You are the Project Manager of the XYZ project. You want to find the planned expenses for next month. Which document do you need to refer to?
Responda
Cost Management Plan
Cost Baseline
Cost Control Plan
Cost Variance report
Questão 3
Questão
You are working on the project of painting of your house. You identify a dependency that the painting of roof should begin only after two days of completion of painting of walls. This is an example of :
Responda
Lag
Lead
Slack
Float
Questão 4
Questão
Control Procurements is a process in the Project Procurement Management Knowledge area.
Responda
True
False
Questão 5
Questão
Which of the following theory was suggested by Deming?
Responda
Apply continuous small improvements to reduce costs and ensure consistency.
Marginal Analysis
Expectancy theory - people expect to be rewarded for their efforts.
Plan-do-check-act to improve quality.
Questão 6
Questão
You are required to estimate the time to paint a large wall. You know it takes two hours to paint one square foot of wall. The wall has an area of 30 square foot. So you estimate that it will take 60 hours to paint the wall. Which estimation model are you using?
Responda
Bottom-up
Parametric modeling
Analogous
Expert judgment
Questão 7
Questão
In which process of Project Risk Management knowledge area are numeric values assigned to probabilities and impact of risks?
Responda
Perform Qualitative Risk Analysis
Perform Quantitative Risk Analysis
Perform Numeric Risk Analysis
Plan Risk Response
Questão 8
Questão
Which of the following is an output of the Identify Risks process.
Responda
Lessons Learned
Checklists
Risk Register
SWOT Analysis
Questão 9
Questão
The process of Conduct Procurements is part of the planning phase.
Responda
True
False
Questão 10
Questão
Which process identifies the project manager?
Responda
Develop Project Management Plan
Develop Project Charter
Define Scope
Select Project Process