Question 1
Question
1. How much mixed material is needed to complete a floor screed 5.000 m long by 4.000 m wide
and 0.050 m thick?
Answer
-
0.25 m3
-
0.5 m3
-
1 m3
-
1.5 m3
Question 2
Question
2. Tools and equipment for floor screeding will generally include:
Answer
-
sweeping brush, trowel, float, mixer, shovel
-
splash brush, small tool, gauger, trowel, float
-
spirit level, trowel, buckets, mixer, float
-
levelling equipment, trowel, float, shovel buckets, mixer
Question 3
Question
Plastic sheeting below the structural floor is the:
Answer
-
damp proof membrane
-
vapour barrier
-
moisture trap
-
aid to curing the floor
Question 4
Question
The type of cement used in floor screeds is:
Answer
-
Masonry Portland
-
Extra Portland
-
Rapid Portland
-
Ordinary Portland
Question 5
Question
Sands used for floor screeding:
Answer
-
should contain a high proportion of fine grains
-
should contain a high proportion of large grains
-
can be any type
-
should be sharp and well graded
Question 6
Question
Ready-mixed screeds are:
Answer
-
prepared off site and delivered as required
-
prepared after work for the following day
-
prepared in the morning for use during the day
-
used only for self-levelling floors
Question 7
Question
Screed rails or battens are used to:
Answer
-
help delivery of screed material to the workstation
-
assist in forming the main area of floor
-
tamp down the surface of the screed
-
form channels for drainage
Question 8
Question
The purpose of a damp proof membrane is to:
Answer
-
assist the passage of moisture
-
assist in the curing process
-
allow the screed to dry out quickly
-
prevent the passage of moisture
Question 9
Question
Cracking of large area floors may be reduced by:
Question 10
Question
Battens used as a guide for screeds may be:
Answer
-
set out from datum lines
-
laid at 50 mm depth
-
set out from base floor
-
laid to form 75 mm depth
Question 11
Question
The most accurate proportioning of floor screeding materials:
Answer
-
is by weight
-
is important near heavily trafficked areas
-
can be carried out using shovels
-
can be carried out using buckets
Question 12
Question
The correct consistency for floor screeding materials is:
Answer
-
as dry as possible
-
slurry like
-
semi wet
-
semi dry
Question 13
Question
Mixing of screed material:
Answer
-
does not have to be thorough as it will be spread by shovel
-
needs to be consistent or wear will take place
-
should be carried out as slowly as possible
-
can take place after water has been added
Question 14
Question
Compacting screeds results in a:
Answer
-
lightweight screed
-
quicker set screed
-
more dense screed
-
slower set screed
Question 15
Question
Compacting can be carried out with a:
Answer
-
screed rail
-
datum
-
rule or float
-
level
Question 16
Question
High volumes of ventilation:
Answer
-
will aid the setting process
-
will not affect the screeds after laying
-
will allow the cement to harden quickly
-
may make the surface of the screed dusty
Question 17
Question
The finish on a floor screed:
Answer
-
is not important as it will all be covered up
-
is important as it may show through the final covering
-
can be completed the next day
-
can be completed by the floor layer with the finish
Question 18
Question
Laying polythene sheet on the floor screed after laying will:
Answer
-
act as an accelerator to the set
-
produce an even surface
-
allow the cement to set naturally
-
keep the floor soft for the next process
Question 19
Question
The purpose of curing is to:
Answer
-
allow the cement to set and harden over a long period
-
produce an even surface
-
produce a lightweight screed
-
aid compaction to take place
Question 20
Question
Where drainage outlets are fitted:
Answer
-
the floor must be laid from this point
-
they can be repositioned later
-
the floor can be altered to fit when finish is applied
-
the drainage contractor will alter them to suit