Scrum Master - Simulado 6 - Inglês - 25 questões

Description

Quiz on Scrum Master - Simulado 6 - Inglês - 25 questões, created by canaldevbr com on 05/01/2019.
canaldevbr com
Quiz by canaldevbr com, updated more than 1 year ago
canaldevbr com
Created by canaldevbr com almost 6 years ago
60
0

Resource summary

Question 1

Question
1) Who should make sure everyone does his or her tasks for the Sprint Backlog?
Answer
  • a) The product owner
  • b) The development team
  • c) The Project manager
  • d) The scrum master
  • e) All the above

Question 2

Question
2) The length of a Sprint should be:
Answer
  • a) Short enough to keep the business risk acceptable to the product owner
  • b) Short enough to be able to synchronize the development work with other business events
  • c) No more than one month
  • d) All these answers are correct

Question 3

Question
3) Which of the following is NOT a product owner’s responsibility?
Answer
  • a) Running the daily scrum meeting
  • b) Working with stakeholders to determine and detail product features
  • c) Gathering requirements for the product backlog items
  • d) Inspecting work at sprint review

Question 4

Question
4) How should items in the product backlog be ordered?
Answer
  • a) Alphabetically first and then by list order in the product backlog
  • b) Grouped by business features first and then chronologically by date of original business request
  • c) Prioritized by business importance first: the items that result in biggest ROI must be prioritized first
  • d) Chronologically by date of original business request first and then by list order in the product backlog

Question 5

Question
5) Which of the following is a role in the scrum framework?
Answer
  • a) Database admin
  • b) Development team
  • c) QA tester
  • d) Senior developer

Question 6

Question
6) When might a sprint be abnormally terminated?
Answer
  • a) When it becomes clear that not everything will be finished by the end of the sprint
  • b) When the sales department has an important new opportunity
  • c) When the development team feels that the work is too hard
  • d) When the sprint goal becomes obsolete

Question 7

Question
7) When multiple team work together on the same product, each team should maintain a separate product backlog.
Answer
  • True
  • False

Question 8

Question
8) Why does scrum prevent product owners from changing product backlog items that are being worked on during the sprint?
Answer
  • a) The development team cannot meet their sprint commitment to complete work if requirements are changing
  • b) A sprint cycle is not enough time for senior management to review and approve changes
  • c) This forces product owners to focus on what is really important for the team to develop
  • d) The development team must be able to limit the product owner authority

Question 9

Question
9) Which of the following is not an official scrum artifact?
Answer
  • a) User stories
  • b) Sprint backlog
  • c) Product backlog
  • d) Software increment

Question 10

Question
10) When do Development Team members become the exclusive owner of a Sprint Backlog item?
Answer
  • a) Never. All Sprint Backlog Items are “owned” by the entire Development Team, even though each one may be done by an individual Development Team member
  • b) During the Daily Scrum
  • c) At the Sprint planning meeting
  • d) Whenever a team member can accommodate more work

Question 11

Question
11) Which of the following statements best explains what the term Sprint means in Scrum?
Answer
  • a) A Sprint is a specific amount of days for a team to test and resolve any issues prior to product release or shipment
  • b) A Sprint is a specific amount of days for a team to work at a sustainable pace to finish select work
  • c) A Sprint is an agreed upon period of time for team members to select individual items from the product backlog to work on
  • d) A Sprint is a specific amount of days for a team to work as many hours as needed to finish assigned work

Question 12

Question
12) A product owner is entitled to postpone the start of a new Sprint after the conclusion of a previous Sprint for the following reason
Answer
  • a) The product owner has not identified a Sprint Goal
  • b) The QA department needs more time to make the previous increment “done”
  • c) The stakeholders are not happy with the value produced in the previous Sprint
  • d) There is no acceptable reason. A new Sprint starts immediately after the conclusion of the previous Sprint
  • e) Not enough Product Backlog items are “Ready”

Question 13

Question
13) Which of the following is not a Scrum cycle activity?
Answer
  • a) Sprint retrospective
  • b) Daily Scrum
  • c) Weekly inspection
  • d) Sprint planning

Question 14

Question
14) Which of the following statements is true about product backlog items?
Answer
  • a) Undefined poorly defined product backlog items should be place on the product backlog with low priority
  • b) All product backlog items are the result of an analysis, requirements and/or design phase(s)
  • c) Undefined or poorly defined product backlog items should be kept out from the product backlog until sufficient detail in a Sprint
  • d) Every product backlog item, whether low priority or high priority, should possess sufficient detail for the team to complete in a Sprint.

Question 15

Question
15) Which of the following is required by Scrum?
Answer
  • a) Release Planning
  • b) Release retrospective
  • c) Sprint Burndown chart
  • d) Members must stand up at the daily Scrum
  • e) Sprint Review
  • f) All the above

Question 16

Question
16) Under what circumstances should separate Product Backlogs be maintained?
Answer
  • a) There are several Product Owners for one product: each Product Owner should have their own Product Backlog
  • b) There are multiple teams working on independent products: each unique combination of team and product should have an independent Product Backlog
  • c) There are multiple product features being developed by the same team
  • d) There are multiple teams working on the components of the same product: each team should have an independent Product Backlog

Question 17

Question
17) Who determines whether the Development Team has been assigned enough work in a Sprint?
Answer
  • a) The Development Team
  • b) The Product Owner
  • c) The Product Owner and the Scrum Master
  • d) The Scrum Master

Question 18

Question
18) Which of the following is not a Product Owner's responsibility?
Answer
  • a) Maintaining the Product Backlog with current information
  • b) Working with stakeholders to determine and detail product features
  • c) Assigning tasks to team members
  • d) Prioritizing the Product Backlog

Question 19

Question
19) Which of the following activities do not occur at the end of the Sprint? (choose 3 answers):
Answer
  • a) Software development
  • b) Release deployment
  • c) Sprint Review meeting
  • d) Quality assurance testing

Question 20

Question
20) What does the Scrum Development Team attempt to develop every Sprint?
Answer
  • a) A product that is ready for customer delivery
  • b) A completed Sprint Backlog
  • c) A product that is ready for QA and/or QC testing
  • d) A product increment that is potentially-ready for customer delivery

Question 21

Question
21) Which two (2) things does the Development Team do during the first Sprint?
Answer
  • a) Develop a plan for the rest of the release
  • b) Deliver an increment of releasable software.
  • c) Develop and deliver at least one piece of functionality.
  • d) Create the complete Product Backlog to be developed in subsequent Sprints.
  • e) Determine the complete architecture and infrastructure for the product.

Question 22

Question
22) The Sprint Planning meeting is comprised of how many sections?
Answer
  • 4
  • 3
  • 2
  • 1

Question 23

Question
23) Please select which of the following statements are true: (choose 3 answers)
Answer
  • a) The Product Owner itemizes which Product Backlog items are done and which Product Backlog items are not done during Sprint Review
  • b) The Product Owner demonstrates potentially-shippable product features and/or components during the Sprint Review
  • c) The Scrum Master provides a report of what happened during the Sprint
  • d) The Development Team demonstrates potentially-shippable product features and/or components during the Sprint Review
  • e) Feedback from stakeholders during the Sprint Review may result in additional Product Backlog items

Question 24

Question
24) Who is responsible for managing the progress of work during a Sprint?
Answer
  • a) The most junior member of the Team
  • b) The Product Owner
  • c) The Development Team
  • d) The Scrum Master

Question 25

Question
25) From the activities given, which is the latest step in sequence of the Scrum framework?
Answer
  • a) Daily scrum
  • b) Sprint retrospective
  • c) Sprint Review
  • d) Sprint planning
Show full summary Hide full summary

Similar

Scrum Master - Simulado 4 - 20 questões - inglês
canaldevbr com
Mapa Mental - Exame de Certificação CTFL-AT
Larissa Trindade
Desenvolvimento Software ágil
Karina Braga
Mapa Mental - Exame de Certificação CTFL-AT
Ayrton Sato
Mapa Mental - Exame de Certificação CTFL-AT
Mayara Cardoso
Simulado CTFL-AT-Agile Tester BSTQB[v1.2br]- 40 questões.
Roger Drumond
Scrum Master - Simulado 1 - Nível iniciante
canaldevbr com
Cadastro Novo Cliente Sales Force Involves
Guilherme Xavier
Foundation Level Syllabus – Agile Tester
Larissa Taw
Simulado Product Owner 02 - Inglês - 30 questões
canaldevbr com