Frage 1

Frage
Crashing differs from fast tracking because crashing:
Antworten
  • a. Usually increases value.
  • b. Usually increases the cost.
  • c. Usually saves more time
  • d. Usually saves more money.

Frage 2

Frage
Crashing in time management is:
Antworten
  • a. A schedule compression technique includes reducing schedule activity durations and increasing the assignment of resources to schedule activities.
  • b. A schedule compression technique in which phases or activities that normally would be done in sequence are performed in parallel.
  • c. The timely input of data to calculate the critical path.
  • d. Equivalent to minimizing float.

Frage 3

Frage
Bar charts are useful in determining:?
Antworten
  • a. The level of effort of an activity.
  • b. Activity start and end dates, as well as expected durations.
  • c. Availability of resources assigned to perform an activity.
  • d. Relative priority of activities.

Frage 4

Frage
An example of a “soft logic” dependency, is:?
Antworten
  • a. Project A, the company’s participation in a Industry trade show, depends on the successful completion of Project B, which is building the prototype of the product that is going to be displayed.
  • b. To install the plumbing and electrical work at the same time family is living in a house.
  • c. Finished software before training program.
  • d. To schedule the final testing activity of a computer before the manual is finish.

Frage 5

Frage
Analogous duration estimating is:?
Antworten
  • a. Bottom-up estimating.
  • b. Frequently used to estimate project duration when there is a limited amount of detailed information.
  • c. Similar to multiple duration estimating.
  • d. Deductive estimating.

Frage 6

Frage
All of the following are true about resource leveling EXCEPT:?
Antworten
  • a. Can be used to keep selected resource usage at a constant level during specific time periods.
  • b. Offer results in a projected duration for the project that is longer than the preliminary project schedule.
  • c. Is sometimes called the resource-based method.
  • d. Is used to develop a meaningful WBS.

Frage 7

Frage
An organization uses a desktop scheduling software for project scheduling. What would this software be considered as??
Antworten
  • a. Project management office.
  • b. Enterprise environmental factor.
  • c. Organizational process asset.
  • d. Integrated change control system.

Frage 8

Frage
All of the following choices represent inputs to the Estimate Activity Resources EXCEPT:?
Antworten
  • a. Organizational process assets.
  • b. Activity cost estimates.
  • c. The actual final cost of the last project.
  • d. Risk register

Frage 9

Frage
As one of the tools and techniques of Sequence Activities, a lead:?
Antworten
  • a. Directs a delay in the successor activity.
  • b. Could be accomplished by a finish-to-start relationship with a delay time.
  • c. Means the successor activity cannot start until after the predecessor is completed.
  • d. Allows an acceleration of the successor activity.

Frage 10

Frage
A schedule compression technique to determine how to obtain the greatest amount of compression for the least incremental cost is called:?
Antworten
  • a. Crashing.
  • b. PERT.
  • c. Precedence Diagram Method - PDM.
  • d. Fast tracking.
Zusammenfassung anzeigen Zusammenfassung ausblenden

ähnlicher Inhalt

Stilmittel
Cassibodua
Online Karteikarten im Klassenraum
Laura Overhoff
Wege, um mit GoConqr Tools zu unterrichten
Elena Koch
PuKW STEP 4 (mögliche Prüfungsfragen/Prüfungsvorbereitung)
Sandra S.
GPSY ALPS
hf.meyer
Themen der Vektorrechnung II
Paula Raithel
WERB Uni Wien 2017/18
Denise Schmid
Vetie Allgemeine Pathologie Altfragen 2016
Nele Unger
Vetie Mibi 2012
Tropsi B
Vetie - Spezielle Pathologie 2021
Svea Schill
Vetie - Lebensmittelkunde 2021
Valerie Nymphe