Project Mngt Chapter 5

Descrição

Project Mngt Chapter 5 Test Questions
damimgd2u
Quiz por damimgd2u, atualizado more than 1 year ago
damimgd2u
Criado por damimgd2u mais de 8 anos atrás
11974
0

Resumo de Recurso

Questão 1

Questão
Scope management is the function controlling a project in terms of its goals and objectives during the execution phase.
Responda
  • T/F
  • Answer: FALSE

Questão 2

Questão
The statement of work is a detailed narrative description of the work required for a project.
Responda
  • T/F
  • Answer: TRUE

Questão 3

Questão
A comprehensive statement of work includes an estimate of time and costs, resource requirements, and the scope of the work to be performed.
Responda
  • T/F
  • Answer: TRUE

Questão 4

Questão
Until a project has gone through work breakdown structure, it is impossible to determine the relationships among the constituent activities.
Responda
  • T/F
  • Answer: TRUE

Questão 5

Questão
The scope baseline is a document that provides a summary description of each reporting relationship along with a schedule for meetings and reports.
Responda
  • T/F
  • Answer: FALSE

Questão 6

Questão
A work package may be composed of one or more subdeliverables.
Responda
  • T/F
  • Answer: FALSE

Questão 7

Questão
A work package may consist of more than one milestone.
Responda
  • T/F
  • Answer: TRUE

Questão 8

Questão
Work authorization functions as the formal "It's OK to begin work," on the project.
Responda
  • T/F
  • Answer: TRUE

Questão 9

Questão
The terms lump-sum contract and turnkey contract are interchangeable.
Responda
  • T/F
  • Answer: TRUE

Questão 10

Questão
A lump-sum contract requires the customer to pay for the full delivered price of the project before any work is done.
Responda
  • T/F
  • Answer: FALSE

Questão 11

Questão
Which statement about scope management is best? A) Scope management must take place during the conceptual development, full definition, execution, and termination phases. B) Project goals don't matter in scope management as long as the budget is not exceeded. C) Scope management is accomplished in a single step by any one project team member. D) Scope management can begin once a project hits operational level.
Responda
  • M/C
  • Answer: A

Questão 12

Questão
The Scope Management chapter begins and ends with the quote, "It's a dream until you write it down. Then it's…" A) "… etched in stone." B) "… a scope statement." C) "… a documented dream." D) "… a goal."
Responda
  • M/C
  • Answer: D

Questão 13

Questão
Scope management for a project begins with: A) a work package. B) an organization breakdown structure. C) a statement of goals. D) a configuration statement.
Responda
  • M/C
  • Answer: C

Questão 14

Questão
Restrictions that affect project development are: A) problems. B) constraints. C) stop-limits. D) limitations.
Responda
  • M/C
  • Answer: B

Questão 15

Questão
The cat-skinning project management team considers the many ways to accomplish their objective before settling on one technique as part of their: A) information gathering step. B) need statement step. C) project objectives step. D) alternative analysis step.
Responda
  • M/C
  • Answer: D

Questão 16

Questão
There were conceivably an infinite number of courses he could take during his final semester, but since he worked 8-5, Jake needed to take night classes. He also needed to ensure that the class was offered at the Edmond campus rather than Midwest City, so he could get home in time for his favorite programs. This whittled down the list of possibilities to Systems Analysis Design and Differential Equations. "Neither of these courses is very attractive. I may have to rethink my priorities," Jake wondered aloud. "The work schedule and wrestling schedule are significant: A) scope statements." B) alternatives." C) constraints." D) goals."
Responda
  • M/C
  • Answer: C

Questão 17

Questão
Conceptual development for a project concludes with: A) project objectives. B) alternative analysis. C) project delivery. D) team dissolution.
Responda
  • M/C
  • Answer: A

Questão 18

Questão
One consequence of conceptual development that proceeds with a problem that is poorly understood is: A) problem restatement. B) cost overruns. C) problem clarification. D) task confusion.
Responda
  • M/C
  • Answer: B

Questão 19

Questão
Which statement about conceptual development is best? A) A project goal of "significantly increase computer performance" is better than "improve processing speed 20%" because the team may exceed 20%. B) It is vital that a best approach to solving a problem be locked in as soon as possible to save analysis time downstream. C) Conceptual development begins with the process of reducing the project's overall complexity to a more basic level. D) Project goals should be optimistic to the point of excess.
Responda
  • M/C
  • Answer: C

Questão 20

Questão
The statement of work should contain: A) information on the key objectives for the project. B) a brief and general description of the work to be performed. C) expected project outcomes. D) All of these are elements of a statement of work.
Responda
  • M/C
  • Answer: D

Questão 21

Questão
A statement of work identifies: A) a need. B) a project organization. C) members of the project team. D) alternatives.
Responda
  • M/C
  • Answer: A

Questão 22

Questão
Which of these is NOT a typical element of a statement of work? A) introduction and background B) a list of activities needed to complete the project C) technical description of the project D) timeline and milestones
Responda
  • M/C
  • Answer: B

Questão 23

Questão
The description and scope section of a statement of work would contain statements regarding: A) environmental risks. B) termination of project information. C) expected benefits. D) major milestones.
Responda
  • M/C
  • Answer: C

Questão 24

Questão
Expected commitments from other departments in support of the project would most likely be detailed in the: A) approach section of the SOW. B) risks and concerns section of the SOW. C) acceptance criteria section of the SOW. D) resource requirements section of the SOW.
Responda
  • M/C
  • Answer: D

Questão 25

Questão
A testing plan would be outlined in which section of a statement of work? A) acceptance criteria B) risks and concerns C) description and scope D) approach
Responda
  • M/C
  • Answer: A

Questão 26

Questão
Any measurable, tangible, verifiable outcome, result, or item that must be produced to complete a project or part of a project is a: A) product. B) deliverable. C) tangible. D) work product.
Responda
  • M/C
  • Answer: B

Questão 27

Questão
Which of the following is NOT a project goal criteria? A) cost B) schedule C) team membership D) review and approval gates
Responda
  • M/C
  • Answer: C

Questão 28

Questão
The organizational structure for the project team, including policies and procedures, is the: A) work breakdown structure. B) rules statement. C) scope statement. D) management plan.
Responda
  • M/C
  • Answer: D

Questão 29

Questão
Which of these scope statement steps creates the all-important bureaucracy for a project? A) the management plan B) the work breakdown structure C) the scope baseline D) the project goal criteria
Responda
  • M/C
  • Answer: A

Questão 30

Questão
The mountaineers all agreed that their quest to build a bridge between the two peaks of Mount Kilimanjaro was a noble one, but they had no idea how long it would take to complete until they finished their: A) project goal criteria. B) work breakdown structure. C) scope baseline. D) management plan.
Responda
  • M/C
  • Answer: B

Questão 31

Questão
The new Magic Pan coming soon to your area usually serves 20,000 customers in the first year of operation. Construction plans include site selection, foundation, framing, finishing, egg-laying, and chicken acquisition. The scope statement step that determines relationships among these steps, e.g. does the chicken acquisition come before the egg laying, etc., is the: A) project goal criteria. B) management plan. C) work breakdown structure. D) scope baseline
Responda
  • M/C
  • Answer: C

Questão 32

Questão
Budget and schedule information for each activity in a project is contained in the: A) project goal criteria. B) management plan. C) work breakdown structure. D) scope baseline.
Responda
  • M/C
  • Answer: D

Questão 33

Questão
The final step in the process of systematically laying out all pre-work information is the creation of the: A) scope baseline. B) work breakdown structure. C) management plan. D) project goal criteria.
Responda
  • M/C
  • Answer: A

Questão 34

Questão
The PMBoK definition stating, "a process that sets a project's scope by breaking down its overall mission into a cohesive set of synchronous, increasingly specific tasks," is for the: A) project plan. B) work breakdown structure. C) deliverable statement. D) scope expansion.
Responda
  • M/C
  • Answer: B

Questão 35

Questão
What are work breakdown structure elements that must be completed to conclude the project deliverables? A) activities B) tasks C) work packages D) milestones
Responda
  • M/C
  • Answer: C

Questão 36

Questão
The lowest level in work breakdown structure contains the: A) atoms. B) activities. C) finite elements. D) work packages.
Responda
  • M/C
  • Answer: D

Questão 37

Questão
The highest level of work breakdown structure is the: A) project. B) deliverable. C) subdeliverable. D) work package.
Responda
  • M/C
  • Answer: A

Questão 38

Questão
The second level in work breakdown structure contains the: A) projects. B) deliverables. C) subdeliverables. D) work packages.
Responda
  • M/C
  • Answer: B

Questão 39

Questão
In order to allocate costs more precisely, a company will assign: A) bar codes to each activity. B) activity codes to each subdeliverable. C) WBS codes to each activity. D) level 4 codes to each package element.
Responda
  • M/C
  • Answer: C

Questão 40

Questão
Which of these statements about subdeliverables is best? A) Subdeliverables have durations of their own. B) Subdeliverables consume resources. C) Subdeliverables have direct assignable costs. D) Subdeliverables summarize the outcomes of work packages.
Responda
  • M/C
  • Answer: D

Questão 41

Questão
The costs attached to subdeliverables: A) are the summary of the work packages that support it. B) are called phantom costs. C) should be subtracted directly from deliverable costs. D) are not recoverable unless explicitly stated in the work breakdown structure.
Responda
  • M/C
  • Answer: A

Questão 42

Questão
When a supporting document functions as a project control device throughout the project's development, it is not prepared in advance: A) due to time constraints. B) as it is a dynamic document. C) since micromanaging can occur. D) because control devices are left to project completion.
Responda
  • M/C
  • Answer: B

Questão 43

Questão
When work is organized into cost control accounts: A) the work no longer needs to be tracked by the project manager. B) the subdeliverables become cost centers instead of profit centers for the project. C) these are assigned to the units performing project activities. D) these budgets can then be assigned back to the project manager's department.
Responda
  • M/C
  • Answer: C

Questão 44

Questão
Organizational breakdown structure (OBS) allows companies to: A) assign the duties of tracking costs to the customer's accounting function. B) circumvent the onerous task of work breakdown structure. C) issue a preliminary TPS report. D) define the work to be accomplished.
Responda
  • M/C
  • Answer: D

Questão 45

Questão
A project manager can identify personnel who will be directly responsible for each task in the project's development by using a(n): A) responsibility assignment matrix. B) milestone designation chart. C) Merrill report. D) work package report.
Responda
  • M/C
  • Answer: A

Questão 46

Questão
Project team members can identify who should be notified of task completion status by checking the: A) control account. B) linear responsibility chart. C) statement of work. D) monthly joint review report.
Responda
  • M/C
  • Answer: B

Questão 47

Questão
The step that reflects the formal "go ahead" given to the project to commence once the scope definition, planning documents, and other contractual documents have been prepared and approved is the: A) go ahead. B) send off. C) work authorization. D) work release.
Responda
  • M/C
  • Answer: C

Questão 48

Questão
In the case of projects developed for external clients, work authorization typically addresses: A) budget linkage. B) audit trail establishment. C) resource requirements. D) contractual obligations.
Responda
  • M/C
  • Answer: D

Questão 49

Questão
All projects are promised in terms of the specific functionality or performance criteria they will meet. The key feature of the contractual documentation that specifies this functionality or criteria is the: A) contractual requirements. B) valid consideration. C) contracted terms. D) contractual performance.
Responda
  • M/C
  • Answer: A

Questão 50

Questão
The exchange that is specified by the contractual documentation documents is: A) the terms. B) valid consideration. C) reciprocity. D) fair and unencumbered.
Responda
  • M/C
  • Answer: B

Questão 51

Questão
The section of the contractual documentation that identifies what are the excusable delays, allowable costs, and criteria for inspection is called the: A) bylaws. B) amendments. C) contracted terms. D) dissolution factors.
Responda
  • M/C
  • Answer: C

Questão 52

Questão
A project management firm that promises to do everything for a major project and hand over a fully functional, ready-to-use deliverable is performing under a(n): A) umbrella contract. B) all-inclusive contract. C) cost-plus contract. D) turnkey contract.
Responda
  • M/C
  • Answer: D

Questão 53

Questão
Which pair of statements is best? A) Cost-plus contracts are prone to budget overruns while turnkey contracts are typically underbid by the contractor. B) Cost-plus contracts are prone to a budget surplus while turnkey contracts are typically underbid by the contractor. C) Cost-plus contracts are prone to a budget surplus while turnkey contracts are typically overbid by the contractor. D) Cost-plus contracts are prone to budget overruns while turnkey contracts are typically overbid by the contractor.
Responda
  • M/C
  • Answer: D

Questão 54

Questão
Your professor moonlights to make ends meet during the summer months and has a knack for painting houses. You agree to pay $500 over whatever the materials and equipment rental cost for the job and delight in sipping lemonade in the shade watching your poor professor perform under a(n): A) cost-plus contract. B) lump-sum contract. C) time and material contract. D) fixed wage contract.
Responda
  • M/C
  • Answer: A

Questão 55

Questão
The reporting frequency, report recipients, and content required during project execution is laid out by: A) the organizational breakdown structure. B) scope reporting. C) the information system architecture. D) a need-to-know basis.
Responda
  • M/C
  • Answer: A

Questão 56

Questão
Updates on how the project is performing against milestones can be accomplished by issuing a report containing: A) S-curves. B) schedule status. C) earned value. D) technical performance.
Responda
  • M/C
  • Answer: B

Questão 57

Questão
An earned value report shows: A) how much money has actually been spent so far on the project. B) slippages in performance measures for the work product. C) the budgeted value of work performed. D) slippages in time against planned measures.
Responda
  • M/C
  • Answer: C

Questão 58

Questão
An S-curve report does NOT contain information on: A) time. B) cost. C) budget. D) quality.
Responda
  • M/C
  • Answer: D

Questão 59

Questão
Procedures that monitor emerging project scope against the original baseline scope are called: A) configuration control. B) design control. C) trend monitoring. D) document control.
Responda
  • M/C
  • Answer: A

Questão 60

Questão
A young professor becomes obsessed with the latest release of Halo and completely loses sight of his research commitment to his colleagues, falling hopelessly behind schedule and consuming 80% of the department's computing budget. Addictive behavior notwithstanding, this sad tale would never have happened had: A) configuration controls been established. B) trend monitoring been regularly performed. C) design controls been appropriately deployed. D) document control been conducted assiduously.
Responda
  • M/C
  • Answer: B

Semelhante

Project Mngt Chapter 8
damimgd2u
Project Mngt Chapter 7
damimgd2u
Project Mngt Chapter 9
damimgd2u
Project Mngt Chapter 6
damimgd2u
Chapter 5 Homework
void pickle
Chapters 5-9 T/F
damimgd2u
Chapter 4 E-commerce Quiz Multiple Choice
Sergio López
E-commerce Chapter 4 TRUE/FALSE Quiz
Sergio López
Mechanics-Chapter 5-Moments
Thomas Marshall
Project Mngt Chapter 9
David Parker
Project Mngt Chapter 6
Leah Dou