Project Mngt Chapter 5

Description

Project Mngt Chapter 5 Test Questions
Leah Dou
Quiz by Leah Dou, updated more than 1 year ago More Less
damimgd2u
Created by damimgd2u over 8 years ago
Leah Dou
Copied by Leah Dou almost 8 years ago
71
1

Resource summary

Question 1

Question
Scope management is the function controlling a project in terms of its goals and objectives during the execution phase.
Answer
  • T/F
  • Answer: FALSE

Question 2

Question
The statement of work is a detailed narrative description of the work required for a project.
Answer
  • T/F
  • Answer: TRUE

Question 3

Question
A comprehensive statement of work includes an estimate of time and costs, resource requirements, and the scope of the work to be performed.
Answer
  • T/F
  • Answer: TRUE

Question 4

Question
Until a project has gone through work breakdown structure, it is impossible to determine the relationships among the constituent activities.
Answer
  • T/F
  • Answer: TRUE

Question 5

Question
The scope baseline is a document that provides a summary description of each reporting relationship along with a schedule for meetings and reports.
Answer
  • T/F
  • Answer: FALSE

Question 6

Question
A work package may be composed of one or more subdeliverables.
Answer
  • T/F
  • Answer: FALSE

Question 7

Question
A work package may consist of more than one milestone.
Answer
  • T/F
  • Answer: TRUE

Question 8

Question
Work authorization functions as the formal "It's OK to begin work," on the project.
Answer
  • T/F
  • Answer: TRUE

Question 9

Question
The terms lump-sum contract and turnkey contract are interchangeable.
Answer
  • T/F
  • Answer: TRUE

Question 10

Question
A lump-sum contract requires the customer to pay for the full delivered price of the project before any work is done.
Answer
  • T/F
  • Answer: FALSE

Question 11

Question
Which statement about scope management is best? A) Scope management must take place during the conceptual development, full definition, execution, and termination phases. B) Project goals don't matter in scope management as long as the budget is not exceeded. C) Scope management is accomplished in a single step by any one project team member. D) Scope management can begin once a project hits operational level.
Answer
  • M/C
  • Answer: A

Question 12

Question
The Scope Management chapter begins and ends with the quote, "It's a dream until you write it down. Then it's…" A) "… etched in stone." B) "… a scope statement." C) "… a documented dream." D) "… a goal."
Answer
  • M/C
  • Answer: D

Question 13

Question
Scope management for a project begins with: A) a work package. B) an organization breakdown structure. C) a statement of goals. D) a configuration statement.
Answer
  • M/C
  • Answer: C

Question 14

Question
Restrictions that affect project development are: A) problems. B) constraints. C) stop-limits. D) limitations.
Answer
  • M/C
  • Answer: B

Question 15

Question
The cat-skinning project management team considers the many ways to accomplish their objective before settling on one technique as part of their: A) information gathering step. B) need statement step. C) project objectives step. D) alternative analysis step.
Answer
  • M/C
  • Answer: D

Question 16

Question
There were conceivably an infinite number of courses he could take during his final semester, but since he worked 8-5, Jake needed to take night classes. He also needed to ensure that the class was offered at the Edmond campus rather than Midwest City, so he could get home in time for his favorite programs. This whittled down the list of possibilities to Systems Analysis Design and Differential Equations. "Neither of these courses is very attractive. I may have to rethink my priorities," Jake wondered aloud. "The work schedule and wrestling schedule are significant: A) scope statements." B) alternatives." C) constraints." D) goals."
Answer
  • M/C
  • Answer: C

Question 17

Question
Conceptual development for a project concludes with: A) project objectives. B) alternative analysis. C) project delivery. D) team dissolution.
Answer
  • M/C
  • Answer: A

Question 18

Question
One consequence of conceptual development that proceeds with a problem that is poorly understood is: A) problem restatement. B) cost overruns. C) problem clarification. D) task confusion.
Answer
  • M/C
  • Answer: B

Question 19

Question
Which statement about conceptual development is best? A) A project goal of "significantly increase computer performance" is better than "improve processing speed 20%" because the team may exceed 20%. B) It is vital that a best approach to solving a problem be locked in as soon as possible to save analysis time downstream. C) Conceptual development begins with the process of reducing the project's overall complexity to a more basic level. D) Project goals should be optimistic to the point of excess.
Answer
  • M/C
  • Answer: C

Question 20

Question
The statement of work should contain: A) information on the key objectives for the project. B) a brief and general description of the work to be performed. C) expected project outcomes. D) All of these are elements of a statement of work.
Answer
  • M/C
  • Answer: D

Question 21

Question
A statement of work identifies: A) a need. B) a project organization. C) members of the project team. D) alternatives.
Answer
  • M/C
  • Answer: A

Question 22

Question
Which of these is NOT a typical element of a statement of work? A) introduction and background B) a list of activities needed to complete the project C) technical description of the project D) timeline and milestones
Answer
  • M/C
  • Answer: B

Question 23

Question
The description and scope section of a statement of work would contain statements regarding: A) environmental risks. B) termination of project information. C) expected benefits. D) major milestones.
Answer
  • M/C
  • Answer: C

Question 24

Question
Expected commitments from other departments in support of the project would most likely be detailed in the: A) approach section of the SOW. B) risks and concerns section of the SOW. C) acceptance criteria section of the SOW. D) resource requirements section of the SOW.
Answer
  • M/C
  • Answer: D

Question 25

Question
A testing plan would be outlined in which section of a statement of work? A) acceptance criteria B) risks and concerns C) description and scope D) approach
Answer
  • M/C
  • Answer: A

Question 26

Question
Any measurable, tangible, verifiable outcome, result, or item that must be produced to complete a project or part of a project is a: A) product. B) deliverable. C) tangible. D) work product.
Answer
  • M/C
  • Answer: B

Question 27

Question
Which of the following is NOT a project goal criteria? A) cost B) schedule C) team membership D) review and approval gates
Answer
  • M/C
  • Answer: C

Question 28

Question
The organizational structure for the project team, including policies and procedures, is the: A) work breakdown structure. B) rules statement. C) scope statement. D) management plan.
Answer
  • M/C
  • Answer: D

Question 29

Question
Which of these scope statement steps creates the all-important bureaucracy for a project? A) the management plan B) the work breakdown structure C) the scope baseline D) the project goal criteria
Answer
  • M/C
  • Answer: A

Question 30

Question
The mountaineers all agreed that their quest to build a bridge between the two peaks of Mount Kilimanjaro was a noble one, but they had no idea how long it would take to complete until they finished their: A) project goal criteria. B) work breakdown structure. C) scope baseline. D) management plan.
Answer
  • M/C
  • Answer: B

Question 31

Question
The new Magic Pan coming soon to your area usually serves 20,000 customers in the first year of operation. Construction plans include site selection, foundation, framing, finishing, egg-laying, and chicken acquisition. The scope statement step that determines relationships among these steps, e.g. does the chicken acquisition come before the egg laying, etc., is the: A) project goal criteria. B) management plan. C) work breakdown structure. D) scope baseline
Answer
  • M/C
  • Answer: C

Question 32

Question
Budget and schedule information for each activity in a project is contained in the: A) project goal criteria. B) management plan. C) work breakdown structure. D) scope baseline.
Answer
  • M/C
  • Answer: D

Question 33

Question
The final step in the process of systematically laying out all pre-work information is the creation of the: A) scope baseline. B) work breakdown structure. C) management plan. D) project goal criteria.
Answer
  • M/C
  • Answer: A

Question 34

Question
The PMBoK definition stating, "a process that sets a project's scope by breaking down its overall mission into a cohesive set of synchronous, increasingly specific tasks," is for the: A) project plan. B) work breakdown structure. C) deliverable statement. D) scope expansion.
Answer
  • M/C
  • Answer: B

Question 35

Question
What are work breakdown structure elements that must be completed to conclude the project deliverables? A) activities B) tasks C) work packages D) milestones
Answer
  • M/C
  • Answer: C

Question 36

Question
The lowest level in work breakdown structure contains the: A) atoms. B) activities. C) finite elements. D) work packages.
Answer
  • M/C
  • Answer: D

Question 37

Question
The highest level of work breakdown structure is the: A) project. B) deliverable. C) subdeliverable. D) work package.
Answer
  • M/C
  • Answer: A

Question 38

Question
The second level in work breakdown structure contains the: A) projects. B) deliverables. C) subdeliverables. D) work packages.
Answer
  • M/C
  • Answer: B

Question 39

Question
In order to allocate costs more precisely, a company will assign: A) bar codes to each activity. B) activity codes to each subdeliverable. C) WBS codes to each activity. D) level 4 codes to each package element.
Answer
  • M/C
  • Answer: C

Question 40

Question
Which of these statements about subdeliverables is best? A) Subdeliverables have durations of their own. B) Subdeliverables consume resources. C) Subdeliverables have direct assignable costs. D) Subdeliverables summarize the outcomes of work packages.
Answer
  • M/C
  • Answer: D

Question 41

Question
The costs attached to subdeliverables: A) are the summary of the work packages that support it. B) are called phantom costs. C) should be subtracted directly from deliverable costs. D) are not recoverable unless explicitly stated in the work breakdown structure.
Answer
  • M/C
  • Answer: A

Question 42

Question
When a supporting document functions as a project control device throughout the project's development, it is not prepared in advance: A) due to time constraints. B) as it is a dynamic document. C) since micromanaging can occur. D) because control devices are left to project completion.
Answer
  • M/C
  • Answer: B

Question 43

Question
When work is organized into cost control accounts: A) the work no longer needs to be tracked by the project manager. B) the subdeliverables become cost centers instead of profit centers for the project. C) these are assigned to the units performing project activities. D) these budgets can then be assigned back to the project manager's department.
Answer
  • M/C
  • Answer: C

Question 44

Question
Organizational breakdown structure (OBS) allows companies to: A) assign the duties of tracking costs to the customer's accounting function. B) circumvent the onerous task of work breakdown structure. C) issue a preliminary TPS report. D) define the work to be accomplished.
Answer
  • M/C
  • Answer: D

Question 45

Question
A project manager can identify personnel who will be directly responsible for each task in the project's development by using a(n): A) responsibility assignment matrix. B) milestone designation chart. C) Merrill report. D) work package report.
Answer
  • M/C
  • Answer: A

Question 46

Question
Project team members can identify who should be notified of task completion status by checking the: A) control account. B) linear responsibility chart. C) statement of work. D) monthly joint review report.
Answer
  • M/C
  • Answer: B

Question 47

Question
The step that reflects the formal "go ahead" given to the project to commence once the scope definition, planning documents, and other contractual documents have been prepared and approved is the: A) go ahead. B) send off. C) work authorization. D) work release.
Answer
  • M/C
  • Answer: C

Question 48

Question
In the case of projects developed for external clients, work authorization typically addresses: A) budget linkage. B) audit trail establishment. C) resource requirements. D) contractual obligations.
Answer
  • M/C
  • Answer: D

Question 49

Question
All projects are promised in terms of the specific functionality or performance criteria they will meet. The key feature of the contractual documentation that specifies this functionality or criteria is the: A) contractual requirements. B) valid consideration. C) contracted terms. D) contractual performance.
Answer
  • M/C
  • Answer: A

Question 50

Question
The exchange that is specified by the contractual documentation documents is: A) the terms. B) valid consideration. C) reciprocity. D) fair and unencumbered.
Answer
  • M/C
  • Answer: B

Question 51

Question
The section of the contractual documentation that identifies what are the excusable delays, allowable costs, and criteria for inspection is called the: A) bylaws. B) amendments. C) contracted terms. D) dissolution factors.
Answer
  • M/C
  • Answer: C

Question 52

Question
A project management firm that promises to do everything for a major project and hand over a fully functional, ready-to-use deliverable is performing under a(n): A) umbrella contract. B) all-inclusive contract. C) cost-plus contract. D) turnkey contract.
Answer
  • M/C
  • Answer: D

Question 53

Question
Which pair of statements is best? A) Cost-plus contracts are prone to budget overruns while turnkey contracts are typically underbid by the contractor. B) Cost-plus contracts are prone to a budget surplus while turnkey contracts are typically underbid by the contractor. C) Cost-plus contracts are prone to a budget surplus while turnkey contracts are typically overbid by the contractor. D) Cost-plus contracts are prone to budget overruns while turnkey contracts are typically overbid by the contractor.
Answer
  • M/C
  • Answer: D

Question 54

Question
Your professor moonlights to make ends meet during the summer months and has a knack for painting houses. You agree to pay $500 over whatever the materials and equipment rental cost for the job and delight in sipping lemonade in the shade watching your poor professor perform under a(n): A) cost-plus contract. B) lump-sum contract. C) time and material contract. D) fixed wage contract.
Answer
  • M/C
  • Answer: A

Question 55

Question
The reporting frequency, report recipients, and content required during project execution is laid out by: A) the organizational breakdown structure. B) scope reporting. C) the information system architecture. D) a need-to-know basis.
Answer
  • M/C
  • Answer: A

Question 56

Question
Updates on how the project is performing against milestones can be accomplished by issuing a report containing: A) S-curves. B) schedule status. C) earned value. D) technical performance.
Answer
  • M/C
  • Answer: B

Question 57

Question
An earned value report shows: A) how much money has actually been spent so far on the project. B) slippages in performance measures for the work product. C) the budgeted value of work performed. D) slippages in time against planned measures.
Answer
  • M/C
  • Answer: C

Question 58

Question
An S-curve report does NOT contain information on: A) time. B) cost. C) budget. D) quality.
Answer
  • M/C
  • Answer: D

Question 59

Question
Procedures that monitor emerging project scope against the original baseline scope are called: A) configuration control. B) design control. C) trend monitoring. D) document control.
Answer
  • M/C
  • Answer: A

Question 60

Question
A young professor becomes obsessed with the latest release of Halo and completely loses sight of his research commitment to his colleagues, falling hopelessly behind schedule and consuming 80% of the department's computing budget. Addictive behavior notwithstanding, this sad tale would never have happened had: A) configuration controls been established. B) trend monitoring been regularly performed. C) design controls been appropriately deployed. D) document control been conducted assiduously.
Answer
  • M/C
  • Answer: B
Show full summary Hide full summary

Similar

Expertise in Project Management
tonesha_g
PMP® Pre-Test by Coursefountain.com
Team Coursefountain
Ch1 - The nature of IT Projects
mauricio5509
Introduction notes on SCRUM Project management framework.
Wesley Thomson
Project Management: Week 1
Sharon Ott
Summary of Definitions/Key Terms for the PMP Exam
Andrea Leyden
PMP Prep quiz
Andrea Leyden
06 PROJECT TIME MANAGEMENT
miguelabascal
Project Scope Management Process
neeshar
Project Management Integration
craigmag
PMP Executing, Monitoring and Controlling Processes
myrdenafrancis