Frage 1

Frage
An essential auxillary in a gas turbine system is
Antworten
  • regenerator
  • starting motor
  • intercooler
  • waste heat boiler
  • combustor

Frage 2

Frage
A gas turbine is started in the following sequence of operation 1. air is heated in the combustor 2. air is drawn into the compressor 3. exhaust gases expand through the turbine 4. air is exhausted to atmosphere or hrsg
Antworten
  • 1,2,3,4
  • 2,1,3,4
  • 4,2,3,1
  • 2,4,1,3
  • 3,1,2,4

Frage 3

Frage
Air choking in the high pressure end of the compressor is also termed:
Antworten
  • sputtering
  • back-firing
  • choking
  • surging
  • dead-heading

Frage 4

Frage
When starting a gas turbine in manual mode, what would be the first step
Antworten
  • start the starting motor
  • engage the ignitors
  • load the power turbine
  • engage the turning gear
  • start the auxillary systems

Frage 5

Frage
Water washing and adding chemicals to fuels that contain sodium or vanadium is primarily for
Antworten
  • reducing deposits on turbine blades
  • reduce blade erosion
  • lower exhaust gas temperatures
  • reduce turbine blade erosion
  • lower NOX emmisions

Frage 6

Frage
Major overhauls are performed on a gas turbine:
Antworten
  • annualy
  • when performance is poor
  • monthly
  • according to the manufacturers specifications
  • during off-peak hours

Frage 7

Frage
Which of the following components will reduce noise pollution from a gas turbine system: 1. inlet silencers 2. exhaust silencers 3. acoustic insulation 3. using axial air compressors
Antworten
  • 1,2
  • 2,3,4
  • 1,2,4
  • 1,2,3
  • 1,2,3,4

Frage 8

Frage
Which interlocks need to be in the start position to start a gas turbine 1. oil pressure normal 2. dampers and ducting open 3. controls circuits energized 4. governer in start position
Antworten
  • 1,2
  • 2,3,4
  • 1,2,4
  • 1,2,3
  • 1,2,3,4

Frage 9

Frage
Minor servicing carried out on a gas turbine:
Antworten
  • is done monthly
  • is done annualy
  • may only allow some adjusting to the combustor unit
  • will include power turbine blade replacement
  • will include compressor balancing and mechanical maintenance

Frage 10

Frage
when inspecting the flame tube of a gas turbine during a turnaround the operator should check for
Antworten
  • distortion
  • proper ignition
  • air flow restrictions
  • scaling
  • corrosion salts

Frage 11

Frage
combustion unit inspections and maintenance includes 1. cleaning 2. ignition checks 3. adjusting fuel flows 4. igniters and retraction gear tested
Antworten
  • 1,2
  • 2,3,4
  • 1,2,4
  • 1,2,3
  • 1,2,3,4

Frage 12

Frage
The lubrication system on a gas turbine for be checked for: 1. leaks 2. water 3. dirt 4. metal particles
Antworten
  • 1,2
  • 2,3,4
  • 1,2,4
  • 1,2,3
  • 1,2,3,4
Zusammenfassung anzeigen Zusammenfassung ausblenden

ähnlicher Inhalt

Können Sie die Flosse der Airline zuordnen?
B G
Genetik Quiz
Laura Overhoff
1 Grundlagen der Finanzbuchhaltung
Ella Wandao
Fahrtheorie
malimi something
Quiz zum Basiswissen Europa und Europäische Union
lea_seelbach
13. Altklausuren - Allgemeinwissen Makro
Rafael Mentges
Vetie Immunologie Altfragen
Rebecca Bindewald
Chirurgie Kleintiere Vetie
Anne Käfer
Basiswissen Management Sozialer Dienstleistungen - Dienstleistungscharakteristika
Bernd Leisen
Vetie Reprospaß2
Tropsi B
Vetie - Lebensmittel 2016
Kim Langner