Chapters 5-9 T/F

Descrição

Project Mngt Chapters 5-9 T/F
damimgd2u
Quiz por damimgd2u, atualizado more than 1 year ago
damimgd2u
Criado por damimgd2u mais de 8 anos atrás
3821
0

Resumo de Recurso

Questão 1

Questão
Scope management is the function controlling a project in terms of its goals and objectives during the execution phase.
Responda
  • T/F
  • Answer: FALSE

Questão 2

Questão
The statement of work is a detailed narrative description of the work required for a project.
Responda
  • T/F
  • Answer: TRUE

Questão 3

Questão
A comprehensive statement of work includes an estimate of time and costs, resource requirements, and the scope of the work to be performed.
Responda
  • T/F
  • Answer: TRUE

Questão 4

Questão
Until a project has gone through work breakdown structure, it is impossible to determine the relationships among the constituent activities.
Responda
  • T/F
  • Answer: TRUE

Questão 5

Questão
The scope baseline is a document that provides a summary description of each reporting relationship along with a schedule for meetings and reports.
Responda
  • T/F
  • Answer: FALSE

Questão 6

Questão
A work package may be composed of one or more subdeliverables.
Responda
  • T/F
  • Answer: FALSE

Questão 7

Questão
A work package may consist of more than one milestone.
Responda
  • T/F
  • Answer: TRUE

Questão 8

Questão
Work authorization functions as the formal "It's OK to begin work," on the project.
Responda
  • T/F
  • Answer: TRUE

Questão 9

Questão
The terms lump-sum contract and turnkey contract are interchangeable.
Responda
  • T/F
  • Answer: TRUE

Questão 10

Questão
A lump-sum contract requires the customer to pay for the full delivered price of the project before any work is done.
Responda
  • T/F
  • Answer: FALSE

Questão 11

Questão
Team building and conflict management skills are two of the most important people skills that project managers can cultivate.
Responda
  • T/F
  • Answer: TRUE

Questão 12

Questão
The first step in assembling a project team is to talk to potential team members.
Responda
  • T/F
  • Answer: FALSE

Questão 13

Questão
If preferred project team members are not available, the project manager should notify top management of the consequences.
Responda
  • T/F
  • Answer: TRUE

Questão 14

Questão
Project managers are best able to promote a sense of enthusiasm within the project team when they create an environment that is challenging, supportive, and personally rewarding.
Responda
  • T/F
  • Answer: TRUE

Questão 15

Questão
High turnover among project team members is a key element of success since new team members will bring fresh perspectives and ideas to the group.
Responda
  • T/F
  • Answer: FALSE

Questão 16

Questão
Project team productivity is at its peak during the norming phase of group development.
Responda
  • T/F
  • Answer: FALSE

Questão 17

Questão
The punctuated equilibrium model suggests that groups spend the majority of their time in stasis.
Responda
  • T/F
  • Answer: TRUE

Questão 18

Questão
Cross-functional cooperation directly influences both the actual implementation of the project and the team members' assessment that the project experience was worthwhile.
Responda
  • T/F
  • Answer: TRUE

Questão 19

Questão
In general, a superordinate goal is a replacement goal for the goals of all functional groups involved in the project.
Responda
  • T/F
  • Answer: FALSE

Questão 20

Questão
Accessibility is the perception of the project team members that they are physically located in such a way that it is easy for them to interact.
Responda
  • T/F
  • Answer: FALSE

Questão 21

Questão
The risk is highest in the earliest phase of the project life cycle.
Responda
  • T/F
  • Answer: TRUE

Questão 22

Questão
Opportunity emerges from favorable project circumstances and risk from unfavorable events.
Responda
  • T/F
  • Answer: TRUE

Questão 23

Questão
As risk decreases in the project life cycle, opportunity increases
Responda
  • T/F
  • Answer: FALSE

Questão 24

Questão
Risks can be quantified by multiplying the likelihood a failure will occur by the severity of the failure.
Responda
  • T/F
  • Answer: TRUE

Questão 25

Questão
Technical risk is the probability that the project will not perform to the required standards or produce substandard products or have excessive operating cost consumption.
Responda
  • T/F
  • Answer: TRUE

Questão 26

Questão
The probability that the investments made to fund the front-end activities will be lost due to project abandonment is financing risk.
Responda
  • T/F
  • Answer: FALSE

Questão 27

Questão
One approach to risk mitigation is simply to accept it.
Responda
  • T/F
  • Answer: TRUE

Questão 28

Questão
Risk cannot be transferred because ultimately your own project will suffer the consequences if the event occurs.
Responda
  • T/F
  • Answer: FALSE

Questão 29

Questão
Contingency reserves require a construction company to hold back some funds in an account just in case something happens that increases the overall project cost.
Responda
  • T/F
  • Answer: TRUE

Questão 30

Questão
The highest dollar value of reserves is typically task contingency.
Responda
  • T/F
  • Answer: FALSE

Questão 31

Questão
Direct costs are those clearly assigned to the aspect of the project that generated the cost.
Responda
  • T/F
  • Answer: TRUE

Questão 32

Questão
Material is an example of a cost that is recurring, variable and direct.
Responda
  • T/F
  • Answer: TRUE

Questão 33

Questão
An expedited cost is one that does not vary with respect to their usage.
Responda
  • T/F
  • Answer: FALSE

Questão 34

Questão
The term expedited cost has the same meaning as crashing cost in the project management milieu.
Responda
  • T/F
  • Answer: TRUE

Questão 35

Questão
An order of magnitude estimate is usually more accurate than a ballpark estimate.
Responda
  • T/F
  • Answer: FALSE

Questão 36

Questão
Comparative estimates are more accurate than definitive estimates when applied to the same project.
Responda
  • T/F
  • Answer: TRUE

Questão 37

Questão
A learning rate of 90% means that for every doubling of output, the time required by the activity falls by 10%.
Responda
  • T/F
  • Answer: TRUE

Questão 38

Questão
Function point analysis is a system for estimating the size of software projects based on the number of lines of code a typical programmer can write in a day.
Responda
  • T/F
  • Answer: FALSE

Questão 39

Questão
A common reason for cost overruns in a project is a low initial estimate of project cost.
Responda
  • T/F
  • Answer: TRUE

Questão 40

Questão
There is a tendency for different departments or functions to compete for scarce resources in a zero-sum game when bottom-up budgeting is used to develop a project budget.
Responda
  • T/F
  • Answer: FALSE

Questão 41

Questão
Preceding activities are those that must occur before others can be done.
Responda
  • T/F
  • Answer: TRUE

Questão 42

Questão
A backward pass is performed when it is necessary to undo some work that has been performed in order to complete it properly.
Responda
  • T/F
  • Answer: FALSE

Questão 43

Questão
A merge activity has two or more immediate predecessors.
Responda
  • T/F
  • Answer: TRUE

Questão 44

Questão
Float is always measured in exactly the same way as slack.
Responda
  • T/F
  • Answer: TRUE

Questão 45

Questão
The PERT technique assumes that durations are more deterministic.
Responda
  • T/F
  • Answer: FALSE

Questão 46

Questão
Burst activities are those with two or more successor activities.
Responda
  • T/F
  • Answer: FALSE

Questão 47

Questão
You must know the mean of an activity in order to determine its standard deviation.
Responda
  • T/F
  • Answer: FALSE

Questão 48

Questão
In assigning a value for the most pessimistic (b) duration, the project manager should estimate the duration of the activity to have a 99% likelihood that it will take b or less amount of time.
Responda
  • T/F
  • Answer: TRUE

Questão 49

Questão
The late start time should be calculated using a forward pass through the network.
Responda
  • T/F
  • Answer: FALSE

Questão 50

Questão
Negative float exists when a project's critical path has been completed more quickly than anticipated.
Responda
  • T/F
  • Answer: TRUE

Semelhante

Project Mngt Chapter 8
damimgd2u
Project Mngt Chapter 7
damimgd2u
Project Mngt Chapter 9
damimgd2u
Project Mngt Chapter 5
damimgd2u
Project Mngt Chapter 6
damimgd2u
Project Mngt Chapter 9
David Parker
Project Mngt Chapter 6
Leah Dou
Project Mngt Chapter 5
Leah Dou
Project Mngt Chapter 9
Leah Dou
Project Mngt Chapter 7
Leah Dou
Project Mngt Chapter 8
Muhammed Aras