Frage 1
Frage
Crashing differs from fast tracking because crashing:
Antworten
-
a. Usually increases value.
-
b. Usually increases the cost.
-
c. Usually saves more time
-
d. Usually saves more money.
Frage 2
Frage
Crashing in time management is:
Antworten
-
a. A schedule compression technique includes reducing schedule activity durations and increasing the assignment of resources to schedule activities.
-
b. A schedule compression technique in which phases or activities that normally would be done in sequence are performed in parallel.
-
c. The timely input of data to calculate the critical path.
-
d. Equivalent to minimizing float.
Frage 3
Frage
Bar charts are useful in determining:?
Antworten
-
a. The level of effort of an activity.
-
b. Activity start and end dates, as well as expected durations.
-
c. Availability of resources assigned to perform an activity.
-
d. Relative priority of activities.
Frage 4
Frage
An example of a “soft logic” dependency, is:?
Antworten
-
a. Project A, the company’s participation in a Industry trade show, depends on the successful completion of Project B, which is building the prototype of the product that is going to be displayed.
-
b. To install the plumbing and electrical work at the same time family is living in a house.
-
c. Finished software before training program.
-
d. To schedule the final testing activity of a computer before the manual is finish.
Frage 5
Frage
Analogous duration estimating is:?
Frage 6
Frage
All of the following are true about resource leveling EXCEPT:?
Antworten
-
a. Can be used to keep selected resource usage at a constant level during specific time periods.
-
b. Offer results in a projected duration for the project that is longer than the preliminary project schedule.
-
c. Is sometimes called the resource-based method.
-
d. Is used to develop a meaningful WBS.
Frage 7
Frage
An organization uses a desktop scheduling software for project scheduling. What would this software be considered as??
Antworten
-
a. Project management office.
-
b. Enterprise environmental factor.
-
c. Organizational process asset.
-
d. Integrated change control system.
Frage 8
Frage
All of the following choices represent inputs to the Estimate Activity Resources EXCEPT:?
Antworten
-
a. Organizational process assets.
-
b. Activity cost estimates.
-
c. The actual final cost of the last project.
-
d. Risk register
Frage 9
Frage
As one of the tools and techniques of Sequence Activities, a lead:?
Antworten
-
a. Directs a delay in the successor activity.
-
b. Could be accomplished by a finish-to-start relationship with a delay time.
-
c. Means the successor activity cannot start until after the predecessor is completed.
-
d. Allows an acceleration of the successor activity.
Frage 10
Frage
A schedule compression technique to determine how to obtain the greatest amount of compression for the least incremental cost is called:?