Question 1
Question
Identify the example that would not usually be considered a project.
Answer
-
building a house
-
developing a computer software application program
-
hosting a wedding reception
-
assembly line manufacturing of automobiles
Question 2
Question
According to the authors, the prime objectives of project management are
Answer
-
scope, cost, time
-
quality, scope, schedule
-
customer satisfaction, budget, schedule
-
cost, quality, customer satisfaction
Question 3
Question
In a conventional project lifecycle, as work progresses, uncertainty about the expected outcome should
Answer
-
become a constant
-
decrease
-
increase
-
be fully removed
Question 4
Question
The attributes that characterize a project are
Answer
-
purpose, repetition, inter-dependencies, consistency, uncertainty, conflict, and one¬time occurrence
-
life cycle, schedule, cost, uncertainty, independence, uniqueness, and purpose
-
resources, uniqueness, conflict, inter-dependencies, one-time occurrence, and finite duration,
-
purpose, life cycle, conflict, certainty, independence, performance, and finite duration
Question 5
Question
The "stretched-5" pattern observed during the project lifecycle, for the most part, is a result of the
Answer
-
changing levels of resources used during successive stages of the project lifecycle
-
changing attitudes of the people who work in the project
-
difficulty in performing the individual activities of a project
-
principle that work expands to fill the allotted time
Question 6
Question
The desired outcomes or results of a project are called
Answer
-
subgroups
-
work packages
-
subprojects
-
deliverables
Question 7
Question
Earned value is based on the concept that the percentage of project completion is closely correlated with
Answer
-
the number of levels in the project
-
relevance of the project
-
cost or the use of resources
-
final assembly of the output
Question 8
Question
Which of the following is not one of the four dimensions of project success?
Answer
-
opening new opportunities for the future
-
number of people working on the project
-
impact on the customer
-
business impact on the organization
Question 9
Question
The project to construct a highway is unique because
Answer
-
the characteristics of terrain will be different for different segments
-
consistency of the concrete will vary for different segments
-
different types of laborers will be used to build various segments of the highway
-
different people manage different sections of the highway
Question 10
Question
Projects often interact with other projects being carried out simultaneously within the organization and these interactions take the form of competition for scarce resources between project. This is an example of project
Answer
-
bottleneck
-
breakdown
-
interdependencies
-
malfunctioning
Question 11
Question
When done properly, project management begins with
Question 12
Question
The chance that project processes or outcomes will not turn out as planned is called
Answer
-
risk
-
projecting
-
effort
-
negative outcome
Question 13
Question
Having only partial or no information about the situation or outcomes is called
Answer
-
uncertainty
-
risk
-
effort
-
cluelessness
Question 14
Question
Relations between organizational functions, where one function or task is dependent on others, are known as
Answer
-
interdependencies
-
links
-
projects
-
tasks
Question 15
Question
The of the project team is a crucial but unstated element of ancillary trade-
offs that the project manager must consider.
Question 16
Question
The project is generally credited with beginning the era of modern project
management
Answer
-
Manhattan
-
Chicago
-
Great Wall of China
-
Egyptian pyramids
Question 17
Question
is a subset of a project consisting of work packages
Answer
-
task
-
program
-
project
-
process
Question 18
Question
Projects are bound by the three objectives of scope, time, and cost. These are collectively referred to as the
Answer
-
Triple Constraint
-
Triple Factors
-
Three Constraints
-
Triple Play
Question 19
Question
Individuals or groups with a special interest in a project are called
Answer
-
stakeholders
-
project managers
-
leaders
-
directors
Question 20
Question
The production of weekly employment reports or the delivery of mail could be considered a
Answer
-
project
-
non-project
-
quasi-projects
-
triple projects
Question 21
Question
Which of the following demonstrates the quality of flexibility required of a project selection model?
Answer
-
It does not require special interpretation, data that are difficult to acquire, or excessive personnel.
-
It gives valid results within the range of conditions that the firm might experience.
-
It reflects the multiple objectives of both the firm and its managers.
-
It deals with situations both internal and external to the project.
Question 22
Question
The two basic types of project selection models identified in the text are
Answer
-
biased and unbiased
-
numeric and nonnumeric
-
active and passive
-
numeric and qualitative
Question 23
Question
If a system is being updated due to operating necessity, the project was selected because
Answer
-
the system is worth saving at any cost
-
the system is worth saving at the estimated cost of the project
-
the dimension of cost is not relevant to execution of the project
-
the cost overruns can be hidden in someone else's budget
Question 24
Question
The drawback of the ___________ model is that it fails to consider cash flows obtained once the initial investment has been recovered.
Answer
-
payback period
-
average rate of return
-
discounted cash flow
-
profitability index
Question 25
Question
If the NPV for a project is < 0, it indicates that the project will
Question 26
Question
Scoring models are most often used to overcome this disadvantage of profitability models.
Answer
-
The inability to account for the time value of money
-
The inability to account for project results beyond the payback period
-
The inability to account for multiple decision criteria
-
The inability to account for cash flow
Question 27
Question
Firms usually have two or more projects and this collection of projects is referred to as
Answer
-
a portfolio
-
an initiation
-
a program
-
a stochastic model
Question 28
Question
A technique useful for developing numeric values that are equivalent to subjective, verbal measures of relative value is the
Answer
-
Delphi system
-
expert system
-
portfolio
-
simulation
Question 29
Question
Which of the following is a type of numeric model?
Question 30
Question
The _________ is the value of an opportunity foregone
Answer
-
real option
-
profit
-
opportunity cost
-
revenue
Question 31
Question
The _________ is the interest rate set by an organization as the minimum acceptable rate of return for a project
Answer
-
hurdle rate
-
acceptable rate
-
internal rate of return
-
net present value
Question 32
Question
In a project portfolio, _______________ projects have objectives or deliverables that are only
incrementally different in both product and process from existing offerings.
Answer
-
breakthrough
-
R&D
-
platform
-
derivative
Question 33
Question
In a project portfolio, a project that involves a new technology or even a disruptive technology that is known to the industry would serve as an example of a project
Answer
-
breakthrough
-
R&D
-
platform
-
derivitive
Question 34
Question
The set of documents submitted when evaluating a project is referred to as the
Answer
-
project proposal
-
evaluation set
-
evaluation criteria
-
project manual
Question 35
Question
When the decision maker's information is not complete, he/she will have to make a decision under conditions of
Answer
-
proof
-
uncertainty
-
management
-
risk mitigation
Question 36
Question
The discounted cash flow method determines the net present value of all cash flows by discounting them by the
Answer
-
hurdle rate
-
acceptable rate
-
internal rate of return
-
net present value
Question 37
Question
Financial forecasts are reported as __________ financial statements.
Answer
-
final
-
initial
-
pro forma
-
hypothetical
Question 38
Question
A project selection criteria that focuses on how well new products would fit the firm's existing product line would be
Question 39
Question
According to research by Sanchez and Robert (2010), which of the following is not a reason why strategic benefits may be difficult to appraise?
Question 40
Question
________ is a modeling technique for emulating a process, usually conducted a
considerable number of times to understand the process better and measure its outcomes under different policies.
Answer
-
Simulation
-
Project management
-
Projectizing
-
Modeling
Question 41
Question
According to the authors, the analytic method, when applied to systems, focuses on
Answer
-
assembling the components of a system into an integrated package
-
building an array of individually designed and manufactured components
-
calculating the cost and schedule requirements
-
dividing the components of a system into smaller and smaller elements
Question 42
Question
The ideal project manager should be
Answer
-
a direct, technical supervisor knowledgeable in the technology of the process being used
-
both generalist/facilitator and have a high level of technical competence in the science of the project
-
a facilitator and specialist with technical credibility
-
a technical specialist competent in principles of robust design
Question 43
Question
The project manager must make trade-offs between project progress and process. Conceptually, this involves trade-offs between the _______ functions.
Answer
-
technical and managerial
-
schedule and cost
-
performance and schedule
-
cost and performance
Question 44
Question
According to the authors the project manager should be more skilled at
Answer
-
general management
-
technology
-
synthesis
-
analysis
Question 45
Question
The project manager needs _______ credibility.
Question 46
Question
Projects are conducted in four important environments. They are
Answer
-
economic, political, legal, and sociotechnical
-
internal, external, transitional, and multicultural
-
routine, unique, fast-paced, and complex
-
profit, not for profit, government, and industry
Question 47
Question
According to the authors, the key to coping with uncertainty at the end of a project (a common obstacle for project managers) is
Answer
-
discipline
-
communication
-
planning
-
supervision
Question 48
Question
During the buildup phase, the project goals, in order of importance, are
Answer
-
schedule, scope, cost
-
cost, schedule, scope
-
schedule, cost, scope
-
cost, scope, schedule
Question 49
Question
Resources initially budgeted for a project are frequently _________ for the task, partly because of natural optimism by the proposer about how many resources are needed.
Answer
-
sufficient
-
delayed
-
insufficient
-
hindrances
Question 50
Question
Most of the time spent by a project manager is spent
Question 51
Question
11. The functional manager uses the ________ approach and the PM uses the ________ approach
Answer
-
systems; analytic
-
numerical; nonnumeric
-
analytic; systems
-
nonnumeric; numerical
Question 52
Question
The project manager's responsibility to the project and to the client is met by ensuring that the _______ of the project is preserved in spite of conflicting demands made by stakeholders.
Answer
-
management
-
integrity
-
analysis
-
synthesis
Question 53
Question
During the final or phaseout stage of the project lifecycle, ___________ is the dominant goal of many project managers.
Answer
-
schedule
-
cost
-
scope
-
quality
Question 54
Question
The structure of a society is determined by its
Answer
-
institutions
-
wages
-
jobs
-
enemies
Question 55
Question
Which of the following is not a phase in the Tuckman ladder?
Answer
-
forming
-
defining
-
norming
-
mourning
Question 56
Question
The _________ is a person who spearheads an idea or action and sells it throughout the organization.
Answer
-
stakeholder
-
champion
-
interviewer
-
coach
Question 57
Question
The ______________ is an alternative action if the expected result fails to materialize.
Answer
-
trade-off
-
system plan
-
feedback
-
contingency plan
Question 58
Question
The __________ represents everything outside the system that delivers inputs or
receives outputs from the system.
Answer
-
environment
-
feedback
-
culture
-
system
Question 59
Question
The __________ is the "corporate culture" within the organization, or even within the
project
Answer
-
cultural anomaly
-
microculture
-
multiculture
-
interfirm culture
Question 60
Question
The project manager makes a ___________ by allowing one aspect of the project to get
worse in return for allowing another aspect of the project to get better.
Answer
-
decision
-
turnaround
-
trade-off
-
chart
Question 61
Question
A party to a conflict will usually be satisfied when the level of frustration has been
Answer
-
increased by the domination of the other party
-
lowered to the point where no action against the other party is contemplated
-
lowered because the party realizes the hopelessness of continuing the conflict
-
eliminated because the party has surrendered to the other party
Question 62
Question
Most of the conflicts that involve the organization and outsiders have to do with
Answer
-
interpersonal differences
-
cultural differences and status differences
-
technical differences
-
property rights and contractual obligations
Question 63
Question
During project formation, the organizational structure selected will have a major impact on the ways in which conflicts are handled. Lack of clarity about the relative power/influence/authority of the PM and the functional managers is a major component of all conflicts involving
Question 64
Question
If a resource conflict arises between two high-priority projects, precedence is typically given to the project with the
Answer
-
earliest due date
-
fastest completion time
-
biggest revenue stream
-
lowest cost to complete
Question 65
Question
During project build-up, the project should move from a general concept to
Question 66
Question
During project build-up, if the project is independent and standalone, the project manager seeks a commitment of __________ from the functional departments.
Answer
-
work
-
materials
-
people
-
budgets
Question 67
Question
During project build-up, if the project is functionally tied down, the project manager seeks a commitment of _________ from the functional departments.
Answer
-
work
-
materials
-
people
-
budgets
Question 68
Question
Personality conflicts during project phase-out are often caused by
Answer
-
the absence of deadlines
-
the influx of newer technology
-
pressure to complete the project and anxiety about leaving the project
-
distribution of expenses charged to the project
Question 69
Question
According to the authors, the nature of negotiation as it applies to project management is the realization that few of the conflicts arising in projects have to do with
Answer
-
whether or not the task will be done
-
the precise design of the deliverable
-
how the design will be achieved
-
who will do the work, when, and at what cost
Question 70
Question
When dealing with conflict between parties, it is recommended that one _______ in order to avoid the conflict becoming interpersonal.
Question 71
Question
Partnering is an attempt to _________ the risk associated with sub-contracting.
Answer
-
mitigate
-
Increase
-
absorb
-
allow
Question 72
Question
_________ is the process which begins when one party perceives that the other has frustrated, or is about to frustrate, some concern of his.
Answer
-
conflict
-
happiness
-
contentment
-
utility
Question 73
Question
According to the authors, the favored technique for resolving conflict is
Answer
-
negotiation
-
mitigation
-
avoidance
-
collaboration
Question 74
Question
The process through which two or more parties seek an acceptable rate of exchange for items they own or control is called
Answer
-
negotiation
-
mitigation
-
compromising
-
collaboration
Question 75
Question
During the early program phases of the project lifecycle, Thamhain et al say that conflict intensity is the greatest with respect to
Answer
-
cost
-
schedules
-
scope
-
quality
Question 76
Question
During the main program phases of the project lifecycle, Thamhain et al say that conflict intensity is the greatest with respect to
Answer
-
cost
-
schedules
-
scope
-
quality
Question 77
Question
Toward the end of the project lifecycle, Thamhain et at say that conflict intensity is the greatest with respect to
Answer
-
cost
-
schedules
-
scope
-
quality
Question 78
Question
Negotiating to a(n) __________ solution is the key to conflict resolution in project management.
Answer
-
win-lose
-
win-win
-
avoidance
-
confrontation
Question 79
Question
The total level of conflict in the project lifecycle is highest during the _________ stage
Answer
-
closing
-
main program
-
project build-up
-
project formation
Question 80
Question
The ___________ approach to negotiation aims to achieve a win-win result.
Answer
-
principled
-
posititional
-
stakeholder
-
paretto
Question 81
Question
If the project manager controls when and what people do while the functional managers control who will be assigned to the project and what technology will be used, the ______organizational form is probably being used.
Answer
-
projectized
-
pure project
-
matrix
-
weak project
Question 82
Question
In the systems approach to design, one organization would have to take responsibility for
Answer
-
manufacturing everything in the system
-
the integrity of the project design
-
the integrity of the subcontractors
-
product warranties
Question 83
Question
The process of dealing with uncertainties in projects that may affect the project for better or for worse has come to be known as
Answer
-
scope management
-
risk management
-
quality management
-
procurement management
Question 84
Question
A common objective of an organization's PM is often created by organizations to
Answer
-
establish consistent project management standards and methods
-
deal with technological obsolescence
-
train process managers
-
administer application software
Question 85
Question
A major purpose of the project management office should be to serve as
Answer
-
the central location for all clerical support
-
the critical disaster recovery support
-
a link between strategic management and project management
-
maintenance for the project management library
Question 86
Question
This member of the project team is in charge of product design and development and is responsible for functional analysis, specifications, drawings, cost estimates, quality/reliability, engineering changes, and documentation
Answer
-
systems architect
-
manufacturing engineer
-
project controller
-
support services manager
Question 87
Question
This member of the project team is responsible for the efficient production of the product of the process, including the manufacturing engineering, design and production of tooling, production scheduling, and other production tasks
Answer
-
project engineer
-
development engineer
-
contract administrator
-
support services manager
Question 88
Question
This person is responsible for the installation, testing, and support of the product (process) once its engineering is complete.
Answer
-
development engineer
-
systems architect
-
test engineer
-
project controller
Question 89
Question
One of the main technical problems faced by the project manager is meeting ________ without compromising performance.
Answer
-
supplier's targets
-
schedule and cost goals
-
technical specifications
-
cost and conflict goals
Question 90
Question
A major advantage of using a _________ placement for a project is that individual
experts can be utilized by many different projects.
Answer
-
standard
-
virtual
-
projectized
-
functional
Question 91
Question
Virtual teams, when composed, should consist of "boundary spanners" who number about one in every _________ team members
Question 92
Question
When a firm engages in a large number of similar projects, the ___________ organizational form is apt to be preferred.
Answer
-
pure project
-
partial matrix
-
functional
-
mixed matrix
Question 93
Question
When the standard departments of the organization represent individual disciplines such as engineering, marketing, purchasing, and so on, the organization follows
Answer
-
projectized management
-
matrixed management
-
functional management
-
mixed management
Question 94
Question
The firm or organization within which the project is being conducted is known as the
Answer
-
parent organization
-
consulting firm
-
project team
-
stakeholder company
Question 95
Question
______________ engineering refers to the use of a design team that includes design and manufacturing engineers as well as staff from other relevant areas of the business.
Answer
-
Concurrent
-
Alignment
-
Matrix
-
Social
Question 96
Question
The _________ is a basic project document that describes all the work that must be done to complete the project and forms the basis for costing, scheduling, and work
Answer
-
WBS
-
OBS
-
PMO
-
project charter
Question 97
Question
The approach to organizing that includes both functions (disciplines) and projects in its hierarchy is known as the
Answer
-
mixed organization
-
functional organization
-
projectized organization
-
matrix organization
Question 98
Question
This person's task is the efficient production of the product or process the project engineer has designed, including responsibility for manufacturing engineering, design and production of code, unit testing, production scheduling, and other production tasks.
Answer
-
test engineer
-
contract administrator
-
development engineer
-
systems architect
Question 99
Question
TQM and Six Sigma are good examples of ____________ programs
Answer
-
participative
-
exclusive
-
frequency
-
inclusive
Question 100
Question
If both functional and projectized divisions coexist in a firm, this would result in the __________ organizational structure.
Answer
-
composite
-
objective
-
encompassing
-
free-form
Question 101
Question
The _________ is a specialized view of the action plan that focuses on who has what
responsibility for each project task.
Question 102
Question
The success of the project launch meeting is dependent on the existence of
Answer
-
a project charter
-
the project's scope statement
-
a well-defined set of objectives for the project
-
project planning templates
Question 103
Question
This project plan element describes both the managerial and the technical approaches to the work. The technical discussion describes the relationship of the project to available technologies.
Answer
-
overview
-
objectives
-
general approach
-
contractual aspects
Question 104
Question
This project plan element should include profit and competitive goals as well as technical goals.
Answer
-
overview
-
objectives
-
general approach
-
contractual aspects
Question 105
Question
The _______ of a project includes the objectives of the project as well as the time and cost required to complete the project to the customer's satisfaction.
Answer
-
scope
-
change order
-
outcome
-
purpose
Question 106
Answer
-
responsive, accountable, consult, inform
-
responsible, accountable, consult, inform
-
responsive, accountable, consult, integrate
-
responsible, admissible, consult, integrate
Question 107
Question
The set of physical elements required to build a project is called the
Answer
-
bill of materials
-
deliverable
-
milestone list
-
work statement
Question 108
Question
___________ is an approach that breaks the planning task down into the activities that must be done in each managerial level of the organization. Typically, the upper level sets the objectives for the next lower level.
Answer
-
Strategic planning
-
Organizational planning
-
Hierarchical planning
-
Agile planning
Question 109
Question
The major tool that a project manager uses during the planning phase is called the
Answer
-
WBS
-
change request
-
scope statement
-
project plan
Question 110
Question
___________is the tendency for the project objectives to be changed with little or no discussion with other parties actively engaged in the project
Answer
-
Scope reference
-
Scope creep
-
Effectiveness
-
Hierarchical planning
Question 111
Question
_______________ is a visual approach that closely mirrors how the human brain records and stores information that can help tap the creative potential of the entire project team
Answer
-
WBS generation
-
Project planning
-
Risk response planning
-
Mind mapping
Question 112
Question
When using a WBS, all of the work should roll up to the next level such that no extra work is required. This is referred to as the
Answer
-
Development rule
-
All-inclusive rule
-
100% rule
-
WBS rule
Question 113
Question
For projects that are constantly changing, the __________ methodology is recommended
Answer
-
waterfall
-
agile
-
adaptable
-
organic
Question 114
Question
Having key stakeholders involved early in the project tends to
Question 115
Question
When using the mind mapping process, you should designate one team member as the ___________ to ensure that all team members are involved and contributing, and to ensure that team members are focusing on the work that must be done.
Answer
-
planner
-
facilitator
-
contractor
-
manager
Question 116
Question
A useful tool for facilitating the management of changes to a project's scope is the
Question 117
Question
A project manager must ___________ as a type of risk response planning in order to soften the danger of a threat by reducing the likelihood that it will occur or by reducing its impact if it does occur.
Answer
-
avoid
-
transfer
-
accept
-
mitigate
Question 118
Question
The ____________ is a list of the project activities with major activities broken down into subactivities.
Question 119
Question
The process of coordinating the work and timing of the different groups working on multidisciplinary teams is called
Answer
-
procurement management
-
integration management
-
vertical management
-
matrix management
Question 120
Question
This element of the project plan contains a brief description of the procedure to be followed in monitoring, collecting, storing, and evaluating the history of the project
Answer
-
schedule
-
resources
-
personnel
-
evaluation methods
Question 121
Question
If a project budget is under funded, it will often
Answer
-
stimulate increased performance
-
improve utilization of resources
-
frustrate committed stakeholders
-
reduce costs
Question 122
Question
The project's budget should
Answer
-
associate resource use with the achievement of organizational goals
-
allow funds to be spent without linkage to achievement
-
not reflect the timing of expenses associated with the use of resources
-
never be changed during project execution
Question 123
Question
In order to develop a budget, the PM must forecast
Question 124
Question
A work element whose cost is fully developed would
Answer
-
exclude the cost of labor and resources
-
include only the profit and direct costs
-
exclude the cost of special machinery and overheads
-
include direct costs plus overhead and G&A charges
Question 125
Question
The traditional organizational budget is
Question 126
Question
__________ budgeting allows income and expenditures to be aggregated across projects.
Answer
-
Category-oriented
-
Activity-oriented
-
Project-oriented
-
Expense-oriented
Question 127
Question
The authors identify ____________ estimation errors as the two types of generic estimation errors.
Answer
-
small and large
-
random and planned
-
certain and uncertain
-
random and biased
Question 128
Question
The pattern of deviations in cost and usage used for exception reporting to management is called
Answer
-
simulations
-
assumptions
-
variances
-
summaries
Question 129
Question
___________ costs vary with output.
Question 130
Question
Unless the project manager is familiar with the firm's ______________ it will be very difficult to exercise budget control.
Answer
-
accounting system
-
budget plans
-
marketing procedure
-
cost accounting
Question 131
Question
The __________ form of budgeting has the advantage of using individuals closer to the work to provide estimates of resource requirements.
Answer
-
top-down budgeting
-
work element costing
-
bottom-up budgeting
-
iterative budgeting
Question 132
Question
The ___________ charge is composed of the costs of senior management, the various data functions, and any other expenses not included in overhead. Often, these charges are a fixed percentage of either the direct costs or the total of all direct and indirect costs.
Answer
-
salary
-
project management
-
ethical
-
G&A
Question 133
Question
Each time the output doubles, the worker hours per unit decrease to a fixed percentage of their previous value. That percentage is called the ___________ rate.
Answer
-
inflation
-
hurdle
-
interest
-
learning
Question 134
Question
Suppose that a person requires 60 minutes to complete a work element on the first attempt. On the second attempt, the work element is completed in 48 minutes. The learning rate for this person is _________% for this work element
Question 135
Question
_____________ relies on well-known statistical correlations between various factors such as the total cost of a house relative to the square feet of living area.
Answer
-
Parametric estimating
-
Statistical equivalence
-
Bottom-up estimating
-
Top-down estimating
Question 136
Question
A budget strategy that is based on collecting the judgments and experiences of top and middle managers is referred to as the ___________ approach or method.
Answer
-
parametric estimating
-
statistical equivalence
-
bottom-up estimating
-
top-down estimating
Question 137
Question
________________ are where the defined responses to the risks are detailed, but their amounts are not
yet precisely known.
Answer
-
Known-unknowns
-
Unknown-knowns
-
Known-knowns
-
Unknown-unknowns
Question 138
Question
Unknown-unknowns are not part of the baseline budget and are referred to as
Answer
-
management reserves
-
contingency reserves
-
PMBOK reserves
-
Buffered reserves
Question 139
Question
The advantage of the ____________ process is that it is generally associated with participative management
Answer
-
bottom-up
-
top-down
-
Murphy's
-
Efficient
Question 140
Question
______________ issues are present when bidders "low-ball" a bid or when some bidders get a "last look."
Answer
-
Ethical
-
Strategic
-
Efficient
-
Effective
Question 141
Question
The authors recommend preparing a schedule for each
Question 142
Question
In the AOA network, circles depict
Answer
-
networks
-
events
-
logical dependencies
-
dummy activities
Question 143
Question
The shortest time in which the entire network can be completed is referred to as the
Answer
-
critical time of the network
-
real duration of the network
-
elapsed time of the network
-
slack time of the network
Question 144
Question
A precedence relationship where the completion of a successor activity depends on the completion of a predecessor activity is called a
Answer
-
start to finish dependency
-
finish to start dependency
-
finish to finish dependency
-
start to start dependency
Question 145
Question
A precedent relationship where the completion of a predecessor activity depends on the initiation of a successor activity is called a
Answer
-
start to finish dependency
-
finish to start dependency
-
finish to finish dependency
-
start to start dependency
Question 146
Question
The difference between the late start and early start for an activity is called its
Answer
-
critical path
-
task
-
progress
-
float
Question 147
Question
A(n) __________ is the conversion of the project work breakdown structure into an operating timetable.
Answer
-
chart
-
application
-
crash
-
schedule
Question 148
Question
A(n) _________ is a specific task or set of tasks that are required by the project, use up resources, and take time to complete
Answer
-
milestone
-
activity
-
node
-
path
Question 149
Question
The arrangement of all activities (and, in some cases, events) in a project arrayed in their logical sequence and represented by arcs and nodes is called a
Answer
-
network
-
critical path
-
path
-
crashed path
Question 150
Question
In a network, if the delay of an activity will delay completion of the project, the activity is called a(n)
Answer
-
valuable
-
efficient
-
critical
-
noteworthy
Question 151
Question
In AOA networks, an activity of zero duration is called a(n)
Answer
-
dummy activity
-
critical
-
important
-
critical activity
Question 152
Question
The _____________ chart shows planned and actual progress for a number of tasks displayed against a horizontal timescale.
Answer
-
PERT
-
timeline
-
critical
-
Gantt
Question 153
Question
A clearly identifiable point in a project or set of activities that commonly denotes a reporting requirement or completion of a large or important set of activities is called a(n)
Answer
-
milestone
-
anniversary
-
node
-
dummy activity
Question 154
Question
In AON diagrams, a(n) ________________ is a point where one or more lines (arrows) begin or terminate, commonly used for depicting an event or activity.
Question 155
Question
______________ is the amount of one factor that must be sacrificed in order to achieve more or less of another factor.
Answer
-
trade-off
-
synergy
-
barter limit
-
limiting quantity
Question 156
Question
A _____________ is a combination of interrelated activities and events depicted with arcs and nodes.
Answer
-
linked plan
-
chain of events
-
critical chain
-
network
Question 157
Question
____________ law suggests that work expands to fill the allotted time.
Answer
-
Parkinson's
-
Murphy's
-
Brooks'
-
Federal
Question 158
Question
In application, PERT has primarily been used for
Question 159
Question
The authors define _________ as the time an activity can be delayed without affecting the start time of any successor activity
Answer
-
free slack
-
total slack
-
project slack
-
overhead slack
Question 160
Question
__________ is one possible way to check the nature and impacts of interactions between probabilistic paths in a network.
Question 161
Question
If deterministic time estimates are used, and if project deadlines are firm, there is a high likelihood that it will
Answer
-
not be necessary to crash any activities in projects
-
be necessary to crash the last few activities of most projects
-
be completed on time and within budget
-
be completed as per schedule
Question 162
Question
Assume two activities, printing and binding. Printing is a predecessor of binding. If printing is _______, then binding will start late by whatever amount of lateness is bequeathed to it by printing.
Answer
-
necessary
-
early
-
late
-
time-neutral
Question 163
Question
________ aims to minimize the period-by-period variations in resource loading by shifting tasks within their slack allowances. The purpose is to create a smoother distribution of resource usage.
Answer
-
Resource loading
-
Resource leveling
-
Scope loading
-
Resource succeeding
Question 164
Question
A project task is said to be __________ if it requires a fixed amount of time and known quantities of resources
Answer
-
scope constrained
-
time constrained
-
resource constrained
-
system constrained
Question 165
Question
One of the problems that Goldratt observed was that if an activity has slack time, the task might become delayed until the slack is removed. This is referred to as
Answer
-
Goldratt's Law
-
Murphy's Law
-
the delay game
-
the student syndrome
Question 166
Question
The points between the extreme points of the relationship between time use and resource use represent
Answer
-
time constrained projects
-
resource constrained projects
-
alternative trade-offs between time and resources
-
a non-feasible solution space of trade-off alternatives related to time and resource use
Question 167
Question
The _________ technique overlaps the design and build phases of a project to expedite its completion.
Answer
-
crashing
-
fast-tracking
-
leading
-
blitzing
Question 168
Question
Most heuristic solution methods start with the _____________ and analyze resource usage period by period, resource by resource.
Answer
-
GERT schedule
-
Gantt chart
-
PERT/CPM schedule
-
Master schedule
Question 169
Question
The use of ______________ activity time estimates may reduce the chance that crashing the
project will be needed.
Answer
-
one probabilistic
-
two probabilistic
-
three probabilistic
-
four probabilistic
Question 170
Question
The standard practice with AOA and AON is to estimate activity times under the assumption of resource loadings that are
Answer
-
probabillistic
-
crashed
-
normal
-
dynamic
Question 171
Question
With respect to project scheduling, __________ is the amount of work waiting to be processed because there is a shortage of some resource.
Answer
-
in-process inventory
-
schedule slippage
-
resource utilization
-
management delay
Question 172
Question
If the appropriate scheduling equation for task A of a project were W = D * U, and it was initialized so that W = 40d, D = 10d, and U = 4 resources, and task A is an effort-driven activity, correctly balance this equation if the value for U is changed from 4 to 5. To balance the equation, the altered variable and its new value are
Answer
-
D = 6w
-
W = 6d
-
D = 8d
-
W = 8d
Question 173
Question
The principal reason why a project manager is surprised by resource constraints on a project is the failure to include _________ in risk identification activities.
Answer
-
resource availability
-
resource cost
-
resource mobility
-
resource skill
Question 174
Question
Which of the following describes a situation where priorities are assigned to activities according to some rule not associated with task length, slack, or resource requirements?
Answer
-
student's syndrome
-
arbitrary
-
most successors
-
most resources
Question 175
Question
The two fundamental approaches to constrained allocation problems are
Answer
-
heuristic approaches and rules of thumb
-
linear programming approaches and optimization models
-
heuristic approaches and optimization models
-
goal programming and trial and error
Question 176
Question
When crashing a project, our first task is to develop
Answer
-
a table or graph of the cost of a project as a function of the project's possible completion dates
-
a schedule that shows the risks associated with each activity in the project
-
a list that shows the activities and the events of a project without referring to the costs
-
a table showing the noncritical activities and the cost associated with each of those activities
Question 177
Question
In some situations, two activities are scheduled to be carried out in parallel and using the same scarce resource. If the supply of the scarce resource is not sufficient to allow both activities to be carried out simultaneously, then whichever of the two is given priority immediately lengthens the other activity's path but not its actual
Answer
-
duration
-
slack
-
float
-
buffer
Question 178
Question
The two principles to follow when crashing a project focuses on the
Answer
-
critical path and selects the least expensive alternative
-
critical path and selects the most expensive alternative
-
shortest path and selects the least expensive alternative
-
shortest path and selects the most expensive alternative
Question 179
Question
Using Goldratt's meaning of the word "dependent," the activities of a project can be ordered into paths based on their resource dependencies as well as on their technological precedence requirements. The longest of these paths of sequentially time-dependent activities is known as the
Answer
-
priority chain
-
critical chain
-
dependency path
-
heuristic path
Question 180
Question
The ___________ heuristic provides a general solution for critical path and time and is usually the default rule for a schedule.
Answer
-
as soon as possible
-
as late as possible
-
minimum slack first
-
shortest task first
Question 181
Question
Monitoring, as an activity, should be kept distinct from __________, which uses data supplied by monitoring to bring actual performance into approximate congruence with planned performance.
Answer
-
recording
-
controlling
-
collecting
-
reporting
Question 182
Question
An appropriate and common secondary user for monitoring includes
Answer
-
auditing, learning from mistakes, and reporting progress and status
-
exercising effective control over the project
-
evaluating current status of the project
-
fixing the blame when things go wrong
Question 183
Question
According to the authors, the key items to be planned, monitored, and controlled are
Answer
-
schedule, budget, and financial stability
-
schedule, quality, performance, and customer satisfaction
-
schedule, budget, and feasibility
-
schedule, budget, and performance
Question 184
Question
According to the authors, in the planning - monitoring - controlling cycle, the directions of the flows indicate that
Answer
-
information flows from the top to bottom and authority flows from the bottom to the top
-
information flows from the bottom to the top and authority flows from the top to the bottom
-
authority flows from the bottom to the top
-
information flows from the top to the bottom
Question 185
Question
The first step in setting up a monitoring system is to
Answer
-
collect existing data to see what data is relevant and available
-
collect every available piece of information so it can be analyzed
-
use whatever information is available
-
identify the key factors to be controlled
Question 186
Question
In earned value analysis, the 50-50 rule assumes that
Answer
-
50 percent is earned when the task is half done and 50 percent is earned at completion
-
50 percent is earned when the task begins and 50 percent is earned at completion
-
50 percent is earned when the task begins and 50 percent is earned at the halfway stage
-
50 percent is earned when the project is planned and 50 percent is earned when the project is over
Question 187
Question
In earned value analysis, if the cost variance is (-$10,000),
Answer
-
the cost variance is favorable
-
the cost variance is unfavorable
-
the scheduled variance is favorable
-
the scheduled cost avoidance is unfavorable
Question 188
Question
One of the most common errors when collecting data is
Answer
-
collecting rapidly changing data frequently
-
collecting data infrequently because data collection is so time consuming
-
collecting data that rarely changes
-
reporting to management after collecting data
Question 189
Question
Reports for ______________ have a need for detailed information about individual tasks and the factors affecting such tasks.
Answer
-
top executives
-
lower-level personnel
-
all the stakeholders
-
project managers
Question 190
Question
The project control process should be viewed as a(n) ________________, with revised plans
and schedules (if warranted) following corrective actions. The project control process should run continuously until the project is completed.
Answer
-
closed loop system
-
open loop system
-
open environment
-
earned value plan
Question 191
Question
Ordinal rankings of performance are examples of a _________ type of measure.
Question 192
Question
____________ are used when some aspect of system performance cannot be measured
directly
Answer
-
Indicators
-
Frequency counts
-
Raw numbers
-
Verbal measures
Question 193
Question
____________ can often give the project manager early warning signals of potential problems in a project and help understand the relationships of individual tasks to one another and to the overall project.
Question 194
Question
The earned value rule that divides the actual task time-to-date by the scheduled time for the task to calculate percent complete is called the _________ rule.
Answer
-
50-50
-
0-100 percent
-
critical input use
-
proportionality
Question 195
Question
In earned value analysis, EAC refers to the
Question 196
Question
In earned value analysis, BAC refers to the
Answer
-
budgeted annual cost
-
budget at completion
-
budget at close-out
-
big annual cost
Question 197
Question
If EV= $500, AC = $475, PV = $450; SV =
Question 198
Question
If CSI is less than 1, it is indicative of a(n)
Answer
-
problem
-
good project
-
efficient project
-
budget error
Question 199
Question
Conceptually, EAC represents the amount spent to date
Answer
-
plus the delay costs
-
BAC
-
CV
-
ETC
Question 200
Question
In earned value analysis, the 0 - 100 percent rule allows
Answer
-
100 percent credit before starting work and 0 percent credit after the completion
-
0 percent credit when work begins and 100 percent credit when the project is complete
-
0 percent credit when work begins and 100 percent credit at completion of the activity
-
0 percent credit at completion of the activity and 100 percent credit at formal acceptance during scope verification