risk register generally includes some or all of the following EXCEPT:
Responda
  • The WBS
  • Actual outcomes of the projects risks
  • Outcomes of risk reassessments

Questão 167

Questão
To be successful, an organization should be committed to addressing risk management:
Responda
  • Proactively throughout the entire project
  • As soon as time & cost estimates are ready
  • As early as possible in the execution phase

Questão 168

Questão
The primary output of the identify risks process is the:
Responda
  • Risk register
  • Risk mitigation plan
  • List of the corrective actions

Questão 169

Questão
The mitigate risk response strategy:
Responda
  • Reduces the probability of occurrence or impact of a threat
  • Seeks to make sure the risk negative response happens
  • Seeks to eliminate the threat or protect the project from its impact

Questão 170

Questão
The probability and impact risk assessment thresholds:
Responda
  • Show quantitative risk results for the project
  • Are determined by the # of threats
  • Are unique for each organization

Questão 171

Questão
Sensitivity analysis helps determine which risks have the most potential impact on the project. How is that info shown?
Responda
  • Probability and impact matrix
  • Cost/probability chart
  • Tornado diagram

Questão 172

Questão
Expected monetary value (EMV) analysis has all of the following characteristics except:
Responda
  • It is a statistical concept that calculates the average outcome when the future includes scenarios that may or may not happen.
  • The EMV of opportunities are generally expressed as positive values, whereas those of threats are expressed as negative values.
  • EMV analysis cannot be used effectively in decision tree analysis unless a risk-averse assumption is made.

Questão 173

Questão
An output of perform qualitative risk analysis is:
Responda
  • Project documents updates
  • Risk management plan
  • Risk register
  • Meetings

Questão 174

Questão
Identify stakeholders is a part of which process group?
Responda
  • Initiation
  • Execution
  • Planning

Questão 175

Questão
You are evaluating various bids to determine which vendor you will purchase your building materials from. What process are you in?
Responda
  • Plan procurement management
  • Conduct procurements
  • Planning

Questão 176

Questão
You are a Project Manager constructing a large building to store your company’s work vehicles. You know exactly what you want built. It will only take 3 weeks to build. In this case, what type of contract would you want to use?
Responda
  • Hybrid
  • Time & material
  • Fixed price
  • Cost reimbursable

Questão 177

Questão
You a working on a project that will augment the staff in grade schools by providing temporary substitute teachers for the school district. To account for fixed overhead costs and hourly wages, the best contract type would be:
Responda
  • Fixed cost
  • Cost reimbursable
  • Time & material

Questão 178

Questão
The stakeholder register is an output of which process?
Responda
  • Stakeholder analysis
  • Plan stakeholder management
  • Manage stakeholder engagement
  • Identify stakeholders

Questão 179

Questão
In the Power/Interest stakeholder grid, which quadrant should you spend the most time on and provide the most attention?
Responda
  • Low p low I
  • High p low I
  • High p high I

Questão 180

Questão
The stake holder register should contain at least the following:
Responda
  • Identification information, risk analysis, assessment matrix
  • Stakeholder engagement data flow diagram, risk analysis, assessment matrix
  • Identification information, assessment information, stakeholder classification
  • Stakeholder management plan, stakeholder classification, risk analysis

Questão 181

Questão
Lessons learned:
Responda
  • Collects project performance data
  • Shows how events were addressed or should be addressed in the future with the purpose of improving future performance
  • An event to plan organize and direct work

Questão 182

Questão
If a contract has an incentive fee, financial incentives are dependent on:
Responda
  • Inflation
  • Legal penalties
  • Agreed upon metrics

Questão 183

Questão
During closing, you should hand off the project to:
Responda
  • PMO
  • Exec Sponsor
  • End User
  • The group that will own or be responsible on a daily basis

Questão 184

Questão
In the agile framework, individuals and interactions are valued more than:
Responda
  • Deliverables
  • Methodology
  • Processes & tools

Questão 185

Questão
You are a Project Manager for Apple and your latest project is developing the new iPhone 6Z. You need to build a solar battery that will enable the phone to go without charging for 2 weeks at a time. Critical to this project is the new chip design that requires a special assembly line to produce. This new assembly line is not a core competency of Apple. You need to decide what type of contract will work best to acquire the new chip. What procurement process are you in?
Responda
  • Conduct procurements
  • Identify stakeholders
  • Plan procurement management

Questão 186

Questão
Which type of contract is the riskiest for a contractor?
Responda
  • Cost plus fee
  • Time & materials
  • Firm fixed price

Questão 187

Questão
The output of the conduct procurements process is:
Responda
  • Procurement management plan
  • Closed procurements
  • Signed contract agreement
  • Work performance info

Questão 188

Questão
Your project Sponsor is actively engaged in your project and understands the benefits and impacts. How would you classify the Sponsor as a stakeholder?
Responda
  • Resistant
  • Expert
  • Leading

Questão 189

Questão
During the Closing process, you should do all of the following except
Responda
  • Conduct lessons learned
  • Gain approval to close
  • Classify stakeholders

Questão 190

Questão
Enterprise environ factors are:
Responda
  • Outputs
  • Project management systems
  • Conditions that influence or constrain

Questão 191

Questão
Who represents the customer in SCRUM?
Responda
  • PM
  • PT
  • Product Owner
  • Scrum master

Questão 192

Questão
Procurement is:
Responda
  • Acquiring goods & services
  • Reviewing contracts
  • Obtaining the resources you need for the project

Questão 193

Questão
The best measure for progress in agile is:
Responda
  • Design
  • Working software
  • Technical excellence

Questão 194

Questão
Cost plus fixed fee contracts (CPFF) have all of the following characteristics except:
Responda
  • Seller receives a fixed-fee payment calculated as the initial estimated project cost.
  • The fee is paid only for completed work and does not change due to seller performance unless the project scope changes.

Questão 195

Questão
You are involved in the process of communicating and working with stakeholders to meet their needs/expectations, address issues as they occur, and foster appropriate stakeholder engagement in project activities throughout the project life cycle. This is known as:
Responda
  • Plan stakeholder management
  • Communicate with stakeholders
  • Control stakeholders
  • Manage stakeholder engagement

Questão 196

Questão
Manage Stakeholder Engagement involves all of the following activities except:
Responda
  • Managing stakeholder expectations through negotiation and communication
  • Avoiding potential concern that have not yet become issues
  • Anticipating future problems
  • Clarifying & resolving identified issues

Questão 197

Questão
Control Stakeholder Engagement tools and techniques include all of the following except:
Responda
  • Behavior modification analysis
  • Expert judgement
  • Meetings
  • Information management systems

Questão 198

Questão
Outputs from the Close Procurements Process generally include all of the following except:
Responda
  • Deliverable acceptance
  • Closed procurements
  • Lessons learned
  • The contractors working proposal

Semelhante

Português - 3 - Ortografia e acentuação
glenerdourado
Evolução Biológica: os mecanismos. A formação de novas espécies I
Bruno Fernandes3682
Curiosidades do Mundo: Fatos da História
Alessandra S.
Doenças Cardiovasculares
marianamota99
Leis de Newton
Guilherme Hayashida
História da informática
Renato Costa
Mapa Mental - Como Criar um Mapa Mental
Adelaide Silva A
FCE Opposites Practice
titaleoni
Liderança e Gestão de Equipes
Pierre Curi
CLIMA GEOGRAFIA
Alice Sousa
RESUMO DE LITERATURA (PARTE 1)
Ana Loss