Zusammenfassung der Ressource
SAB7#62_Optimization
Resources
- Resource Leveling
- Leveling lengthnes the schedule
and increases cost in order to deal
with a limited amount of resources,
resource availability and other
resources constraints.
- Allows to level the peaks
and valleys of the
schedule.
- Balanced resources
according to
availability. Usually
increase the critical
path
- Resource Smoothing
- The resources are leveled only
within the limits of the float of
their activities, so the completion
dates of activities are not delayed.
- It doesn't change the critical path
- It doesn't have resources optimization
- Find ways to adjust the use of resources